HomeMy WebLinkAbout09/29/2016- Email regarding C.O. Melanie Curtis
From: Melanie Curtis
Sent: Thursday, September 29, 2016 11:59 AM
To: 'Dan Nunn'
Cc: 'Jim Lillesve'; 'rdenman@charlescudd.com'; 'Terrence Chastan-Davis'; Roger Peitso
Subject: 2750 Casco Point Road - final CO
Good morning, Dan.
The temporary CO for 2750 Casco Point Road was issued on August 29th with a list of items to be completed by Oct 1 for
issuance of the final C0. One of the issues which remains outstanding is the removal of the sediment within the
stormwater pipe which inlets on the Atlas Homes'site at 3800 Casco Ave and terminates in the ditch across the road.
Lauren Sampedro with the MCWD discussed this with you. The sediment within the pipe is the result of the Charles Cudd
project on 2750 Casco Point Road. The cleaning of the pipe and removal of the sediment from the ditch/creek(which
drains to the lake) is a requirement of your final CO for this project.
The City and/or the MCWD will inspect the pipe on or after Monday, October 3�d to verify compliance. Once cleaned and
determined to be acceptable by the City/MCWD we can close out the 2750 Casco Point Road permit; Atlas Homes will
then assume responsibility moving forward.
The City will continue to hold the final CO and the $10,000 escrow until all items are completed. We are also waiting for
an as-built survey to be submitted.
Please let me know if you have any questions.
Thanks,
Melanie
Melanie Curtis, Planner
Direct 952.249.4627
Planning &Zoning Office 952.249.4620
2750 Kelley Parkway, Orono, MN 55356
Email: mcurtisCa�ci.orono.mn.us
Website: www.ci.orono.mn.us
1
Melanie Curtis
From: Melanie Curtis
Sent: Thursday, September 29, 2016 12:03 PM
To: 'Todd Holmers'
Cc: 'Mark Way (mark@atlashomesmn.com)'; 'Terrence Chastan-Davis'
Subject: 3800 Casco Avenue
FYI: See below. �
Please be advised once Charles Cudd cleans the storm drain pipe and the City approves the final result, Atlas homes will
then be responsib for protecting the drain.
A suggestion I ca offer would be to completely re-do the erosion control measures around the drain to incorporate some
hay bales and ne trenched in fencing or newly placed biorolls. If you have questions on solutions moving forward
please contact me or Terrence Chastan-Davis with the MCWD (copied).
Melanie Curtis
S'952.249.4627 �mcurtis@ci.orono.mn.us
From: Melanie Curtis
Sent:Thursday, September 29, 2016 11:59 AM
To: 'Dan Nunn' <Dann@charlescudd.com>
Cc: 'Jim Lillesve'<JimL@charlescudd.com>; 'rdenman@charlescudd.com' <rdenman@charlescudd.com>; 'Terrence
Chastan-Davis' <tchastan-davis@minnehahacreek.org>; Roger Peitso <rpeitso@ci.orono.mn.us>
Subject: 2750 Casco Point Road -final CO
Good morning, Dan.
The temporary CO for 2750 Casco Point Road was issued on August 29th with a list of items to be completed by Oct 1 for
issuance of the final CO. One of the issues which remains outstanding is the removal of the sediment within the
stormwater pipe which inlets on the Atlas Homes'site at 3800 Casco Ave and terminates in the ditch across the road.
Lauren Sampedro with the MCWD discussed this with you. The sediment within the pipe is the result of the Charles Cudd
project on 2750 Casco Point Road. The cleaning of the pipe and removal of the sediment from the ditch/creek (which
drains to the lake) is a requirement of your final CO for this project.
The City and/or the MCWD will inspect the pipe on or after Monday, October 3�d to verify compliance. Once cleaned and
determined to be acceptable by the City/MCWD we can close out the 2750 Casco Point Road permit; Atlas Homes will
then assume responsibility moving forward.
The City will continue to hold the final CO and the $10,000 escrow until all items are completed. We are also waiting for
an as-built survey to be submitted.
Please let me know if you have any questions.
Thanks,
Melanie
Melanie Curtis, Planner
Direct 952.249.4627
Planning &Zoning Office 952.249.4620
2750 Kelley Parkway, Orono, MN 55356
Email: mcurtis(a�ci.orono.mn.us
Website: www.ci.orono.mn.us