HomeMy WebLinkAboutLA18-98 ExB Draft PC MinutesMINUTES OF THE
ORONO PLANNING COMMISSION MEETING
Tuesday, January 22, 2019
6:30 o’clock p.m.
_____________________________________________________________________________________
Page 1 of 2
4. LA18-000098 JEN AND TONY ISHAUG, 4245 CHIPPEWA LANE, VARIANCES, 7:21
P.M. – 7:29 P.M.
The applicant was not present.
Barnhart stated the applicants are requesting a front yard setback variance for a detached garage. The
new accessory building requirements allow a detached garage 1,000 square feet or smaller to be forward
of the principal building, subject to conditions, which includes the requirement that the building should be
consistent in material and color with the principal structure. The applicants have sized and designed the
garage to fit these requirements.
The new accessory building ordinance requires any accessory building forward of the principal building
to meet the front yard setback. The applicants are requesting a variance to allow a 20-foot setback instead
of the 100-foot required setback due to the topography of the property. The improvement will be
consistent in character with the principal structure. This house is located at the end of a dead-end street so
the impact to the neighborhood is relatively minimal.
Staff has completed a preliminary review of the project for compatibility with the septic system and has
determined that the project is not likely to impact the existing or future septic sites. The site plan for the
building permit should call out the alternate septic site.
Due to the unique topography and configuration of improvements on the property, the request for a front
yard setback variance seems reasonable. There are no issues with the proposed grading. When the
building permit is submitted, the associated site plan should depict the location of the erosion control
measures and call out the top and bottom elevation of the proposed retaining wall.
Staff recommends approval of the variance as proposed.
Thiesse asked if Staff has confirmed that Chippewa is a dead-end road and there is no right-of-way that
continues past the property line.
Barnhart pointed out the cul-de-sac and the proposed building.
Thiesse stated to his knowledge the right-of-way also ends there so there will not be a through road
constructed there at some point.
Landgraver asked if the adjacent property to the east is landlocked.
Curtis indicated they front on Watertown Road.
The applicant was not present.
Chair John Thiesse opened the public hearing at 7:25 p.m.
There were no public comments regarding this application.
Chair John Thiesse closed the public hearing at 7:25 p.m.
MINUTES OF THE
ORONO PLANNING COMMISSION MEETING
Tuesday, January 22, 2019
6:30 o’clock p.m.
_____________________________________________________________________________________
Page 2 of 2
Lemke asked if there are any trees that will be removed as part of this project.
Barnhart indicated he has not spoken to the applicant, but that it is his understanding some trees will be
removed. A picture of the site shows the trees in that area to be around two inches in girth.
Landgraver asked whether any screening was proposed between the accessory structure and the street.
Barnhart stated it does not appear so and nor is any required.
Libby commented it appears the applicant has made a concerted effort to match it to the principal
structure and that there does not appear to be a lot of soil disruption or change in grade. Libby stated it is
a nice design.
Landgraver noted they already have a four-stall garage.
Erickson commented he likes the sketch.
Landgraver moved, Libby seconded, to recommend approval of Application No. LA18-000098, Jen
and Tony Ishaug, 4245 Chippewa Lane, front yard setback variance. VOTE: Ayes 5, Nays 0.