Enamel <br /> September 23,2010 <br /> Page 2 of 2 <br /> Project Description <br /> The existing Orono Substation has been in service since 1990 and is situated on land owned in fee by <br /> Xcel Energy. All proposed substation upgrade components will he located within existing Xcel Energy ' <br /> property. Xcel Energy also proposes to build a new transmission line to connect the Orono Substation to <br /> the existing 115kV Line 0831 located approximately 1/2 mile northwest of the Orono Substation. The <br /> new 115kV transmission line route will run north from the Orono Substation across Xcel.Energy , <br /> property for approximately 1/4 mile and then cross an additional'/mile of private property as shown on <br /> the attached map(see Figure 1). <br /> Local Governmental Unit <br /> The City of Orono(City)is the local governmental unit(LGU)for the Project. While the Project <br /> is required to be approved by the Minnesota Public Utilities Commission(PUC),the Project <br /> qualifies for local review. Xcel Energy is requesting local review and approval from the City via <br /> the CUP process. City staff has indicated they are willing to review and grant a CUP for the <br /> Project. ' <br /> On August 20,2010,Xcel Energy submitted a CUP application to the City for review and <br /> approval of the Project. On September 20,2010,the City Planning Commission met to discuss <br /> the Project,review EA requirements,and request public comment on the scope of the EA. The <br /> EA will be prepared over the next month and will be available for public review and comment in <br /> November. Should you have comments on the Project or scope of the EA, please provide them <br /> to me within 30 days at(612)330-6435,email at noseoh,a,sedarski(a7xcelenergy.com or the <br /> following address: <br /> Xcel Energy <br /> ATTN: Joe Sedarski,Senior Permitting Analyst <br /> 414 Nicol let Mall—MPS <br /> Minneapolis,MN 55401 <br /> Thank you for your assistance with this matter. <br /> Sincerely, <br /> XCEL ENERGY <br /> Joseph Sedarski <br /> Senior Permitting Analyst <br /> cc: Melanie Curtis, Planning&Zoning Coordinator,City of Orono-w/enc, <br /> Enc: Figure <br /> Fact Sheet <br /> Draft Table of Contents for Project Environmental Assessment <br />