Minutes of Meeting No. 1
Date: December 10, 1996
Project: Orono Ice Arena
Orono, Minnesota
Present: Orono Ice Arena, Inc.
Mark Engebretson
Kaare Birkeland
City of Orono
Lyle Oman ,DEC 2 .3 1996
Kraus-Anderson
Gary Benson
Rich Jacobson
Dick Lembke
Hammel, Green & Abrahamson
David Leschak
Ted Rozeboom Architects
Ted Rozeboom
Victor Pechaty
Doboszenski & Sons
Neil Grace
Scott Neumann
Metro Utilities
David Johnson
Date of
Origin Item # Description Action By
12/10/96 1.1 Earthwork: They are removing utility
excess material and working on the east
parking lot. They will then begin
working on pond. Doboszenski
12/10/96 1.2 Doboszenski suggested a 6" rock at east lot.
K/A decided to wait until spring to install.
12/10/96 1.3 Footings and building pad will begin in
two to three weeks. Doboszenski
12/10/96 1.4 Utilities: Substantially complete. Testing
to begin after City has hooked up their
utilities in the spring. Metro
12/10/96 1.5 Riprap in the pond will be installed when
the pond is complete. Metro
12/10/96 1.6 The hydrant was approved as submitted.
Minutes of Meeting No. 1 -2- Orono Ice Arena
Date of
Origin Item # Description Action By
12/10/96 1.7 Trench stabilization - K/A to review with
GME. K/A
12/10/96 1.8 Water line - Metro to review costs. Metro
12/10/96 1.9 Precast: Fabcon needs to try and match
Spancrete's sample. K/A to contact
Fabcon. K/A
12/10/96 1.10 Architect/Owner brought up a concern
regarding door frame issue. Fabcon
should supply connection jamb. Fabcon
12/10/96 1.11 Electrical: K/A gave alternate fixture
package from Premiere Electric to Dave
Leschak to review. HGA
12/10/96 1.12 Painting: K/A to get cost for labor only
from Swanson & Youngdale. K/A
12/10/96 1.13 Scheduling: K/A to work up a schedule
when it is determined who the precast
supplier will be. K/A
This report is assumed to be true and accurate account of this meeting unless notification to
the contrary is received within 72 hours.
Submitted by:
KRAUS-ANDERSON CONSTRUCTION COMPANY
MIDWEST DNISIO
Richard J.Jac on
Senior Project Manager
RJJ/ss
cc: All Present
All Listed in Action Column