HomeMy WebLinkAboutAboveground storage tank requirements �
. t,
,
4
��_� General Requirements for
Aboveground Storage Tanks
Minnesota
Poliution
Control Tanks/Aboveground Storage Tanks#1.02 • April 2004
Agency
his fact sheet outlines the • temporary tanks
requirements for regulated above- . tanks that are less than 500 gallons
ground storage tanks (ASTs)found
in Minn. R. chs. 7001 and 7151. These
rules apply to all ASTs storing a liquid AST requirements
substance that is not gaseous or solid at Owners and operators must comply with
ambient temperature and pressure. AST requirements in Minn. R. 7151, unless
The Minnesota Pollution Control Agency exempted as outlined below.
(MPCA)must be notified about all ASTs Many ASTs are exempt from Minn. R. ch.
within 30 days of installation or change in 7151. They are:
tank status(Minn. Stat. § 1 16.48).
• tanks containing 500 gallons or less
The AST rules and notification statute does
not indicate a minimum tank size,but the • farm tanks
MPCA considers the smallest AST . residential tanks 1,100 gallons or less
requiring registration to be a tank that is used for noncommercial purposes
500 gallons or greater in capacity. This size . equipment or machinery containing
is consistent with underground storage tank
notification requirements. substances for operational purposes
like hydraulic lift tanks,heating and
Owners and operators must complete and cooling equipment, and electrical
submit the AST Notification Form to the equipment
MPCA. To get a copy of this form, call . vehicles designed and used to transport
MPCA at 651-296-6300 or toll-free at substances that don't remain at the
1-800-657-3864 or on the MPCA Web site same location for more than 30
at www.pca.state.mn.us/cleanup/ast. consecutive days or refill at the same
site after dispensing the tank's contents
Exemptions from notification . heating oil tanks 1,100 gallons or less
Tanks not required to be registered . wastewater treatment facility
include: equipment
• farm or residential tanks 1,100 gallons . indoor tanks
or less storing motor fuel for . tote tanks
noncommercial purposes
• heating oil tanks 1,100 gallons or less
• tanks greater than 500 gallons capacity,
but less than or equal to 1,100 gallons
• agricultural chemical tanks capacity that are more than 500 feet
• tanks storing liquids that are a gas at from surface water
atmospheric temperature and pressure
• tote tanks
t-a 1-02
Minnesota Pollution Control Agency • 520 Lafayette Rd. N., St. Paul, MN 55155-4194 • www.pca.state.mn.us
651-296-6300 • 800-657-3864 • TTY 651-282-5332 or 800-657-3864 • Available in alternative formats
• septic tanks Requirements for AST facilities with a
• a surface impoundment, pit, pond, or lagoon capacity greater than one million gallons
• stormwater collection systems Facilities with greater than one million gallons total
capacity for all liquid storage tanks must apply to the
• temporary tanks (tanks at a site less than 30 days MPCA for a major facility permit. Requirements for
• storage tanks with drinking water, filtered-surface tanks at these facilities are based on the individual site
water, demineralized water, noncontact cooling and tank characteristics(Minn. R. 7001.4200).
water, or water stored for emergency purposes Requirements for small tanks near surface
Requirements for regulated tanks greater Water
thatl 1,100 gallOnS Regulated tanks with a capacity of greater than 500
gallons, but less than or equal to 1,100 gallons that are
All regulated tanks with a capacity greater than 1,100 within 500 feet of a class 2 surface water(water that can
gallons must: be used for recreational purposes)are required to:
• be registered with the MPCA . be registered with the MPCA
• be labeled • be labeled
• be constructed using appropriate industry standards . provide secondary containment
• have secondary containment . have a sign at the facility
• have a facility sign posted . be constructed using appropriate industry standards
• have substance transfer area safeguards
Requirements for temporary tanks
• have internal and/or external corrosion protection
Tanks larger than 1,100 gallons that store product for
• have overfill protection longer than 30 days, but less than one year are defined as
• be monitored for leaks and regularly inspected temporary tanks and must:
• be properly maintained • be labeled
• have monitoring and inspection records on site • have a posted facility sign
• assess releases during operations or at tank removal • have secondary containment
and report them to the State Duty Officer at . be maintained
1-800-422-0798
Temporary tanks with a capacity of greater than 500
• label lines so connections can be identified during gallons within 500 feet of a class 2 surface water must
substance transfer also meet the temporary tank requirements listed above.
• have underground pipin�safeguards if utilized The MPCA will not require temporary tanks to be
• be properly closed if no longer used registered, however the rule requirements still apply.
• be sampled for contamination when tank is removed Compliance with other regulations
More information about these requirements and their Other regulations that tank owners need to be in
effective dates can be found in fact sheets listed at the compliance with include:
end of this document in the"Need more informatiorr"
section.
General Requirements for Aboveground Storage Tanks • t-a1-02 • Apri�2004 �. � MinnesoW Pollution
�'�" Ca�trol Aye�xY
Page 2
� .
• the federal Spill Prevention,Control and
Countermeasures Plan
• the Minnesota"Spill Bill" requirements
• hazardous waste regulations
• state and local fire code
• other state and local regulations
Also, petroleum products that are stored for resale in
ASTs greater than 2,000 gallons must comply with the
petroleum product delivery law(see Petroleum Product
Delivery Law fact sheet for more information).
Need more information?
Visit the AST Program at
www.pca.state.mn.us/cleanup/ast.html. The site has
forms, fact sheets, and other information about ASTs
and AST requirements.
You can also call the MPCA at 651-296-6300 or
1-800-657-3864.
General Requirements for Aboveground Storage Tanks • t-a1-02 • April 2004 �Fnnesow roUui�on
� Control Agency
Page 3
1
�..�,,,� Minnesota Pollution Aboveg ro u n d Sto rage Ta n k
� Control Agency
520 Lafayette Road (AST) P ro g ra m
St.Paul,MN 55155-4194
Major AST Facility Permit Application
Pursuant to Minn. Stat. § 115.03, subd. (1)(e)(3)and Minn. R. ch. 7001, a permit is required for the aboveground storage of liquid
substances at a major facility.A major facility is one where the total liquid storage design capacity of all tanks, including indoor tanks,
is one million gallons or greater.
Instructions
1. This permit application is to be used for:
. proposed new major facilities
• non-major facilities that intend to expand liquid substance storage to one million gallons or greater
• re-permitting of existing major facilities
2. This application form should not be used for permit modification requests; a separate form is available at:
http://www.pca.state.m n.us/pu blications/t-a3-26.doc.
3. For new and expanding facilities, a permit must be issued by the Minnesota Pollution Control Agency(MPCA)prior to initiating
tank construction. It is recommended that this application be submitted at least 90 days prior to initiating tank construction.
4. For permitted facilities, this application must be submitted at least 90 days prior to expiration of the current permit according to
Minn. R. 7001.0040, subp.3 and Minn. R. 7001.0020.H.
5. Answer all questions, except for questions limited to facility types(new,expanding, or existing)other than your own. Answer
questions in the blocks provided. If more space is needed, enlarge or create additional blocks, or add information at the end of
the document on additional pages.
6. Answer questions using information that is currently available.Where an answer to a question is unknown,would require
further testing or assessment, indicate"Unknown".
7. Even if the information requested has been submitted to the MPCA at some other time or in some other form, please include it
here in order to verify that it is up to date. One exception would be if a specific document is requested which was previously
submitted; in this case, reference the name of the document and date it was submitted.
8. To add rows to the tables to accommodate more information or more tanks, click on the last box in the table and hit the Tab key
or use the Table-Insert-Rows above or Rows Below function.
9. The application must be signed and certified by the appropriate authorized company representative as defined in Minn. R.
7001.0060.
10. Submit:
• a signed paper copy of the completed application
• all required attachments
Submit to: Aboveground Storage Tank Program
Attn: Beckie Olson
Minnesota Pollution Control Agency
520 Lafayette Road North
St. Paul, Minnesota 55155-4194
I. General
This permit application is for(check one):
❑ A proposed new major facility("New")
❑ A non-major facility that intends to expand liquid storage to one million gallons or greater("Expanding")
❑ Re-permitting of an existing major facility("Existing")
Company permit contact:
Last name: First name:
Address:
City: State: Zip code:
Email: Telephone Number:
t-a3-25
4/4/07 Page 1 of 8
Preparer of application contact:
Last name: First name:
Address:
City: State: Zip code:
Email: Telephone Number:
II. Current Permit (Existing facilities only)
AST Permit number:
Date of issuance or
most recent modification:
Expiration date:
III. Tank Owner/Operator
List any legal entity that is an owner or operator as defined in Minn. R. 7151.1200, subp. 24 and 26, of any tank at the facility. If
there are multiple owners and/or operators,designate each as(Owner)or(Operator).
Cor orate name Mailin address Re istered a ent name
IV. Facility
Facility name:
Address:
City or township: County: GPS identifier:
V. Description of Business Activities
Provide a brief description of the nature of the business activities at the facility and how aboveground liquid storage is used in the
course of the business activities:
VI. Tanks
Using the tables below, provide the applicable information regarding tanks at the facility. In Part A., list all regulated AST systems at
the facility. Part B requests the applicant to list certain AST's that are not regulated, for purposes of verifying their exclusion from
regulation. For questions about whether or not a tank should be listed, consult an AST permit manager by calling 651-297-8305.
A. Regulated Tanks
List all AST systems located at the facility that are being used to store any substance as defined in Minn. R. 7001.4205,
and that are not excluded AST systems under Minn. R. 7151.1300. For each tank, identify:
Tank number: If the facility has a permit, use the company's numbering system from the current permit. If there is no
current permit, provide a numbering system. Each tank must have a unique number. Tank numbers must be keyed to
the facility layout and to the secondary containment and substance transfer sections of the application.
Substance: Identify the stored liquid substance with as much specificity as possible. For petroleum products, food
products, and chemicals, identify grade, type, or solutions. If the tank is used to store different substances at different
times, list all. If the substance is a mixture, a solution, or has identifiable contaminants, list all components of the
substance,with percentages.
Capacity: Design capacity to overflow(in gallons)
Year of installation
• If uncertain, give estimate and identify as an estimate
• If the floor of a steel field-erected tank has been replaced, give most recent year as follows: [new floor vear]
Status
t-a3-25
4/4/07 Page 2 of 8
A=Active(currently contains liquid substances or temporarily empty and resumption of storage is anticipated within
one year or contains no liquid substances but has not been closed according to Minn. R. 7151.8200)
C= Closed(currently contains no liquid substances and resumption of storage is not anticipated within one year
and tank has been closed in accordance with Minn. R. 7151.8200)
Tank material
S= Steel single wall
SS= Stainless steel single wall
DW= Steel double wall
F= Fiberglass
P= Plastic
C=Tiled concrete
O=Other(describe)
Fabrication type
SF= Shop-fabricated
FE= Field-erected
Tank foundation design(One or more as applicable)
S =Tank resting on native soil, gravel, or sand
L=Tank resting on synthetic liner on native soil, gravel, or sand
C=Tank resting on concrete slab or pad (CC=concrete is coated)
R=Tank resting on concrete ringwall
E =Tank is elevated on supports
O=Other(describe or provide a drawing)
Capacity Year Fabrication
Tank# Substance igallon�_ installed Status Tank Material �e Tank Foundation Desi�
Last external inspection
• Field-erected tanks=give date of last external inspection per API Standard 653 or other protocol.
• Shop-fabricated tanks=give date of last periodic inspection per STI SP001-00 or other protocol.
. None= never externally inspected to any protocol.
Lastinternalinspection
• Field-erected tanks=give date of last out-of-service internal inspection. Attach copy of full API Standard 653
inspection report, or inspection report summary, using MPCA Guidelines format. If inspection protocol was
other than API 653, attach a description of the protocol and results of the inspection. If inspection report or
summary has previously been submitted to the MPCA, mark Report Submitted (date).
• Shop-fabricated tanks=give date of last certified inspection per STI SP001-00 or other protocol.
• None= never internally inspected to any protocol.
Next external inspection
• Field-erected tanks only: give proposed date of next e�ernal inspection.
Next internal inspection
• Field-erected tanks: provide proposed date of next out-of-service internal inspection and justification(ten years
from date of initial service for new tanks).
• Shop-fabricated tanks: provide proposed date of ne�certified inspection and justification per STI SP001-00 or
other protocol.
Release Prevention Barrier(RPB), if any
If the tank has a RPB placed under the tank which has the function of:
1. Preventing the escape of released material, and
2. Containing or channeling released material for leak detection; identify as either:
S=synthetic liners
C=concrete pads
CL=clay liners
DB =double steel bottom
DB-L=double steel bottom with synthetic liner
Other: describe yours
t-a3-25
4/4/07 Page 3 of 8
Internal floor coating (if any)
Give year of installation
Give base material(epoxy, fiberglass, etc)
API 652=coating was installed according to API RP 652
TN =thin coat(less than or equal to 20 mils)
TK=thick coat(greater than 20 mils)
F=fiberglass reinforced
Cathodic protection system for underside of tank floor(if any)
Give year of installation
API 651 =system is designed and operated according to API RP 651
SA=sacrificial anode system
IC= impressed current system
Release detection system(if any)
V= periodic visual monitoring of tank for releases(identify interval)
LT=periodic tank leak testing (identify methodology used and interval)
Last Next Release Intemal Cathodic Release
Last external internal external Next internal prevention coating or protection detection
Tank# ins ection ins ection ins ection ins ection barrier liner s stem s stem
Substance level gauging mechanism I
FL=float gauge, local readout only
FR=float gauge, local and remote readout
O=other type(describe and/or provide schematic)
Substance transfer—Area name or number
Provide a unique name or number, keyed to the facility layout, for any area(s)where transfer vehicles(tank truck,
rail car, barge, or aircraft)are stationed during transfers in and out of the tank.
Substance transfer—In—Identify all methods by which substances may be transferred into the tank.
T=from tank truck
R=from railcar
B=from barge
P=by fixed piping from industrial process, from other tanks, or from outside the facility
Substance transfer—Out—Identify all methods by which substances may by transferred out of the tank.
T=to tank truck
R=to railcar
B=to barge
A=to aircraft
P=by fixed piping to industrial process, to other tanks, or off the facility property
Substance transfer area construction
C= Concrete pad
A=Asphalt
S= Native soil
O=other type(describe)
Overfill prevention system(if any)
. Level 1 = High level alarm visible or audible to person controlling the fill,API RP 2350 design. Level set at no
greater than 95%of capacity to overfill and no less than 30 minutes to overfill at maximum fill rate. Alarm need
not be independent of gauging system. Applicability: Attended transfers of Type A and Type B substances from
vehicle(truck, railcar, barge) into tank containment, and Type C1 substances
• Level 2= Level 1, plus alarm is fully independent of tank gauging system. Applicability: Unattended transfers
(individually initiated and terminated by personnel)of Type A and Type B substances from industrial process,
from other tanks, or from off-site pipeline into tank
• Level 3= Level 2 plus automatic shutoff device fully independent of tank gauging system.Applicability:
Automated and/or continuous transfers(not individually initiated and terminated by personnel)of Type A
substances from industrial process into tank; or unattended transfers(individually initiated and terminated by
personnel)of Type A and Type B substances from industrial process, from other tanks, or from off-site pipeline
into tank
• None=Type C2 substances
t-a3-25
4/4/07 Page 4 of 8
Substances
• Type A=gasoline, aviation gas, naphtha, denatured ethanol, and hazardous materials, or mixtures or blends
containing such substances
• Type B=diesel, kerosene,jet fuel, crude, fuel oils#1-4,waste oii
• Type C1 =fuel oil#6, low hazard chemicals, process wastewater, asphalt emulsion
. Type C2=asphalt, roofing flux, vegetable oils, sugar beetjuice, paper pulp, other regulated substances
Substance transfer—Other
List one or both or leave blank, as applicable:
• I = impermeable containment area at transfer connection point(give materials of construction and
maximum spill volume contained)
• RT= remote transfers may occur, during which transfers either in or out are initiated, monitored,
terminated, or otherwise controlled from outside of the facility, e.g. interstate pipelines
• RT-UM = remote transfers may occur when the facility is unmanned
Substance Substance Substance Substance OverFill
' transfer Area transfer transfer transfer prevention Substance
Tank# Gau in name or# methods—In methods—Out area construction s stem transfer—Other
B. Non-Regulated Tanks
List all tanks at the facility greater than 1100 gallons capacity that are not subject to regulation for one of the specific
reasons given below. Tanks must meet the applicable exclusion criteria in Minn. R. ch. 7151.1300. Tanks at the facility
that are not subject to regulation for other reasons, (e.g. tote tanks)need not be listed below.
1. Tank number or name
Provide a unique number or name for the tank. Tank numbers or names must be keyed to the facility layout.
2. Contents
Identify the contents of the tank.
3. Reason for exclusion(choose one):
❑ Indoor(per Minn. R. 7151.1300, subp. 2.C.)
An indoor tank is one that is located inside of a building, resting on or elevated above an impermeable floor,
from which a release in the amount of the design capacity of the tank would (Identify by letter a/b/c which of the
containment methods applies to the tank.):
a. be entirely contained within a tank-specific secondary containment structure; or
b. would not escape from the building through doorways, floor drains, or by other means; or
c. would be directed by the drainage system of the building either to a permitted on-site wastewater treatment
facility, or to a permitted municipal wastewater treatment facility.
❑ Wastewater clarifiers, basins, and treatment equipment(per Minn. R. 7151.1300, subp. 2.A.)
❑ Hazardous waste(per Minn. R. 7151.1300, subp. 2.E.)
❑ Agricultural chemical(per Minn. R. 7151.1300, subp. 2.F.)
❑ Stainless steel (per Minn. R. 7151.1300, subp. 2.1.)
❑ Clean water(per Minn. R. 7151.1300, subp. 2.J.)
❑ Solid(substance is a solid at ambient temperatures and pressures)
❑ Gas(substance is a gas at ambient temperatures and pressures)
Tank#or name Contents Reason for exclusion
VII. Secondary Containment
List all secondary containment areas for tanks listed in Part VI.A., including:
Containment area number
Give each area a number. This can be the same number as that of the tank in the area, or one of the tanks if
there are more than one, or another numbering system may be used. Containment area number must be keyed to
facility layout.
t-a3-25
4/4/07 Poge 5 of 8
Tank number of each tank within area
Available containment volume
Calculate net available volume of containment in gallons, accounting for contour of land, slope of dike walls,
piping, tanks, buildings, and other obstructions within area. A secondary containment area must be able to
contain at least 100 percent of the design capacity of the largest tank in the secondary containment area plus
displacement from additional tanks within the containment area, with an additional ten percent capacity where
secondary containment areas are exposed to precipitation.
Volume calculation method
M =manual measurements
S=survey showing contour and elevation
Give date of most recent survey or measurement
Attach calculations to the application(new facilities or after major modification)
Construction materials
Identify primary materials used for containment area construction. If dike walls and basin floor are different,
describe each.Attach construction specifications and drawings(new facilities only).
SL=synthetic liner(identify material)
CB=concrete block
CP=poured concrete
CC=coated concrete
ST=steel
NS =native soil
CL=engineered liner using imported clay or bentonite
SA=permeabi�ity of native soil reduced by means of clay amendment
G=geotextile-bentonite mat
Permeability(new and expanding facilities only)(native soil,soil amendment,and clay liners only)
Express permeability as hydraulic conductivity to water in cm/sec. Attach post-construction permeability test
reports.
Area# Tank#'s Volume Calculation method Construction Materials Permeabilit
VIII. Piping
Piping subject to AST major facility permitting includes any piping of two inches or greater inside diameter, located either
aboveground or underground, used to convey a substance to, from, or between any regulated tank(see Minn. R. 7001.4205,
7151.1200, and 7151.1300).
A. Aboveground piping
For aboveground piping at the facility, describe in general terms the Iocation, fabrication (steel, plastic, other), and any
release prevention, detection and containment safeguards and procedures such as visual inspection, pipe coating and
wrapping, double-walled piping, and leak testing. If there is no such piping, indicate"none".
B. Short-run underground piping
Short-run underground piping includes dike penetrations, roadbed crossings, and other line segments that are less than
50 feet in length. For short-run underground piping at the facility, describe in general terms the location,fabrication
(steel, plastic, other)and any release prevention, detection and containment safeguards and procedures such as visual
inspection, pipe coating and wrapping,double-walled piping, non-corrosive materials, API Standard 570, and leak
testing. If there is no such piping, indicate"none".
C. Long-run underground piping
Long-run underground piping includes any line segments that are 50 feet or greater in length. Identify each segment as
specified below and describe any release prevention, detection and containment safeguards and procedures used for
each segment, such as visual inspection, pipe coating and wrapping, double-walled piping, non-corrosive materials,API
Standard 570, and leak testing. Provide a scale schematic showing the location of the endpoints A and B and identify the
endpoints below. If there is no such piping, indicate"none".
t-a3-25
4/4/07 Page 6 of 8
Segment
name or# End oint A End oint B Inside Diameter Fabrication Substance s Existin Safe uards
IX. Site Hydrogeology (New and expanding facilities only)
Requested information may be found in engineering reports or site assessments. Information requested is for facility as a whole;
however, if significant geological differences exist within the facility, give information as applicable to each containment area.
Avera e or estimated de th to round water ft beneath tanks:
Native soil classification s , between surface and roundwater:
Calculated or estimated average vertical permeability to water
of native soil cm/sec :
Avera e or estimated de th to bedrock ft :
Bedrock t e and formation name:
Name of the nearest Class 2 surface water and distance to the
nearest tank at the facility(surface water must be shown on
location ma :
Discuss any known tank-or piping-related site contamination, or
an investi ation indicatin no contamination:
X. Suggestions (Existing facilities only)
If there is any requirement in the current permit which in the view of the applicant is unnecessary, or for which a less burdensome
alternative exists which would accomplish the same goal, please identify and briefly explain.
XI. Attachments
Required of all applicants:
1. Facility layout(minimum scale: 1" = 100')showing the facility with the following marked:
• All tanks as numbered or named in VI.A. and B.
• Boundaries of all secondary containment areas as numbered in VII.
• Substance transfer areas(connection point between tank and transfer vehicle)for each tank listed in VI.A.,
including any loading rack
• Endpoints and approximate run of each long-run underground line segment listed in VIII.C.
• Buildings
• Roads and railroad tracks
• On-site ponds
2. Location Map showing the area surrounding the facility for a distance of at least one mile in all directions(a USGS
Quad map works well for this purpose), including:
• Nearest Class 2 surface water
• Nearest towns and cities
Required for new and expanding facilities only:
• Construction specifications and drawings for field-erected tanks and secondary containment areas.
• Permeability test reports per MPCA testing guidelines for any native soil, engineered clay liner and soil amendment
containment areas.
• Survey and volume calculations for any native soil,engineered clay liner and soil amendment secondary
containment areas. Submit actual drawings showing site contour and elevations. Survey may be up to three years
old if no new containment areas have been constructed and no modifications made to containment areas since the
survey was conducted. A survey over three years old may be submitted if a licensed surveyor has recently shot the
lowest part of each dike and the highest part of the bottom of each diked area to determine if the original elevations
remain accurate.
• Containment area measurements and calculation of available containment volume for each area not subject to
survey.
t-a3-25
4/4/07 Page 7 of 8
Required for new facilities only:
• Copy of any draft or final environmental impact statement or environmental assessment worksheet regarding the
facility.
XII. Certification
Certification must be signed by an authorized company representative who is a member of company management as defined in
Minn. R. 7001.0060.
I hereby certify, under penalty of law, that I have personally examined and am familiar with the information submitted on
this and all attached documents. I believe that the submitted information is true, accurate and complete.
Signature: Date:
Print name: Title:
t-a3-25
4/4/07 Page 8 of 8
_ -T_
This guidance is not a regulatory document and should be considered only informational and supplementary to the
MPCA permits(such as the construction storm water general permit or MS4 permit)and local regulations.
7.62 Containerized Storage: ABOVE-GROUND STORAGE TANKS
GENERAL REQUIREMENTS FOR REGULATED TANKS
(Minn. Rules ch. 7100)
Facilities that have less than 1 million gallons in tank capacity are covered under a general permit
issued on November 1, 1995. These requirements pertain to above-ground storage tanks storing
liquids, such as petroleum products, used oil, chemicals, food products and pulp. A site is
considered to have a liquid storage permit for its above-ground storage tanks if the following
requirements are met.
Tanks over 110 gallons capacity must be registered
Includes: Exempt:
Petroleum tanks Farm, residential, and heating oil tanks 1,100 gallons
Chemical tanks and less
Farm, residential and heating oil tanks over Flow-through process tanks
1,100 gallons Compressed gas tanks
Agricultural chemical tanks
Tanks over 1,100 gallons capacity must have secondary containment
Includes: Exempt:
Petroleum tanks Farm, residential and heating oil tanks 1,100 gallons
Chemical tanks and less.
Tanks which store a liquid which could pollute Flow-through process tanks.
the waters of the state Compressed gas tanks.
Food tanks(e.g., molasses, vegetable oil) Agricultural chemical tanks.
March 2000 7.62-1 Chapter 7
,,,,.,�.� Q Other Regulated Substance
_ Requirements for Aboveground
Minnesota Storage Tanks
Poliution
Control Tanks/Aboveground Storage Tanks#2.07 • April 2004
Agency
boveground storage tanks(ASTs) Stainless steel ASTs
storing liquids other than Stainless steel ASTs(for example,milk
petroleum, hazardous substances, or tanks)containing other regulated
asphalt cement are considered other substances are excluded from Minn. R. ch.
regulated substance ASTs if the product 7151.
has the potential to pollute the waters of the
state. Examples include food-based Labeling
products for human or animal
consumption. ASTs containing other regulated
substances must be clearly labeled
Other regulated substance ASTs must be in �ndicating the type of substance stored and
compliance with specific tank requirements the tank's capacity. If there is more than
outlined in Minn. R. ch. 715 L If site one tank, each tank must be labeled with a
capacity for ASTs is greater than one unique tank number.
million gallons,this rule does not apply
and the owner or operator must apply for a Tank piping used for loading or unloading
permit from Minnesota Pollution Control must be labeled so that the person
Agency (MPCA). performing the product transfer can
identify which tank line is connected to
Registration which tank.
The MPCA does not require the If a person is not on site 24 hours a day, a
registration of other regulated substance sign must be posted with the name,
ASTs.Petroleum and hazardous substance address, and telephone number of the
ASTs must be registered(Minn. Stat. § facility owner or operator, ar a local
116.46, subd. 6). emergency response contact. The sign must
be posted so that it can be seen outside any
containment area.
Exemptions
• corrosion protection and corrosion Secondary containment
protection monitoring
Other regulated substance ASTs need 100
• substance transfer areas percent containment area volume of the
• overfill protection largest tank in the containment area. An
additional 10 percent capacity is required
• leak detection for ASTs exposed to precipitation.
• internal inspections for field-erected
ASTs
• soil or ground water sampling during
removal for possible contamination
t-a2-07
Minnesota Pollution Control Agency • 520 Lafayette Rd. N., St. Paul, MN 55155-4194 • www.pca.state.mn.us
651-296-6300 • 800-657-3864 • TTY 651-282-5332 or 800-657-3864 • Available in alternative formats
T
ASTs installed on or after November 2, 1998, need Annual equipment checks to maintain leak detection or
secondary containment constructed of: monitoring and warning equipment must be done. This
includes function and calibration checks in accordance
• compacted clay(12 inches thick with a permeability with manufacturer's guidance.
of 1 x 10-�cm./sec. and has a cover material to
prevent drying and erosion)that is designed and American Petroleum Institute(API)external inspections
certified by a registered professional engineer of field-erected ASTs were required by November 2,
2003, or five years after the initial construction date,
• concrete whichever is later.
• a synthetic membrane
Maintenance
• a geosynthetic clay liner
• the outer shell of a double-walled tank Owners and operators must minimize rust on the tank
exterior and must dispose of water drawn from the
• the lower bottom of a double-bottomed tank bottom of the tank in accordance with any state and
federal regulations.
• fabricated steel
• fiberglass The secondary containment area must be kept free of
cracks, open seams, open drains, siphons, and vegetation
Tanks installed prior to November 2, 1998, were other than grass. Grass is used to reduce erosion.
required to have a dike(could be made of soil)
preventing release to surface water by'November 1, Precipitation must be removed as often as possible to
1998. By November 1, 2003,the containment area had maintain proper containment area volume. If
to meet a minimum permeability standard based upon precipitation exists in the containment area,the tank
the product type being stored, distance from surface volume must be reduced to maintain the 100 percent
water, and depth to groundwater. For questions about capacity of the largest tank in the containment area.
these requirements, see the"Permeability Testing
Guidance for Secondary Containment Areas"fact sheet. Stormwater that collects in the containment area must be
discharged according to state and federal regulations.
Monitoring Safeguard systems must be installed and maintained
For other regulated substance ASTs, someone must be according to the manufacturer's schedules and standards.
present to visually monitor loading and unloading of
product and be able to shut off product transfer before an Record keeping
overfill occurs. For the life of the tank
A visual inspection for tank releases must be conducted Owners or operators of other regulated substance ASTs
at least every 72 hours if the containment area does not must keep for the life of the tank all tank system design
meet the standards for tanks installed on or after records including maintenance and repair
November 2, 1998. If the containment area meets the documentation,third-party certifications, and as-built
standards for ASTs installed after this date,the drawings.
inspection must be conducted at least weekly.
All containment area evaluations for soil permeability
if the tank is double-walled,the inspection must be must be kept for the life of the tank. These evaluations
conducted at least monthly. should include soil classification, soil description,
sample logs,tables for individual permeability tests, and
On a monthly basis, a visual inspection for both new and the hydraulic conductivity of the soil.
existing tanks is required. This inspection must include a
walk through of the site to identify cracks in the Records for external inspections of field-erected tanks
secondary containment area. Visual examination of the must be retained for the life of the tank system.
exterior surfaces of tanks, piping, valves, pumps, and
other equipment for cracks, corrosion,releases, and
maintenance deficiencies must also be conducted. The
monthly inspection must also identify poor maintenance,
operating practices, or malfunctioning equipment.
Other Regulated Substance Requirements for MfnnesoW Pollution
Aboveground Storage Tank • t-a2-07 • Aprtl 2004 CO�ro1��y
Page 2
� , �
For three years Other regulated substance ASTs
All service check and equipment calibration records considered temporary
must be kept for three years. All periodic monitoring Other regulated substance ASTs that are on site between
(72-hour, weekly and monthly)records must be kept for 30 days and a year are considered temporary tanks and
three years. Documentation for monitoring must include must meet the temporary tank requirements. These ASTs
the name of the person conducting the monitoring,the must be labeled"Temporary Storage"and show the date
method used,the date of the monitoring, and the the storage began.
monitoring results.The owner or operator must keep
records indicating that the AST was taken out of service If a person is not on site 24 hours a day,a sign must be
in compliance with regulations. These records must be posted with the name,address, and telephone number of
kept for three years. the facility owner or operator, or a local emergency
response contact. The sign must be posted so that it can
Discharges to a secondary containment be seen outside any containment area.
area Finally,the secondary containment area must be
An owner or operator of another regulated substance constructed and maintained according to the standards
AST must immediately investigate a suspected release to for ASTs installed before November 2, 1998.
a secondary containment area. Moving other regulated substance ASTs
The owner or operator must assess the secondary If another regulated substance AST is moved from one
containment area for damage where product release site to another, the tank must be determined to be sound
occurred and make any necessary repairs. by conducting one of the following leak tests before it is
The owner or operator must notify the Minnesota Duty put back into use.
Officer immediately of discharges to the secondary . tracer gas test
containment area or of other releases. They can be
reached at 800-422-0798 or 651-649-5451. • vacuum test
• air pressure test
Out-of-service requirements . hydrostatic test
When another regulated substance AST is no longer If the other regulated substance AST is moved within the
used, it must be taken out of service or removed. same site and put back into use, it must be determined to
To take the tank system out of service,the tank owner or be sound through a thorough internal and external
operator must: cleaning,degassing, and inspection. You can also
conduct one of the leak tests above to determine the
• Remove all substances from the AST, connected integrity of the tank.
piping, and appurtenances.
• Secure the AST to prevent unauthorized entrance or AST design standards
tampering. An underground storage tank cannot be used as an AST.
• Thoroughly clean the interior of the tank and piping Also,AST providers must comply with industry tank
of all sludge, solids, and residuals. and piping design and construction standards.
• Dispose of tank bottom sludge according to Need more information?
applicable state and federal regulations.
Visit the AST Program at
• Render the tank free of vapors. http://www.pca.state.mn.us/cleanup/ast.html. The site
• Label the tank exterior"Out of Service,"and the has forms, fact sheets, and other information about
date the tank was removed from service. ASTs and AST requirements.
You can also call the MPCA at 651-296-6300 or
1-800-657-3864.
Other Regulated Substance Requirements for Mtnnesoca vollut�or�
Aboveground Storage Tank • t-a2-07 • April 2004 �- tontrolA9e�cy
Page 3
R
Secondary Containment for
Aboveground Storage Tanks
Minnesota
Pollution
COIIt�OI Tanks/Aboveground Storage Tanks#4.01 • December 2008
Agency
econdary containment helps prevent Materials
serious environmental problems The acceptable impermeable materials that
from occurring because of tank must be used for construction of the
releases. While the tank itself is vital to containment area for ASTs installed on
minimize the potential for leaks, secondary November 2, 1998, or later include:
containment is another important safeguard
from potential releases. This fact sheet • compacted clay (if clay is used,it must
outlines the requirements and choices have a minimum of 12 inches
available for secondary containment for compacted clay, be protected with
aboveground storage tanks(ASTs) cover material to prevent drying and
according to Minn. R. ch. 7151. erosion, be designed, inspected, and
certified by a registered professional
engineer, and be tested after
Compatibllity installation to meet a permeability rate
If more than one type of substance is stored to water equal to or less than 1 x 10-'
within a single containment area,the cm/sec)
substances must be compatible with each . a geosynthetic clay liner
other and the containment material.
• concrete
VOlume • a synthetic membrane
For containment areas which are exposed • the outer layer of a double-walled tank
to precipitation,the containment area . fabricated steel
capacity (available space)must be at least
110 percent of the size of the largest tank • fiberglass
in the containment area. Containment areas with tanks that were
For containment areas which are not �nstalled before November 2, 1998, may be
exposed to precipitation,the containment constructed using any of the impermeable
area capacity must be at least 100 percent materials listed above, or may be
of the size of the largest tank in the constructed of native or amended soils that
containment area. have been tested to meet the following
minimum permeability rates for the
A separate containment area is not required applicable substance type and hydrology.
for double-walled tanks.
Soil testing requirements are explained in
the fact sheet"Permeability Testing for
Secondary Containment Areas."
t-a4-01
Minnesota Pollution Control Agency • 520 Lafayette Rd. N., St. Paul, MN 55155-4194 • www.pca.state.mn.us
651-296-6300 • 800-657-3864 • TTY 651-282-5332 or 800-657-3864 • Available in alternative formats
�
Permeability rates to water for secondary
containment areas made of native or amended soils re-November 2, 2008,tanks onl
Substance Classification If ground water or bedrock is If ground water or bedrock is
< 10 feet from grade or AST is within > 10 feet from grade or AST is within
100 feet of Class 2 water 100 feet of Class 2 water
Type A Minimum of three feet of soil at Minimum of three feet of soil at
1 x 10-5 cm/sec 1 x 10�cm/sec
Type B I Minimum of three feet of soil at Minimum of three feet of soil at
' 1 x 10�cm/sec 1 x 10-3 cm/sec
Type C I Minimum of three feet of soil at No minimum permeability standard
1 x 10-3 cm/sec
Type A substances include gasoline, aviation gas, Temp01'aly ta11kS
naphtha, denatured ethanol,hazardous materials, and
mixtures or blends of these with Types B and C Temporary tanks are ASTs located at a facility for more
substances. (Antifreeze is considered a Type A than 30 days, but less than one year. Secondary
substance.) containment areas for temporary tanks must meet the
volume requirements described above, and be
Type B substances include crude oil, diesel, kerosene,jet constructed either of the impermeable materials listed
fuel, fuel oil types one through four, waste oils, and above or meet the applicable permeabiliry rate from the
mixtures or blends of these with Type C substances. table above.
(Virgin lube oil is considered a Type B substance.)
Drainage
Type C substances include asphalt cement, roofing flux, precipitation that collects within the secondary
fuel oil types 5 and 6, and other regulated substances containment area must be discharged in compliance with
which are not petroleum-based and not hazardous all state and federal regulations
materials.
Release detection design Containment evaluation
For ASTs installed on November 2, 1998, or later, and Owners and operators of tanks must retain, for the life of
for ASTs installed before that date which are lifted or the tank system,the following written records of
moved after that date, the area of secondary containment sampling and testing used to evaluate permeability of
which is directly under the tank must be designed to soil containment areas:
allow for visual detection of a release of a substance . classification of soils used in containment area
through the tank floor. construction
Release detection designs that can be used include: • soil descriptions and logs of each sample location
• tank is elevated • a table of individual permeability tests
• continuous concrete slab under the tank( in the case • Permeability of the soil expressed as cm/sec for each
of a Type A substance, slab must be treated with sample location and for each containment area
material that is impermeable to the substance)
• fiberglass or steel pad under the tank Need more information?
• synthetic membrane under the tank Visit the AST Program at
www.pca.state.mn.us/cleanup/ast.html. The site has
• double-walled tank(shop fabricated) forms, fact sheets, and other information about ASTs
• double bottom tank(field erected) and AST requirements.
You can also call the MPCA at 651-296-6300 or
1-800-657-3864.
Secondary Containment for Aboveground Storage Tanks • t-a4-01 • December 2008 � MEn+tiesaw Po��uiton
�.— Controlllger►cy
Page 2