<br /> <br />CHANGE ORDER NO.: 2 <br /> <br />Owner: City of Orono, MN Owner’s Project No.: <br />Engineer: Samuel A. Ellison Engineer’s Project No.: 0C1.126638 <br />Contractor: Geislinger & Sons Inc. Contractor’s Project No.: N/A <br />Project: 2022 CSAH 19 Watermain - Phase 1 <br />Contract Name: 2022 CSAH 19 Watermain – Phase 1 <br />Date Issued: 4/4/2023 Effective Date of Change Order: 4/4/2023 <br />The Contract is modified as follows upon execution of this Change Order: <br /> Sod, Lawn Type – During construction it was identified that the location and depth of the existing <br />watermain would require modifications to the limits and location of excavation areas. Due to these <br />modifications, additional turf restoration was required to sufficiently restore the corridor. The <br />Engineer has determined that the contractor is owed additional compensation for the additional turf <br />establishment work. The additional costs will be paid at the bid unit price for the Sod, Type Lawn <br />bid item in the amount identified below. <br />Detailed Cost Breakdown: <br />ITEM <br />NO. ITEM UNIT <br />UNIT <br />PRICE <br />EST. <br />QUANTITY Total <br />49 SOD, TYPE LAWN SQ YD $8.00 +742 +$5,936.00 <br /> Total +$5,936.00 <br />Attachments: <br /> N/A <br />Change in Contract Price Change in Contract Times <br />Original Contract Price: Original Contract Times: <br /> Substantial Completion: 10/31/2022 <br />$ 901,016.00 Ready for final payment: 11/25/2022 <br /> Increase from previously approved Change Orders No. 1 to <br />No. 2 <br />Increase from previously approved Change Orders No.1 <br />to No. N/A: <br /> Substantial Completion: N/A <br />$ 73,919.36 Ready for final payment: N/A <br /> Contract Price prior to this Change Order: Contract Times prior to this Change Order: <br /> Substantial Completion: 10/31/2022 <br />$ 974,935.36 Ready for final payment: 11/25/2022 <br /> Increase this Change Order: Increase this Change Order: <br /> Substantial Completion: N/A <br />$ 5,936.00 Ready for final payment: N/A <br /> Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: <br /> Substantial Completion: 10/31/2022 <br />$ 980,871.36 Ready for final payment: 11/25/2022 <br /> Recommended by Engineer Accepted by Contractor <br />By: <br />Title: Project Engineer Vice President <br />Date: <br /> Authorized by Owner Approved by Funding Agency (if applicable) <br />By: N/A