HomeMy WebLinkAboutnotes/ltrs re: permits, plans, etc Christine Mattson From: Miriam Eason <meason@minnehahacreek.org> Sent: Monday, November 09, 2015 3:14 PM To: Melanie Curtis; Christine Mattson Cc: jhsmith3102@aol.com Subject: Amendment to MCWD permit 15-459 (1100 Miliston Rd, Orono) approved Good afternoon, Barbara Burwell has MCWD permission to add 137 linear feet of rip-rap to the shoreline of 1100 Millston Road in the City of Orono.This work is added as an amendment to MCWD permit 15-459 and it is in conformance with MCWD rules. Thanks, MIRIAM EASON District Representative Minnehaha Creek Watershed District 952-641-4586 http://minnehahacreek.or�/ ��� MINNEMANA CRE6K WATER$NED Di$FR9GF 1 1 f �' //`,,�- �%:-, ' �;� f /',.�/ Melanie Curtis ' - From: Dale [dalegus@earthlink.net] Sent: Thursday, December 04, 2014 11:00 AM To: Melanie Curtis Subject: Re: Burwell Attachments: Burwell Shore Plan 12414.pdf; Burwell Stairs 12-4-14.pdf; Zoning Permit Application 2014 complete.pdf Melanie, I hope you had a good Thanksgiving and you are ready for a great Christmas. Well,there are always surprises. Just last week Barbra approved the contract for making the stairs out of wood instead of steel. The plan is very much like the one you have seen before,but we have changed the landings a little and jogged the separate sections of steps to snake between the trees so as to not harm them. The four landings are only 27 square feet,and they jog just one foot at a time. Attached are pdfs of the closeup of the steps,and a copy of the shareline plan along with a partially complete application. What else would you like me to submit? I thought you might want my contact information because the first approval had that on it. I could do it for Concept Landscape if that would be better. Dale On Nov 6,2014,at 12:11 PM, Melanie Curtis wrote: > I know how you feel. I am so exhausted when I leave here everyday that I completely zone out for my entire drive home... > >You just need a zoning permit(administrative&it's attached),plans and if you can provide planting/screening detail that would be great. > > > >Melanie Curtis 952.249.4627 mcurtis�,ci.orono.mn.us > > >-----Original Message----- >From: Dale [mailto:dalegi$(a�earthlink.net] > Sent: Thursday,November 06,2014 11:43 AM >To: Melanie Curtis > Subject: Re: Burwell > >Melanie, > > Sorry I missed that. It does not surprise me that I missed your response,yesterday was a blur until I finished up about l Opm. > >OK,with the two options left, do we need to submit any additional detail beside the detail of the step construction? Do you want a planting plan to show how we screen them? > >Do we need to go back to the Planning Commission, or the Board,or is it just staff approval? There is consideration of building it this winter. > 1 � >Dale > > >On Nov 6,2014,at 10:58 AM, Melanie Curtis wrote: > »I did respond yesterday. I'll resend when I return to my desk. » »Sent from my iPhone. » »On Nov 6,2014, at 10:53,Dale<dalegus(a�earthlink.net>wrote: » »Melanie, » »Any time to look at the Burwell steps. If you have questions, I am in my office. » » »Thanks, » »Dale > ><Zoning Permit Application 2014.pdfl 2 Christine Mattson From: Melanie Curtis Sent: Thursday, October 24, 2013 8:39 AM To: Tom Potter Cc: Christine Mattson Subject: FW: 20131024 1100 Millston Rd -#13-01076 Tom Please see below. We can get this permit issued pretty quickly but we need the survey to be updated... Melanie Curtis � 952.249.4627 I� mcurtis@ci.orono.mn.us From: Jesse Struve Sent: Thursday, October 24, 2013 8:34 AM To: Melanie Curtis Cc: Christine Mattson Subject: 20131024 1100 Millston Rd - #13-01076 Melanie, I reviewed the permit application for the detached garage at 1100 Millston Rd but it is incomplete. The application has what appears to be a blown up version of an old survey with the location of the proposed garage hand drawn on. Unfortunately this needs to be on a signed survey. Jesse Struve, PE Director of Public Works/City Engineer City of Orono (952) 249-4661 - Direct (952) 249-4616- Fax www.ci.orono.mn.us 1 Jesse Struve From: Jesse Struve Sent: Thursday, October 24, 2013 8:34 AM To: Melanie Curtis Cc: Christine Mattson Subject: 20131024 1100 Millston Rd -#13-01076 Melanie, I reviewed the permit application for the detached garage at 1100 Millston Rd but it is incomplete. The application has what appears to be a blown up version of an old survey with the location of the proposed garage hand drawn on. Unfortunately this needs to be on a signed survey. Jesse Struve, PE Director of Public Works/City Engineer City of Orono (952) 249-4661 - Direct (952) 249-4616- Fax www.ci.orono.mn.us 1 City of Orono RoNo Hardcover Calculation Worksheet 1 � Property Address: � � 00 (����.LS`�-on �oo� , Q rono , m� F L ���'fSH��� Prepared by: �ho�� �o.��r Date: Stormwater Quality Overiay District Tier: (Circie one) -Tier 1 Tier 2 Tier 3 Tier 4 Tier 5 Step 2: PROPOSED HARDCOVER In the following table, identify all items of proposed hardcover on the property, keyed by letter to Certificate of Survey (survey must accompany this form). Include all existing hardcover items that are intended to remain, as well as a(I proposed hardcover items that will be added. Use as many lines as necessary to accurately depict proposed hardcover status of the property. For Tier 1 properties, identify any features by letter which are split at the 75' setback line and calculate hardcover square footage separately for each portion. Key to Hardcover Item (Describe) Length x Width Total Surve (Square Feet) Exam le) (Gara e) t24'x 30') (720 S.F.) A e � � S.F. B o mo v S.F. C ' 'o �t•'i c. o..1�.5 S.F. p o � � S.F. E `� rii t 1 �`l S.F. F ' S.F. G o S.F. H a'_i S.F. I o,.. S.F. J ri g 5 S.F. K ive ° S.F. L S.F. M ro S.F. N ' S.F. O S.F. P S.F. Q S.F. R S.F. S S.F. T S.F_ U S.F. V S.F. W S.F. X S.F. Y S.F. Z S.F. 1) Total Pro osed Hardcover S.F. Excludable Hardcover See Ci Code Sec 78-1684 : S.F. S.F. S.F. S.F. S.F. 2 Total Excludable Hardcover S.F. 3 Net Pro osed Hardcover Subtract line 2 firom line 1 S.F. 4 Total Lot Area S.F. Proposed Hardco�2r Percentage [(3)�-(4)] ' a, % Packet Last Updated: 04/19/2013 Page 15 of 23 City of Orono �.on�o �arc�cover Calcuiation UUorkshe�# ,y `� Property Address: ` l O O /n i�,..�.S�or1 �oa.d ' � hort0 , � l�l �qkESHO�E� Pre ared b : Date: A Y ��-Lo r,nc�.S �o`�l�r Stormwaier Quality Overlay District Tier: (Circie one Tier 1 Tier 2 TieT 3 Tier 4 Tier 5 Step 1: EXISTiiVG HARDCQVER In the fo{lowing table identifiy all items of existing hardcover on the property, keyed by letter to Certificate of Survey (survey must accompany this form). Use as many lines as necessary to accurately depict existing hardcover status of the property. For Tier 1 properties, identify any features by letter which are split at the 75' setback line and calculate hardcover square footage separately for each portion. Key to Hardcover Item (Describe) Length x Width Total Surve Square Feet (Exampl I {Garage) I {24'x 30') (720 S.F.) e A ' S.F. B r� a. �05 ' an S.F. C o S.F. D �.n. ' SF E � SF F o S.F. G ar.'►� C m S.F_ N � p S.F. � F I S.F_ J } 1 K r � '� S.F. � � p S.F. 9 s.F. M S.F. N S.F. O S.F. P S.F. a S.F. R S.F. S S.F. T S.F. U S.F. V S.F. W S.F. X S.F. Y S.F. Z S.F. 1 Total Existin Hardcover a 3 s.F_ Excludable Hardcover See Ci Code Sec 78-1684 : S.F. S.F. S_F. " S.F. S.F. 2 Total Excfudable Nardcover g � 3 Net Existin Hardcover Subtract line 2 from line 1 S.F. 4 Total Lot Area a. �., S.F. Existing Hardcover Percentage j(3)=(4)] � � % (Proposed Hardcover next page) Packet Last Updated: 04/19/2013 Page 14 of 23 Christine Mattson From: Willie Gibbs Sent: Friday, August 30, 2013 11:37 AM To: Christine Mattson Subject: RE: 1100 Millston Road It's done From: Christine Mattson Sent: Friday, August 30, 2013 10:19 AM To: Barb Silus; Willie Gibbs Cc: Melanie Curtis Subject: 1100 Millston Road As I am preparing an escrow refund for the Burwell's at 1100 Millston Road, I don't see a final inspection for the cabana #2011-00983. Will you let me know if it was completed and not entered into PW or if it's an inspection that needs to be scheduled? Thank you. Christine Mattson Planning Assistant City of Orono 2750 Kelly Parkway Orono MN 55356 (physical addressJ PO Box 66 Crystal Bay MN 55323-0066 (mailing addressJ � 952.249.4620 � 952.249.4616 � cmattson@ci.orono.mn.us � www.ci.orono.mn.us Summer Office Hours: (Monday, May 20 through Friday,Auqust 30,2013) Monday-Thursday: 7:30 am to 5 pm Friday: 7:30 am to 11:30 am OUR OFFICE WILL BE CLOSED: Monday, September 2, 2013 1 g-��O C ITY OF ORONO � � Street Address: I Mailing Address: I Telephone(952)249-4600 ��, `'� 2750 Kelley Parkway P.O.Box 66 Fax (952)249-4616 l G Orono,MN 55356 Crystal Bay,MN 55323 www.ci.orono.mn.us qkFSH��� January 8, 2013 Tom Potter Tom Potter Construction 6531 Devonshire Drive Chanhassen, MN 55317 RE: Building Permits 2011-00412 & 2011-00983 1100 Millston Road Tom, While closing out permit project files, I noticed that we have not received a final inspection on the cabana or an as-built survey for the projects at 1100 Millston Road. A requirement of the permits for the pool and cabana was submittal of an as-built survey. We still hold an escrow of $5,000 pertaining to the projects. In order to begin the process for the release of the escrow, an as-built survey must be submitted. Final grading and landscaping must be done prior to submittal of an as-built survey. Attached is a copy of our survey requirements. Upon our engineers review and approval of the as-built survey, we can then process the escrow refund. I can be reached at cmattsonCa�ci.orono.mn.us or at 952-249-4620 if you have any questions. Sincerely, CITY OF ORONO 1� 'stine Mattson Planning Assistant c Rodney Burwell; 7901 Xerxes Ave S; Bloomington, MN 55431 Attachment: Survey Requirements � o� O , O CITY of ORONO ��,y_,, ,, Municipal Offices �•�, ��;��������4 � Street Address: Mailing Address: `�+�� �.� ,�, � � ,�, 2750 Kelley Parkway P.O. Box 66 ,�f �1,���`l����'����`�'',�G Orono, MN 55356 Crystal Bay,MN 55323-0066 �kES�H�4 25 October 2011 Rodney Burwell 1100 Mil�ston Road Wayzata, MN 55391 As you may remember because a bathroom was part of the plan for your pool cabana, the City required your signature on a restrictive covenant in order to issue the permit. On the day you stopped in to sign the covenant your wife, Barbara, was not available to sign. You and I discussed this and decided to remove Barbara's name from the signature block. I thought this would be an acceptable solution. Today I received a notification from our attorney that both you and Barbara must sign the agreement in order to properly record the document at Hennepin County. In order to resolve this issue we have drafted a new document for signature. It would be very helpful if you and Barbara would sign the enclosed, revised, agreement before a notary and submit it to me at your convenience. I apologize for the misunderstanding and any inconvenience this may have caused. Additionally, the City currently holds an escrow for the pool, cabana and septic system projects in the amount of $5000. As soon as the projects have been completed, including completion of the final site grading and vegetation establishment, an as-built survey should be submitted for our review. Once verification of compliance with the approved ptans is completed via the as-built survey the escrow can be released. Please have your contractor contact me regarding as-built survey requirements so this can be taken care of in a timely manner. Please feel free to contact me at mcurtis@ci.orono.mn.us or at 952.249.4627 if you have any questions. Sincerely, CITY OF ORONO � Melanie Curtis Planning and Zoning Coordinator Enclosures: Revised declaration of restrictive covenant c: Kevin Keenan—via email Telephone (952)249-4600 • Fax(952) 249-4616 www.ci.orono.mn.us ���'��'!s�� '�''� ���` .,`� � �t< <. � '� 2335 Highway 36 W St. Paul, MN 55113 Tel 651-636�600 Fax 651-636-1311 www.bonestroo.com September 22, 2011 �Bonestroo Melanie Curtis Planning and Zoning Coordinator City of Orono Post Office Box 66 Crystal Bay, MN 55323 Re: 1100 Millston Road File No. 000139-11000-2 File No. 2011-00983 Dear Melanie: We have reviewed the plan for a proposed structure at 1100 Millston Road. The plans are dated 8-25-11. We have the following comments with regards to engineering matters: • The site and grading plan is acceptable from an engineering standpoint. • This project will disturb more than 100 CY of material. Sediment and erosion control information meeting the requirements of Orono's City Code 79-7(c)(2) must be submitted. The minimum $2000 sediment and erosion control financial security should be required of the owner for this permit. If you have any questions, please call me at (651) 604-4894 or send an email to darren.amundsenCc�bonestroo.com. Sincerely, BONESTR00 �_;�=-Z-_=G�____, Darren Amundsen Cc: Chris Mattson