J- I reviewed the DA and request the following action be taken:
a. Para 12 Time of Performance- All improvements except wear course
to be completed by December 31,2019; all are complete except the iron
monuments and these will complete shortly; the original wear course
dates of August 15- September 15, 2019 were modified to extend to
November 1, 2019, weather permitting. The weather is not expected to
meet the MNDOT requirement of 50 degrees and improving for the wear
course application in the next few weeks and due to extremely wet
conditions the builder on Lot 4 has been unable to remove the excess
dirt on their build site, only about 1/2 removed to date, thus wear
course application will be delayed to next year. The Developer will
assume responsibility for snow plowing over the winter months.
b. Request amend the DA to allow for wear course application
completion until July 31, 2020.