Laserfiche WebLink
8.0 AGENCY INVOLVEMENT, PUBLIC PARTICIPATION,AND REQUIRED <br /> PERMITS AND APPROVALS <br /> ' 8.1 Agency Contacts and Response <br /> ' 8.1.1 Notice to Local Government Units <br /> Xcel Energy provided a notification letter to the City of Orono, the LGU for the Project on January <br /> 10, 2011. See Appendix C.2. This letter indicated that Xcel Energy intended to apply for a Route <br /> Permit for the proposed Project from the Commission. The notification letter to the LGU complies <br /> with the notice requirements of Minn. Stat. § 216E.03, subd. 3a. Xcel Energy has not to date <br /> received response regarding the Project from the City of Orono after this notification. <br /> ' As discussed in Section 4.2.2,Xcel Energy initially sought local review of the proposed Project from <br /> the City. The City subsequently voted to refer review and permitting of the routing and siting of the <br /> ' Project to the Commission pursuant to Minn. Stat. 216E.05, subd. 1(b), and MN Rule 7850.5300 <br /> subp. 4 (see Appendix C, C.3). Xcel Energy then initiated the State permitting process for the Project. <br /> Xcel Energy has had an opportunity to meet with the City and other LGUs during meetings <br /> conducted in June and August 2010. These meetings are discussed further in Section 8.3. <br /> 8.1.2 Notice to Other Agencies and Interested Parties <br /> ' Xcel Energy also provided notice of the Project and requested comments in a letter on January 10, <br /> 2011, to several non-LGU, agencies and interested parties associated with the Project. The purpose <br /> of the letter was to provide notice of Xcel Energy's plan to obtain a Route Permit from the <br /> Commission and request for comments on the proposed Project. See Appendix C.2 for the non- <br /> LGU mailing list and a copy of this letter. <br /> ' 8.1.3 Natural Resource Conservation Service <br /> In a letter dated January 20, 2011, the NRCS Environmental Review and Justice Program indicated <br /> that since the Project sponsors are not USDA program benefit recipients the wetland conservation <br /> provisions of the 1985 Food Security act are not applicable to the Project(see Appendix C.4) <br /> ' 8.1.4 United States Fish and Wildlife Service <br /> In an email dated February 8, 2011, the USFWS indicated that no Federally listed or proposed <br /> species and /or designated or proposed critical habitat is present within the action area of the <br /> proposed Project. The USFWS did recommend that given the proximity to the Baker Park Reserve <br /> and the crossing of the wetland between the proposed Orono Substation replacement and the BNSF <br /> ' railroad right-of-way that bird flight diverters be installed on the shield wire of the proposed <br /> transmission line crossing this wetland. Additionally, the USFWS did recommend that if any <br /> maintenance work were to take place on the existing transmission Line 0831 within the Baker Park <br /> ' Reserve that bird flight diverters also be placed on the shield wire of the transmission line for the <br /> portion that crosses the Baker Park Reserve. (See Appendix C.5). <br /> ' Orono Project June 7,2011 <br /> MPUC Docket No. E002/TL-11-223 65 <br />