SART 1 DIVISION 1 REQUIREMENTS
<br /> 1UIREMENTS
<br /> Nelson Orangery 9415.00
<br /> October 3, 1994 3
<br /> 2. The Contractor will protect the existing house from all damage resulting from the Work
<br /> including, but not limited to,plaster cracking,water damage, etc. and shall repair or
<br /> reimburse the Owner, at the Owner's option,for all damage.
<br /> 3. The General Contractor is responsible for verifying and relocating all existing utility lines
<br /> (electrical,plumbing,HVAC) in existing walls that are to be removed or relocated as a
<br /> result of the remodeling,whether or not they are indicated in the Contract Documents.
<br /> 4. The Contractor shall be responsible for correcting deviations from level, plumb, and
<br /> straightness in the existing framing in all areas where a new wall finish material is being
<br /> installed over existing framing(such as gypsum wallboard) and where this deviation is
<br /> visually apparent after the construction is complete. This is especially critical where new
<br /> cabinets,counters, miscellaneous millwork,tile,stone, and other finsh materials abut the
<br /> existing construction.
<br /> S. The Contractor shall not be responsible for correcting major deviations of the floors,walls,
<br /> or ceilings that are out of level or plumb that are not readily apparent during the bidding
<br /> inspection of the Contractor and that are not specifically called out in the Drawings.
<br /> (a) In areas of major demolition the Contractor shall take measurements to verify that
<br /> the structure is level,plumb, and straight.
<br /> (b) The Contractor shall notify the Architect of the existence of deviations so that
<br /> possible corrective actions may be taken prior to covering the Work.
<br /> B. EXTERIOR
<br /> 1. The Contractor shall submit to the Architect for approval a plan called the Designated
<br /> Construction Area showing areas of the existing property which will be required for
<br /> materials storage and construction operations. The Contractor is to erect a fence
<br /> completely around this designated area.
<br /> (a) Inside the Designated Construction Area:
<br /> (1) The Contractor shall repair, replace,or reimburse the Owner,at the
<br /> Owner's option,for all damage to any part of the this area including,but
<br /> not limited to,paving,walks,decks,sod,or shrubs. Landscape materials
<br /> to be replaced shall be with the appropriate material and size available for
<br /> purchase.
<br /> (b) Outside the Designated Construction Area:
<br /> (1) The Contractor shall repair, replace,or reimburse the Owner,at the
<br /> Owner's option,for all damage to all landscaping outside the designated
<br /> Construction area. Reimbursements shall be in amounts equal to the
<br /> estimated mature value of these landscaping items.
<br /> (2) The Contractor shall repair, replace,or reimburse the Owner,at the
<br /> Owner's option,for all damage to any part of this area including, but not
<br /> limited to, paving,walks,decks, buildings, etc.
<br /> 01700. SITE UTILITIES
<br /> A. The energy and use charges for all utilities that are extended from the Owner's existing services
<br /> shall be paid by the Owner. This includes gas, electricity, and telephone service.
<br /> B. All special purpose utilities required shall be installed and paid for by the Contractor.
<br /> C. The contractor shall provide an on-site phone for the duration of the construction project.