7.9.4 If any Work that is to be inspected, tested or approved is covered <br />without written concurrence of Engineer, it must, if requested by <br />Engineer, be uncovered for observation. Such uncovering shall be at <br />Contractor's expense unless Contractor has given Engineer timely notice of <br />Contractor's intention to cover such Work and Engineer has not acted with <br />reasonable promptness in response to such notice. <br />7.9.5 Neither observations by Engineer nor inspections, tests or <br />approvals by others shall relieve Contractor from his obligations to <br />perform the Work in accordance with the Contract Documents. <br />7.10 UNCOVERING WORK <br />If any Work is covered contrary to the written request of Engineer, it must, <br />if requested by Engineer, be uncovered for Engineer's observation and replaced <br />at Contractor's expense. If Engineer considers it necessary or advisable that <br />covered Work be observed by Engineer or inspected or tested by others, <br />Contractor, at Engineer's request, shall uncover., expose or otherwise make <br />available for observation, inspection or testing as Engineer may required, <br />that portion of the Work in question, furnishing all necessary labor, material <br />and equipment. If it is found that such Work is defective, Contractor shall <br />bear all `he expenses of such uncovering, exposure, observation, inspection <br />and testing and of satisfactory reconstruction, including compensation for <br />additional professional services, and an appropriate deductive Change ,)rder <br />shall be issued. If, however, such Work is not found to be defective, <br />Contractor shall be allowed an increase in the Contract Price or an extension <br />of the Contract Time, or both, directly attributable to such uncovering, <br />exposure, observation, inspection, testing and reconstruction if he makes a <br />claim therefor as provided herein. <br />7.11 OWNER MAY STOP THE WORK <br />if the Work is defective, or Contractor fails to supply sufficient skilled <br />Workmen or suitable materials or equipment, Owner may order Contractor to stop <br />the Work, or any portion thereof, until the cause for such order has been <br />eliminated; however, this right of Owner to stop the bock shall not give rise <br />to any duty on the part of Owner to exercise this right for the benefit of <br />Contractor or any other party. <br />7.12 CORRECTION OR REMOVAL OF UFFYCTIVE WORK <br />If required by Engineer, Contractor shall promptly, without cost to Owner and <br />as specified by Engineer, either correct any defective Work, whether or not <br />fabricated, installed or completed, or, if the Work has been rejected by <br />Engineer, remove it from the site and replace it with nondefective Murk. <br />7.13 ONE YEAR CORRECTION PERIOD <br />If within one year after the date of Substantial Completion or such longer <br />period of time as may be pre s r ibed by law or by the terms of any applicable <br />special guarantee required by the Contract I),cuments or by any specific pro- <br />357ha <br />4/81 <br />Q U , <br />