1.1 G. Comment, Adam Edwards
Comment: SWPPP - Stockpile: Any soil or dirt storage piles containing more than ten cubic
yards of material should not be located within 25-teet from a roadway or drainage channel. If
remaining for more than 14 days, they shall be stabilized by mulching vegetative cover, tarps or
other means and enclosed with down gradient perimeter sediment controls. Piles which will be in
existence for less than 14 days shall be enclosed with perimeter sediment controls.
Comment: SWPPP: The site must have a construction entrance (per city standard detail) that
must be provided and maintained.
Comment: SWPPP - Sediment/Erosion Control: Perimeter sediment control measures should be
installed by the contractor and inspected by the City prior to any work, including demolition. The
contractor must provide a minimum 24-hour notice prior to inspection.
Comment: SWPPP - Street Cleaning: Streets shall be cleaned and swept within 24-hours
whenever tracking of sediments or soils occurs and before the site is left idle for weekends and
holidays.
Comment: Adjacent roadway, curbing and drainage structures must be protected.