Re: Dredging application for 3135 North Shore Drive
Dear Applicant:
Your application for a Minnehaha Creek Watershed District(MCWD) permit was received on
November 7,2005. The permit application is currently incomplete. Please refer to the information
requested below.
Permit applications that do not require a variance or exception to District Rules require a public
notice to all properties within 600 feet of the subject property, which includes a 14 day comment
period allowing members of the public to receive further information and/or request a public
hearing. When a public hearing is requested it will be scheduled on the first available Board
meeting after the application is determined by staff to be complete. The required public notice will
be mailed by MCWD the week of November 14, 2005. Following the completion of the public
process and the District's determination that the permit application is complete you will receive
written notice of conditional approvaL This notice will list the conditions of the approval that will
need to be complete prior to the permit being issued. Permit conditions include but are not limited
to the reimbursement of mailing cost, reimbursement of the cost of District staff time and
engineering services, and submittal of a declaration for the preservation of wetland buffers and/or
stormwater facility maintenance where applicable.
Please submit the following information:
Rule E: Dredging
The following Required e�chibits listed in paragraph 5 of Rule E must be submitted. They are as
follows:
• Site plan showing property lines, delineation ofthe work area, exising elevation contours
of the adjacent upland area, ordinary high water elevation, and regional flood elevation. All
must be reduced to NGVD(1929 datum)
• Site plan showing the proposed location of floating silt curtains
• Support data
o Description and volume computation of material to be removed
o Description of equipment to be used
o Construction schedule
o Location map of spoil containment area
o Erosion control plan for containment area
o Restoration plan for any proposed permanent on-site spoil containment site
showing final grades, removal of control structure, and description of how and
when the site will be restored, covered or revegetated after construction
o Details and specifications of floating silt curtian
t
As we review your submittals,we may find the need to request additional information,and will so
inform you. If you have any questions please call Renae Clark at(952)471-0590.