1 <br /> 1 <br /> 4 PERMIT CONDITIONS <br /> 1 The Permittee shall comply with the following conditions during construction of the transmission <br /> line and associated facilities and the life of this permit. <br /> 4.1 Plan and Profile <br /> At least 30 calendar days before right-of-way preparation for construction begins on any segment <br /> or portion of the project,the Permittee shall provide the Commission with a Plan and Profile of <br /> the right-of-way and the specifications and drawings for right-of-way preparation, construction, <br /> transmission structure specifications and locations, and restoration for the transmission line. The <br /> 1 documentation shall include maps depicting the plan and profile including the right-of-way, <br /> alignment, and structures in relation to the route and alignme .approved per the permit. <br /> The Permittee may not commence construction until the ;d. ° has -xpired or until the <br /> ' Commission has advised the Permittee in writing that it has • p ,"`'fid its review of the <br /> documents and determined that the planned const 'on is co ent with this permit. If the <br /> Permittee intend to make any significant changes in it an d Profile or the specifications and <br /> drawings after submission to the Commission',the Permi shall notify the Commission at least <br /> five days before implementing the changes. No changes shall be made that would be in violation <br /> of any of the terms of this permit. <br /> 4.2 Construction Practices <br /> ' The Permittee shall follow those specific construction practices an aterial specifications <br /> described in the Great Ri r Energy Application t the; ommis ion for a Route Permit, dated <br /> February 26, 2010, and a •escribed in the envirom�nta s sment and Findings of Fact, <br /> i <br /> unless this permit es e •itferent requ .• r 'vh` case this permit shall prevail. <br /> 4.2.1 F'iel Rep.Tentative <br /> At least •ay . for to commencing co truction,the Permittee shall advise the <br /> Commissio ;"""'writing of the person or.::persons designated to be the field representative <br /> for the Permittee with the responsibility to oversee compliance with the conditions of this <br /> permit during construction. <br /> The field representative's address,phone number, email,and emergency phone number <br /> ' shall be provided to the Commission and shall be made available to affected landowners, <br /> residents,public officials and other interested persons. The Permittee may change the <br /> field representative at any time upon written notice to the Commission. <br /> 1 <br /> 1 <br /> 1 <br /> November 2010 Page 19 <br /> I <br />