j If the Contractor claims that additional cost is involved because of but not <br />limited to (1) any written interpretation of the engineer, (2) any order by <br />the Owner to stop the Work where the Contractor was not at fault, (3) any <br />i written order for a minor change in the Work or ( ) failure of payment by the <br />Owner, Contrac' shall make such claim as provided in this Subparagraph. <br />10.7 WORK DIIRINr AN EMERGENCY <br />10.7.1 In any emergency affecting the Lafety of persons or property, the Con- <br />tractor shall act to prevent threatened damage, injury or loss. In all cases <br />j.. he shall, as soon as practicable, notify the Owner of the emergency and he <br />shall not wai.t for the instructions before proceeding to protect both life and <br />property. <br />10.7.2 Any additional compensation or extension of time claimed by the Con- <br />`ractor on account of Fs d emergency work shall be determined under Paragraph <br />* 0.6. <br />SECTION 11 <br />CHANGE OF CONTRACT PRICE AND CONTRACT TIME <br />ll.l ( NTRACT PRICE <br />The Contract Price constitutes the total compensation (subject to authorized <br />adjustments) payable to Contractor for performing the Work. All duties, re- <br />sponsibilities and obligations assigned to or undertaken by Contractor ehall <br />be at his expense without change in the Contract Price. <br />is • 11.2 CHANGE IN CONTRACT CE <br />H.' . Except where unit prices form the basis for payment under the Contract <br />Documents, the Contract Price may only be changed by a Chen Order. Any <br />claim for an increase in the Contract Price shall be based tten notice <br />►+ delivered to Owner and Engineer within ten (10) days of the nce of the <br />event giving rise to the claim. Notice of *he amount of the .m with sup- <br />1porting data shall he delivered within thirty (30) days of such occurrence un- <br />less Engineer allows an additional period of time to ascertain accurate cost <br />data. All claims for adjustment in the Contract i'rice shall be determined by <br />Engineer if Owner and Contractor cannot otherwise agree on the amount in- <br />volved. Any change in the Contract Price resulting from any such claim shall <br />be incorporated in a Change Order. <br />)t Where unit prices form the basis of payment and the quantity of any <br />�t t Work aq given in the Proponal is increased or decreased, payment for <br />tom will he made on the basis of actual quantit. -1leted, at the <br />c. .La unit price for such item. <br />r 11.3 BASIS nF CHANGE <br />The method of determining the cost or credit to the Owner resulting from a <br />r change in the work shall be determined and mutually agreed upon by Owner and <br />- Ll - <br />l/AS - NSO7h <br />ropyripht 1495 <br />Ronvvtron, Rnseno, Anivrl.k <br />4 AsnoLiates, Inc. <br />