Laserfiche WebLink
DIVISION 0 <br /> CONDITIONS OF THE CONTRACT <br /> 00800 -SUPPLEMENTARY <br /> CONDITIONS <br /> 15.3 Periodic Payment Estimate <br /> 15.3.1 When required by the Owner to establish a schedule of money available to make <br /> payment of periodic Applications for Payment, the Contractor shall provide an <br /> estimate by months, of the anticipated amounts for each periodic payment. The <br /> retained percentage shall be considered in the estimate schedule, as well as <br /> anticipated job progress and materials delivery. The schedule will be deemed an <br /> estimate only, for financial planning purposes, and the Contractor shall not be <br /> bound to conform to the schedule. The schedule may be required by the <br /> Contract Documents or requested by the Owner after Contract execution. <br /> 15.4 Layout of the Work <br /> 15.4.1 Each Contractor shall employ a qualified engineer or registered surveyor to <br /> stake out and locate the construction, locate property markers and other points <br /> as needed to properly locate the Work under this Contract. <br /> 15.4.2 The Contractor shall recognize that the drawings necessarily are diagrammatic, <br /> in many instances. All work and in particular, exposed piping, ducts, conduit <br /> and similar items shall be neatly and carefully laid out to provide the most <br /> useful space utilization and the most orderly appearance. Except as otherwise <br /> indicated or directed, piping and similar work shall be installed as close to <br /> ceilings and walls as conditions permit, located to prevent interference with <br /> other work or with the use of the spaces in the manner required by the functions <br /> of the room and the Owner. Valves shall be located in inconspicuous but <br /> accessible places. Before proceeding with any work, particularly where <br /> exposed, the Contractor shall carefully plan the layout and review it with the. <br /> Architect and Construction Manager for acceptability of location. <br /> 15.4.4 The Contractor shall verify grades, lines -levels and dimensions shown on <br /> drawings and report any errors or inconsistencies to Architect, through the <br /> Construction Manager for decision before commencing work. The Contractor <br /> and Subcontractor shall be responsible for the correct location, dimensions and <br /> elevations of his Work. As the Work progresses, the Contractor shall be <br /> responsible for the layout of the exact location of all partitions and similar <br /> features, as guide to all trades. <br /> 15.5 General Quality of Work, Installation and Operation <br /> 15.5.1 All of the Work shall be strictly first quality, in materials, erection, installation <br /> and workmanship. <br /> EXISTING ORONO MIDDLE SCHOOL-NEW MEDIA CENTER SECTION 00800-25 <br /> BID PACKAGE 1: GENERAL CONSTRUCTION,MECHANICAL&ELECTRICAL <br />