Laserfiche WebLink
4.0 FACILITY DESCRIPTION AND ROUTE SELECTION RATIONALE <br />4.1 Transmission Line Description <br />The Project involves replacing the existing 69-13.8 kV Orono Substation (a distribution substation) <br />with a 115-13.8 kV transmission substation and constructing approximately 1,095 feet of single <br />circuit and approximately 2,041 feet of double circuit 115 kV overhead transmission line. The <br />proposed transmission line will originate at the proposed new Orono Substation. See Figure 2. <br />At the point the Proposed Route exits the planned substation replacement area, it extends <br />approximately 866 feet northwesterly and north within the 16 -acre substation site and along Xcel <br />Energy's western property line to south of the BNSF railroad right-of-way. At this point the <br />Proposed Route extends westerly across HFA property and paralleling the BNSF railroad right-of- <br />way approximately 1,205 feet where it will connect to a new transmission structure (to be designated <br />Structure 076-1) that will replace existing Structure 077 on Line 0831. Existing Structure 077 will be <br />removed from its current location on private residential property and moved to a new location on <br />HFA property. See Figure 2. <br />From this point, the Proposed Route continues approximately 590 feet northwesterly and parallel to <br />the BNSF railroad right-of-way across HFA land to a new transmission structure (to be called <br />Structure 077). The Proposed Route then bears southwesterly across HFA land, a water crossing <br />and a wetland to existing Structure 078 where it will terminate. Transmission Structure 078 will be <br />replaced with a new structure, but it will continue to be called Structure 078 on Line 0831. See <br />Figure 2. <br />After exiting Xcel Energy property, the Proposed Route for the transmission line crosses <br />undeveloped land within the HFA for approximately 2,270 feet. Under the City of Orono Zoning <br />Regulations, HFA land is designation "Outlot A" Common Area and is Zoned PRD (Planned <br />Residential Development). The Proposed Route will only traverse approximately 2,270 feet of HFA <br />land and will primarily parallel the existing BNSF right-of-way before terminating at existing Xcel <br />Energy transmission Structure 078. A detailed description of the Proposed Route is provided in <br />Table 4. Figure 2 provides an overview of the Proposed Route and Appendix B, Figure B-2 <br />provides an additional detailed map of the proposed Project. <br />The entire proposed new 115 kV transmission line will be constructed with single -pole, galvanized <br />steel or weathering -steel structures with davit arms or braced posts on drilled pier foundations. The <br />Project's proposed transmission line will create a loop connecting the new Orono Substation and <br />Xcel Energy's Gleason Lake and Crow River Substations via transmission Line 0831. The Gleason <br />Lake Substation is located approximately 6.1 miles east of the Orono Substation, and the Crow <br />River Substation is located approximately 9.5 miles northwest of the Orono Substation. <br />The Proposed Route is within or adjacent to the existing rights-of-way of highways, railroads and <br />Xcel Energy property for approximately 2,661 feet of the length of the route or 84 percent. The <br />remaining 475 feet of the route crosses an undeveloped area of HFA property. Overall the Project <br />crosses Xcel Energy property and undeveloped HFA land for 100 percent of the Proposed Route. <br />Orono Project June 7, 2011 <br />MPUC Docket No. E002/TL-11-223 12 <br />