' <br /> Hennepin County Special Requirements Section 00800 - SUPPLEMENARY CONDITIONS <br /> ' 1/2/02 Edition <br /> Page 4 of 3Z <br /> , Delete Paragraph 3.9 and substitute the following: <br /> 3.9 PROJECT MANAGERAND SUPERINTENDENT <br /> ' 3.9.1 The Contractor shall employ a competent Project Manager who shall administer the <br /> Agreemerrt Between Owner and Contractor and who shall represent the Contractor. <br /> , Communications given to the Project Manager shall lx as binding as if given to the <br /> Contractor. Important communications shall be confirmed in writing. Other <br /> communications shall be similarly confirmed on written request in each case. <br /> , 3.9.2 The Contractor shall employ a competent superintendent and necessary assistants who shall be <br /> in attendance at the Project site during performance of the Work. The superintendent shall <br /> ' represent the Contractor,and commumcations given to the superintendent shall be as binding <br /> as if given to the Contractor. Important communications shall be confirmed in writing. Other <br /> communications shall be similady confirmed on written request in each case. <br /> ' 3.9.3 The Project Manager and the Superintendent shall be assigned to the Project throughout the <br /> term of the Contract except or unless the designa.ted individual's service to the Contractor is <br /> , terminated or the Owner finds reasonable objection to the individual in which case another <br /> individual shall be assigned to the same responsibility for the remaining term of the <br /> Contract. <br /> I3.10 CONTRACTOR'S CONSTRUCTION SCHEDULES <br /> , Add the following to Subparagraph 3.10.1: <br /> The contractor is requested to provide a Critical Path Method Construction Schedule. <br /> ' 3.11 DOCUMENTS AND SAMPLES AT THE SITE <br /> � Add the following to Paragraph 3.11: <br /> 3.11.2 The Architect will furnish one complete set of Drawings and Project Manual to the <br /> ' Contractor for the purposes of recording all changes in the Work. The Contractor sha11 <br /> preserve and maintain these documents at the site in good condition and shall promptly and <br /> , directly record all changes to the Work upon them. <br /> 3.11.3 The Architect shall mspect these Record Documents from time to time during the course of <br /> � the Work to ascertain their condition and that they reflect the current condition of the Work. <br /> 3.11.4 Upon Substantial Complerion of the Work and prior to Final Payment, the Contractor shall <br /> � return the Record Documents to the Architect for the Arclutect's translation of all changes in <br /> the Work in the Record Documents for delivery to the Owner. <br /> � Suppl Conds-4 <br /> ���C��TY Orono �lt toraee <br /> March 22,2002 Project No.: 0031569 Contract No.: 0751 R2 <br /> � <br />