I <br /> I <br /> Ito be acquired where the Proposed Route turns southwest at the western edge of the Project near <br /> the terminations point at existing Xcel Structure 078 of transmission Line 0831. <br /> I <br /> 5.1.3 Right-of-Way Evaluation and Acquisition <br /> Where the Project is expected to use existing rights-of-way, the right-of-way agent will evaluate all <br /> I existing easements. If the terms of the existing easement are sufficient and no new right-of-way is <br /> needed,the right-of-way agent will continue towork with the landowner to address any construction <br /> needs, access,impacts, damages, or restoration issues. To the extent new right-of-way acquisition is <br /> necessary, the right-of-way agent will work with landowners to determine how to expand or modify <br /> I <br /> existing easements. The current status of this evaluation is further discussed in Sections 8.1 to 8.3 of <br /> this Application. <br /> For those segments of the Project where new right-of-way will be necessary, the acquisition process <br /> begins early in the detailed design phase. For transmission lines, utilities acquire easement rights <br /> across certain parcels to accommodate the facilities. The evaluation and acquisition process includes <br /> I <br /> title examination,initial owner contacts,survey work,document preparation,and purchase. Each of <br /> these activities, particularly as it applies to easements for transmission line facilities, is described in <br /> more detail below. <br /> IThe first step in the right-of-way process is to identify all persons and entities that may have a legal <br /> interest in the real estate upon which the facilities will be built. To compile this list, a right-of-way <br /> I agent or other persons engaged by the utility will complete a public records search of all land <br /> involved in the Project. A title report is then developed for each parcel to determine the legal <br /> description of the property and the owner(s) of record of the property, and to gather information <br /> regarding easements,liens,restriction,encumbrances,and other conditions of record. <br /> IAfter owners are identified, a right-of-way representative contacts each property owner or the <br /> property owner's representative. The right-of-way agent describes the need for the transmission <br /> I facilities and how the Project may affect each parcel. The right-of-way agent also seeks information <br /> from the landowner about any specific construction concerns. <br /> I The next step in the acquisition process is evaluation of the specific parcel. For this work,the right- <br /> of-way agent may request permission from the owner for survey crews to enter the property to <br /> conduct preliminary survey work. Permission may also be requested to take soil borings to assess <br /> I the soil conditions and determine appropriate foundation design. Surveys are conducted to locate <br /> the right-of-way corridors, natural features, man-made features, and associated elevations for use <br /> during the detailed engineering of the line. The soil analysis is performed by an experienced <br /> Igeotechnical testing laboratory. <br /> During the evaluation process, the location of the proposed transmission line or substation facility <br /> may be staked with permission of the property owner. This means that the survey crew locates each <br /> Istructure or pole on the ground and places a surveyor's stake to mark the structures or substation <br /> facility's anticipated location. By doing this, the right-of-way agent can show the landowner where <br /> the structure(s) will be located on the property. The right-of-way agent may also delineate the <br /> Iboundaries of the easement area required for safe operation of the line. <br /> Prior to the acquisition of easements or fee purchase of property, land value data will be collected. <br /> IBased on the impact of the easement or purchase to the market value of each parcel, a fair market <br /> I Orono Project June 7, 2011 <br /> MPUC Docket No. E002/TL-11-223 27 <br />