Laserfiche WebLink
� City of Orono, Minnesota Page 18 <br /> August 14, 1979 <br /> Page 2 � � <br /> The Contractor proceeded to install the pipe on centerline using a box in <br /> a 7 ft. wide trench. As of August 6, the pipe had been laid from Tanager <br /> Bridge (station 28+42) to County Road 51 (station 76+55) and the <br /> Contractor was starting to lay pipe from Tanager Bridge northward at <br /> station 25+64 (just north of Tanager Bridge) . <br /> 4 � <br /> On August 6, 1979 , the Hennepin County Sheriff stopped Johnson Bros. <br /> from laying any more pipe north of Tanager Bridge. Hennepin County <br /> Highway Department officials informed the MWCC Construction Depart- <br /> ment and Johnson Bms. that work was stopped because the Contractor did <br /> not have an acceptable pavement restoration procedure and restoration <br /> schedule for that part south of Tanager Bridge to County Road 51. <br /> On August 9 , the MWCC, Consulting Engineers, Johnson Bms. , and <br /> Hennepin County Officials met and agreed on a procedure for additional <br /> bituminous pavement and concrete pavement removal under Hennepin <br /> County permit number 7020, which is part of the contract documents. <br /> As of this date, August 13, the Contractor has commence3 pavement <br /> restoration starting at County Road S1 and working northward on County <br /> Road 15. The Contractor informed me on June 13th that Johnson Bros. will <br /> work 10 hour days and will work Saturdays on pavement restoration on <br /> this project. <br /> I have enclosed , for your information, the latest construction schedule <br /> that I received 8/13 fmm Johnson Bros . You will note that Johnson <br /> Bros. shows work starting on Orono Orcha rd Rd . (LL 0+00 to LL 71+45) <br /> about one week before the pavement is restored and open to traffic on <br /> County Road 15 (OR 25+70 to OR 0+00) . Johnson Bros. knows that the <br /> City of Orono wants County Road 15 open to traffic before work starts on <br /> Orono Orchard Road arxi they are hopeful that the restoration can be <br /> completed and County Road 15 open to traffic by about September 24th <br /> which will eliminate this overlapping. <br /> If you have any questions, please call me at 222-8423. <br /> Very truly yours, ` <br /> �--� 1 - v ' � <br /> R. O. Folland <br /> Director of Constniction <br /> Metropolitan Waste Control Commission <br /> ROF:AM <br /> Encl. <br /> CC: Herbert Klossner, Skip McCombs, William Moeller, j. W. Bain3 , <br /> Johnson Brns. , D. Ca ster <br />