Laserfiche WebLink
DIVISION 1 <br /> GENERAL REQUIREMENTS <br /> 01041 -SCHEDULES <br /> D. The Contractor and Subcontractor shall provide their own data to the <br /> Construction Manager reflecting the actual plan of operation for the Project. <br /> Schedule input data shall include a comprehensive list of all activities of the <br /> construction phase of the project, including submittals (shop drawings, <br /> samples, product data), procurement of material, and on-site activity(erection, <br /> installation, construction). Activities for procurement of materials shall be <br /> included to delineate between material purchasing and fabrication/delivery. <br /> E. The Contractor shall assigndurations and sequencing to each activity. <br /> �1 g tY <br /> Submittal activities shall be listed with the anticipated date of submittal. <br /> Procurement activities shall be listed with the duration required for fabrication r <br /> and delivery from date of purchase. The Construction Manager shall <br /> computerize a PDM network using input data supplied by the Contractor. The <br /> Construction Manager will meet with the Contractor to revise and expand the <br /> Schedule and resolve conflicts. The revised schedule shall conform to the <br /> specific plan of operation envisioned by the Contractor. <br /> The Construction Manager will guide the Contractor in determining the level <br /> of detail to be included in the PDM Networks. The schedule shall be adequate <br /> enough to evaluate progress, cost of work in place and serve as a control <br /> technique for the Contractor's Field Superintendent. <br /> F. The Contractor and all subcontractors shall be obligated to perform in <br /> accordance with the Construction Schedule and to participate in updating the <br /> schedule. The Contractor shall include provisions in all subcontracts binding <br /> Subcontractors to participate in revisions of the schedule as are necessary, and <br /> to supply data throughout the project. <br /> G. Upon request, the Contractor shall submit to the Construction Manager <br /> purchase orders and subcontracts. Such information shall be submitted as <br /> soon as available so the Construction Manager will be aware of the progress <br /> being made by the Contractor in the placing of orders and the status of <br /> material. The Contractor shall be solely responsible for expediting the <br /> delivery of all material furnished by him and coordinating his subcontractors <br /> so construction progress shall be maintained according to Contract Schedule. <br /> 5. COMPLIANCE WITH THE CONSTRUCTION SCHEDULE <br /> A. If the Contractors shall fail to adhere to the Construction Schedule or to the <br /> said schedule as revised, he must promptly adopt such other or additional <br /> means and methods of construction as will make up for the time lost and will <br /> assure completion of the work in accordance with said Construction Schedule <br /> EXISTING ORONO MIDDLE SCHOOL-NEW MEDIA CENTER SECTION 01041 -2 <br /> BID PACKAGE 1: GENERAL CONSTRUCTION, MECHANICAL&ELECTRICAL <br />