4 <br />or <br />prepare and deliver to OWNER a tentative certificate of Sub- <br />stantial Completion which shall fir the date of Substantial <br />Completion. There shall be attached to the certificate a tenta- <br />tive list of items to be completed or corrected before final pay- <br />ment. OW NER shall have seven days after receipt of tht ten- <br />tative certificate during which he may make written objection <br />to ENGINEER as to an+ provisions of the certificate or <br />attached list. If, after considering such objections, ENGI- <br />NEER conc!ud that the Work is not substantially complete. <br />ENGINEER w othin fourteen days after submission of the <br />tentative certifivate to OWNER notify CONTRACTOR in <br />writing, stating his reasons therefor. If, after consideration of <br />OW'NER's objections, ENGINEER considers the Work sub- <br />stantially complete, ENGINEER will withir said fourteen <br />days execute and deliver to OWNER and CONTRACTOR a <br />definitive certificate of Substantial Completion (with a revised <br />tentative list of items to be completed or corrected) reflecting <br />such changes from the tentative certificate as he believes justi- <br />fied after consideration of any objections from OWNER At <br />the time of delivery of the tentative certificate of Substantial <br />Completion ENGINEER will deliver to OWNER and CON- <br />TRACTOR a written recommendation as to division of re- <br />sponsibilities pending final payment between OWNER and <br />CONTRACTOR with respect to security, operation, safety. <br />maintenance, heat, utilities and insuram e. Unless OWNER <br />and CONTRACTOR agree otherwise in writing and so in- <br />form ENGINEER pr,: r to his issuing he definitive .ertificate <br />of Substantial Completion ENGINEER's aforesaid recom- <br />mendation will be binding on OWNER and CONTRACTOR <br />until fiial payment. <br />14 9. OWNER shall have the right to exclude CON- <br />TRACTOR from the Work after the date of Substantial Com- <br />pletion, but OWNER shall allow CONTRACTOR reasonable <br />-access to complete or correct items on the tentative list <br />Partial Utilization <br />14.10. Use by OWNER of completed portions of the <br />Work may be accomplished prior to Substantial Completion <br />of all the Work subject to the following: <br />14.10.1. OWNER at any time may request CON- <br />TRACTOR in writing to permit O*XNER to use any part <br />of the Work which OWNER believes to be substantially <br />complete and which may be so used without significant <br />interference with construction of the other parts of th <br />Work. If CONTRACTOR agrees, CONTRACTOR wii, <br />certify to OWNER and ENGINEER that said part of the <br />Work is substantially complete and request ENGINEER to <br />issue a certificate of Substantial Completion for that part <br />of the Work Within a reasonable time thereafter <br />OWNER. CONTRACTOR and ENGIN hall make <br />an inspection of that part of the Work Tune its <br />status A completion. If ENGINEER coder <br />that part of the work to be substantially umpiete. EN <br />GINEER will notify OWNER and CONTRACTOR in <br />writing gising his reasons therefor If ENGINEER con- <br />siders thi..' part of the Work to be substantially complete. <br />ENGINEER will execute and deliver to OWNER and <br />CONTRACTOR i certificate to that effect, fixing the date <br />of Substantial Completion as :o that part of the Work, <br />attaching thereto a tentative list of items to be _ompleted <br />or corrected before final payment Prior to issuing a cer!i- <br />ficate of Substantial Completion as to part of the Work <br />ENGINEER will deliver to OWNER and CONTRACTOR <br />a written recommendation as to the division of responsi- <br />bilities pending final payment between OWNER and CON- <br />TRACTOR with respect to security, operation. safety, <br />maintenance, utilities and insurance for that part of the <br />Work which shall become binding upon OWNER and <br />CONTRACTOR at the time of issuing the deffnitne _er- <br />nficate of Substantial Completion as to that part of the <br />Work unless OWNER and CONTRACTOR shall have <br />otherwise agreed in writing and so informed ENGINEER. <br />OWNER shall have the right to exclude CONTRACTOR <br />from any part of the Work which ENGINEER has so certi- <br />fied to be substantially complete, but OWNER shall allow <br />CONTRACTOR reasonable access to complete or correct <br />items on the tentative list <br />14.10.: In lieu of the issuance of a certificate of Sub- <br />stantial Completion as to part of the Work. OWNER may <br />take over operation of a facility constituting part of the <br />Work whether or not it is substantia!ly complete if such <br />facility is functionally and separately useable: provided <br />:hat prior to any such takeover. OWNER and CONTRAC- <br />TOR have agreed as �o the division of responsibilities <br />between OW NER and CONTRACTOR for securits, oper- <br />ation, safer, maintenance. correction period, heat, utth- <br />ties and insurance with respect to such facility. <br />14.10.3. No occupancy of part of the Work or taking <br />over of operations of a facility will be accomplished prior <br />to compliance with the requirements of paragraph 5 14 in <br />respect of property insurance. <br />Final Inspecitoo. <br />14 11 l pon written notice from CON^RACTOR that <br />the Work is ;omplete. ENGINEER will make a final :nspec- <br />tion with OWNER and CONTRACTOR and will notify <br />CONTRACTOR -n writing of ail particulars to which this in- <br />spection reveals that the work is incomplete or defective. <br />LONTRACTOR shall immediately take such measures as are <br />necessary to remedy such deficiencies. <br />Final Appitcarron for Payment <br />14 12. -%tier CONTRACTOR has completed all such cor- <br />rections to the satisfaction of ENGINEER and Jelive-red all <br />maintenance and operating instructions, schedules, guaran- <br />tees. Bonds. certificates of inspection, marked -up record <br />documents and other documents —all as required by the Con- <br />tract Documents. and after ENGINEER has:noicatecl that the <br />Work is acceptable isubiect to the provisions of paragraph <br />14 161 CONTRACTOR max make application for 'trial pay- <br />ment following the procedure for progress payments The <br />final Application for Payment shall be accompanied by all <br />Jo:urrentation called 'or in he Contract Documents and such <br />other data and schedules as ENGINEER mas reasonably re - <br />Quire, together with comptete and 'egally effective releases ar <br />