Laserfiche WebLink
Site Plan Application #LA18-000036 <br />2745 Kelley Parkway <br />Page 2 <br />H:\ORNO\C13115486\z-LA18-0000.3_2745 Kelley Parkway\2745KelleyPkwy-1_2018-04-09.docx <br /> <br />requirements, and a detail should be included accordingly. <br />12.Pedestrian ramps must be provided on the sidewalk adjacent to Kelley Parkway at the <br />connections to the driveway entrances and on the accessible routes to the building, and a detail <br />should be included accordingly. <br />13.Once the sanitary sewer stub is exposed and location, size, and elevation are field verified, <br />layout and design of service connection must be submitted to City for review and approval <br />prior to construction. <br />14.In order to limit potential for sewer blockages, a grinder pump should be included prior to <br />connection to public sanitary sewer. <br />15.The final location of fire hydrants, valves, and fire connections must be reviewed by the Fire <br />Chief. <br />16.Due to heavy soils in the area, the applicant should consider installing finger drains at low point <br />inlets, and a detail should be included accordingly. <br />17.Pretreatment of runoff should be provided at the curb cut to the Area 3 rain garden. A Rain <br />Guardian or similar device should be considered for this location. <br />18.Additional information should be provided for the proposed draintile to adequately define pipe <br />characteristics (i.e. invert elevation, diameter, material, slope, etc.), and a detail should be <br />provided to depict the typical section. <br />19.Additional information should be provided to adequately define rain garden construction. A <br />detail should be included to define the typical section, and sequencing notes should be included <br />to define installation procedures and schedule. <br />20.The trunk storm sewer on the south side of the parcel should be indicated on the plans. <br />21.The rain gardens should be revised as follows: <br />a.The inlet east of Area 3 rain garden should be relocated to inside the basin 0.75’ above the <br />basin bottom. <br />b.Catchbasin inlets should be installed for Area 4 and 5 rain gardens to provide the primary <br />outlet. Inlets should be located 0.75’ above basin bottom and connected to the trunk storm <br />sewer line on the south side of the property. <br />c.Surface overflows should be provided for the rain gardens at the 100 year high water level. <br />22.A Landscape Plan should be submitted to verify adequate restoration and plantings are <br />provided. The final locations of trees should be coordinated to avoid conflict with utilities, and <br />native vegetation should be considered for the rain garden areas. <br />23.The Contractor should be required to submit a Site Management Plan prior to work. The plan <br />should outline concrete management, work that will require dewatering, and any other work <br />requiring protective measures to minimize potential for negative environmental impact. <br />24.The Contractor should be required to submit a Traffic Control Plan prior to work. <br />25.The applicant will be required to obtain Minnehaha Creek Watershed District (MCWD) <br />approval and permitting. A copy of any approvals or permits required should be submitted <br />conditional to Final approval. <br />26.The applicant will be required to obtain a General Construction Permit (NPDES) to discharge <br />stormwater associated with construction activity since more than 1 acre will be disturbed. A <br />copy of the permit should be submitted prior to any land disturbing activity. <br />27.The applicant will be required to submit a Maintenance Agreement for all stormwater <br />management structures and facilities. The agreement should define maintenance <br />responsibilities following completion of project, specify types and frequencies of inspection <br />and maintenance activities, and designate who will conduct inspection and maintenance <br />activities. <br />28.Record drawings must be submitted upon completion of the project.