, <br /> 3.8 PLACING ADJUSTING RINGS <br /> A. Full bed Mortar is required between rings and between rings/structure and rings/castings. <br /> Smooth the interior of the rings inside the manhole to provide a smooth surface <br /> approximately 1/2"thick.Provide a"bulb"of concrete outside the rings to maintain a <br /> minimum of 4" of concrete cover. <br /> B. Sealant option: In lieu of mortar sealant noted above the contractor may use a silicone <br /> adhesive,with prior submittals and approvals <br /> 3.9 FLARED END SECTIONS <br /> A. The last three joints of RCP piping shall use two tie bolt fasteners per joint,installed at 60 <br /> degrees from top center of pipe. <br /> B. Place flared end section as detailed. <br /> 3.10 RIP-RAP <br /> A. Subcut and place a type I geotextile over an approved subgrade. <br /> B. Place a 12" layer of filter blanket material over the geotextile. <br /> C. Hand place Rip-rap over the filter blanket material to the depths and dimensions detailed. <br /> 3.11 GENERAL PROCEDURES <br /> A. Clean all sewers of silt,debris,and other foreign matter prior to requesting substantial <br /> completion site observations. <br /> B. Protection: All surface or underground features or structures that are intended to remain <br /> shall be properly protected. If damage occurs immediately notify the A/E office. All costs <br /> associated with repair and replacement of structures damaged by construction shall be the <br /> responsibility of the contractor. <br />• 3.12 TESTS <br /> A. All work shall be inspected,tested and approved in accordance with all state and local <br /> regulations. Provide the General contractor and A/E office with a detailed schedule of <br /> utility work for the purpose of scheduling observations. <br /> B. Sewer lines (PVC pipe only)shall be tested for sectional integrity and deflection. A rigid <br /> ball or mandrel shall be pulled through the line. The outside diameter of the ball,or <br /> mandrel, shall be no less than the 95%of the inside diameter of the pipe being tested. <br /> ADDENDUM#1 <br /> 1607.001 -ORONO ICE ARENA(CP-2) Page 02720 -6 <br />