HomeMy WebLinkAbout06-28-1993 HRA Meeting PacketMINUTES OF THE HRA MEETING
HELD JUNE 28, 1993
ROLL
The HRA met on the above date with the following members present:
Chair Gabriel Jabbour, Charles Kelley, Edward Callahan, J. Oiann
Goetten and JoEllen Hurr. The following represented the City staff:
City Administrator Ron Moorse, Public works Director John
Gerhardson, and Recorder Teri Naab. Chair Jaboour called the
meeting to order at 7:15 P.M.
(#1) APPROVAL OF MINUTES
It was moved by Goetten, seconaea oy Cai'anan. to approve the
minutes of the May 24. 1993 HRA meeting. Ayes 5, nays 0.
(#2) PAYMENT REQUEST #3 - FINAL A.U.S. COMMUNICATIONS, INC.
Moorse exp I a i ned this is the final .:i/ment. inciuamg the retainage
amount, for voice and data cabling. Everything nas been installed
and tested according to specifications.
It was moved by Caiianan. seconced by Gcetten. to approve Final
Payment Request #3 for A.U.S. Communications. Inc., in the amount
of $1,647.00. Ayes 5, nays C.
(•3) PAYMENT REQUEST 81 - INTEGRATED COMMUNICATIONS, INC.
Moorse reported this payment reflects the cost for moving and
expansion of the tetephone system.
Jabbour questioned whether the amount is to be paid by internal
I evy.
Moorse noted the portion for the Pol ice Department wi I I be paid
from the General Fund, the majority of the cost is paid by the
Bui Iding Fund.
It was moved by Callahan, seconded by Kel
Request 0* tc Integrated Communications.
$7,763.76. 5, nayS 0.
ey, to app'^ove Payment
Inc. in the amount of
(•4) CITY FACILITIES CHANGE ORDER
Moorse exp I ained all items have been included m the budget updates
under ’pending". The majority of the items were included in the
original plans, but during the bidding process were overlooked.
Hurr noted she has a difficult time with the wording "missed
items", and stated that is what the City hired the architect and
construction manager for. She stated it appears whenever a mistake
1
HINUTES OF THE HRA MEETING
HELD JUNE 28, 1993
ts made, the City is responsible.
Jabbour expressed frustration over items that were ordered
incorrectiy.
Moorse noted the items that were missed in-the p»'ocess wou I d still
b^ the responsibility of the City, whether at tne beginning or now.
Jabbour felt there were items that the Council was not made aware
of that were installed, such as tne lock change.
It was moved by Jabbour, seconded by Hurr, tc cirect staff to
remove all the changed locks and return for full credit.
Qoetten asked staff for a reasonable explanation of the cnange.
Moorse suggested they reconstruct the chronology of events leading
to the change.
Kelley referred to a memo from Cec ember 13 92 listing 26 i terns which
had not been funded for at the time.
Moorse noted the majority of those items have been provided at no
cost. He said the signage has not yet been reviewed by Council and
they wi I I need to approve expenditure of additional money for such.
Kelley requested a status report on the 26 items.
Hurr suggested the architect and construction manager appear before
the Board to review the changes.
Jabbour noted it is difficult to determine if the changes are due
to design change or building flaws. He said he would like to put
an end to the Issue, and added there will be no more approval of
additional items without going through the process. He withdrew his
motion and suggested they meet with the architect to clarify the
issues.
Callahan felt the solution was through negotiations with the
architect, and suggested they approve the change orders and review
further at their next work session.
Mifhd r ew her second to the mot ion. She felt if the suppliers
were paid, the City would lose leverage with the architect.
It was moved by Jabbour, seconded by Callahan,
following amounts in change orders:
Allied Mechanical Change Order #3
to approve the
$2,701.00
Ilib
MINUTES OF THE HRA MEETING
HELD JUNE 28. 1993
2.070.00
20.■457,50
3.106.00
6,177.00
LaForce Change Order #3
Mid-west Asphalt Change Order «1
Mannstedt & Sons Change Order «3
Gephardt Electric Change Order #3 Balance
and directed staff to report back to the Board at the next meeting
on items that were ordered in duplicate. Ayes 4, nays i. Hurr voted
nay,
Jabbour adjourned tne meeting at 7:45 p.m. to the regular Council
meeting and reopened the meeting at il:05 p.m.
(«5) REVIEW OF LANDSCAPE PLAN
Moorse explained this is a request for direction on the plantings
for the berm at the entrancb.
Hurr felt they should cover the berm wth grass as prairie grass
would be more difficult to maintain.
Goetten expressed regret that tne Soara ^as not asued to review
the landscape plan *n front Tne butiding as they we^^e in charge
of approval of such, and adoeo at this point she did not care what
they planted on the berm.
Kelley questioned the plantings along the Pub Iic works buiIding and
asked if additional money has been budgeted for maintenance as it
is important to maintain the appearance on the outside.
Moorse stated that would be included in the 1994 budget.
All members agreed the berm should be seeded with mowable grass.
ADJOURNMENT
It was moved by Callahan, seconded by Kelley, to adjourn the
AGENDA FOR HRA MEETING
MONDAY* JUNE 26* 1993* 7:15 F.M.
ORONO COUNCIL CHAMBERS
2780 KELLEY PARKWAY* ORONO* MINNESOTA
1. Approval of Minutes May 24, 1993
2. Payment Request No. 3 - Final A.U.S. Communications, Inc.
3. Payment Request No. 1 - Integrated Communications, Inc.
(Telephone system)
4. City Facilities Change Orders
5. Review of Landscape Plan
/
MINUTES OF THE HRA MEETING
HELD HAY 24. 1993
ROLL
Th# HRA m«t on the above date with the following members present;
Chair Gabriel Jabbour, Charles Kelley, Edward Callahan, J. Diann
Goetten and JoEIlen Hurr. The following represented the City staff:
City Administrator Ron Moorse, City Attorney Kevin Staunton and
Recorder Terl Naab. Chair Jabbour called the meeting to order at
7:18 P.M.
(#1) APPROVAL OF MINUTES
It was moved by Goetten, seconded by Callahan, to approve the
minutes of the April 12, 1993 and April 28, 1993 HRA meetings. Ayes
5, nays 0.
(•2) RATIFICATION OF CITY COUNCIL ACTION RELATED TO CITY FACILITIES
FURNITURE
It was moved by Callahan, seconded by Goetten, to ratify the
actions of the City Council related to City facilities furniture.
Ayes 5, nays 0.
(83) CITY FACILITIES CHANGE ORDERS
Moorse reported this reflects a number of change orders, all of
which have been reflected In the budget numbers provided to the
HRA members.
Goetten questioned the savings realized due to the cold storage
unit not being built.
Hoorse stated the electricity was provided and an underground
conduit was Installed to the location of the light stand. He said
If a cold storage unit Is built, a portion of the electrification
will still need to be completed.
Jabbour questioned the $8,000 amount for the conduit and light.
Kelley asked If the dollars have already been spent for such.
Moorse noted the conduit is In place, but the light pole Is not.
Kelley asked If the conduit could carry other I terns such as phone
wires.
Moorse stated he believed It was large enough to do so.
Goetten said she wanted a break down on this cost.
1
MINUTES OF THE HRA MEETING
HELD MAY 24, 1993
CHANGE ORDERS - CONT.
Jabbour raiterated the HRA should not be faced with approving a
change order after the fact. All members agreed.
Kelley inquired about the standards being used for the design of
the exterior monument sign, and felt It should match the Interior
sIgnage.
Moorse said the Architect was putting together a proposal which
would be ready for review next week.
Jabbour suggested an additional meeting with the Architect to
resolve other pending issues. He feit It would be helpful for staff
to prepare a list of flaws In the building, and recommend a
permanent remedy.
Qoetten inquired as to the bidding situation with the Architect.
Moorse said that would be reviewed this week.
It was moved by Qoetten, seconded by Callahan, to approve the City
facilities change orders as presented, with the exception of Item
•7C. Ayes 5, nays 0.
(•4) APPLICATION A CERTIFICATE FOR PAYMENT 916
Moorse reported the Architect and Construction Manager have
recommended payment, and staff has confirmed that the money Is due.
It was moved by Callahan, seconded by Qoetten, to approve the City
facilities change orders as presented. Ayes 6, nays 0.
ADJOURNMENT
It was moved by Callahan, seconded by Qoetten,
meeting at 7:33. Ayes 5, nays 0.
to adjourn the
Gabriel Jabbour, Chair
ATTEST:
Dorothy M. Hal I In, City Clerk
3
TOs
WROUi
DATB:
SUBJICTt
Mayor and City Council
Ron Moorse, City Administrate
June 23, 1993
‘V.
%
Payment Request No. 1 Integrated Communicatio^fevs<4ms,
Tne. (Teleohone system)
Integrated Communications Systems, Inc. is the vendor who relocated
the city's phone from the former facilities and provided expanded
equipment to serve the needs of the new facilities. The total cost
was $7,763.76. The system has been installed and tested and is
working satisfactorily. There is one item that has not been
provided, that is a more rugged type of phone for the outer Police
lobby. It is recommended that at this time the contract amount be
paid less a 10% retainage amount. The amount to be paid is
$6,907.30.
•.'1V:'
TO:
FROM:
DATE:
Orono H.R.A.
Ron Moorse, City Administrator
June 25, 1993
COUNCaMBIM
JUN 2 8 1993
CUVOFOMNW
V
SUBJECT: City Facilities Change Orders
The attached change orders have been reflected in the periodic
budget updates provided to the Council. They have been shovm as
pending items during the period when the Construction Manager and
Architect were completing their review to ensure the items were
done as cost effectively as possible and that the pricing was
reasciable. Most of these items are not actual changes or new
items, but rather are items that were missed between the various
sub-contracts.
1. Allied Mechanical. This is an add of $2,701.
a. ) $1,085 is for miscellaneous job coordination-type plumbing
revisions. These revisions generally occurred when the
locations of the plumbing items conflicted with the placement
of other sub
contract items.
b. ) Additional air and water piping was needed to serve the
public works service equipment; such as the pressure washer
and the air compressor. The drawings for this equipment were
not completed when the mechanical plans were completed and
bid. The service equipment required changes in these
mechanical plans.
2. LaForce. This is an add of $2,070.
a. ) $385 to change locks to match revisions to the Police
secured area.
b. ) $935 to change several locks in the Public Works building.
These included adding locks to the offices and changing locks
in several work rooms that had doors that automatically lock.
c. ) $750 to replace a door that did not match the size of the
closet. The closet had been reduced in size from the original
plan.
3. Mid-West Asphalt. This is an add of $20,457.50.
The plans for the Public Works yard area indicate the rear
area is not to be paved. The plan calls for 8 inches of class
V base and 2 inches of class V limestone as the wearing
course. These costs were not included in the original site
preparation contract and were then missed in the building
plans.
4. Mannstedt and Sons. This is an add of $3,106. This is the
cost of sales tax on the steel supplied after the new sales
. k
i:'
5.
.tax law went into effect.
GoDiiaz'dt Electric. At the last H.R.A. meeting the H.R.A.
pAOuested additional detail on item 6 of the Gephardt Electric
change order #3. This was an add of $6,177. The detail of
this amount is as follows:
a.) Provide a light pole and light fixture and wiring for the
salt and sand mixing area - $2,776.
b.) Revise the wiring for the air compressor to provide a 100
amp switch versus a 60 amp and a 70 amp circuit breaker versus
a 60 amp - $1,214.
c.) Revise wiring for the high pressure washer to provide a 60
amp switch versus 30 and a 40 amp circuit breaker versus 20
$1,048.
d.) Add exterior electrical outlets at each of the four
conditioner condensing unit grouping locations to meet code
related to providing electrical power for the maintenance of
the units - $1,139.
•I
S
5
i
KRAUS-ANDERSON CONSTRUCTION COMPANY
CONTRACTORS .S CONSTRLCriON MAN AGERS
May 21, 199S
Mr. Tom Kuchn
Oty of Orono
RO. Box 66
Crystal Bay. MN 53323
Re: Orono City Hall and
Public Works Buildings
K/A Project #4059
Dear Mr. Kuehn:
• «
■/
■ /
T
Enclosed are four copies of change orders for the following contractor (s):
Allied Mechanical
LaForce Hard%irare
Change Order No. Three
Change Order No. Three
Please sign all copies and return three of each to KrauscAnderson. We will
distribute to the appropriate parties.
Very truly yours,
KRAUS-ANDERSON CONSTRUCTION COMPANY
Imn DaJohn Davies
Project Manager
p/lp
Enc.
^tinwiapofa Division
S25 South 8th Sire«t, Minneapolis, MN B3404
Phone; (6:2) 332-7281 FAX; (612) 332-8739
Equal Opportunity Employer
CHANGE ORDER
CONSTRUCTION MANAGEMENT EDITION
AIA DOCUMENT C701/CM
Distribution to:
OWNER □
ARCHITECT □
CONSTRUCTION MANAGER □
CONTRACTOR □
FIELD □
OTHER □
V S.,'
V
PROJECT:
(name, address)
Orono City Hall and
Public Works Buildings
TO (Contractor):
Allied Mechanical Systems
340 Michigan Street
Hutchinson, MN 55350
CHANCE ORDER NUMBER: Three (3)
INITIATION DATE; January 22, 1993
ARCHITECT'S PROJECT NO: 1124.04
CONSTRUCTION MANAGER'S
PROJECT NO 4059
CONTRACT FOR Mechanical
CONTRACT DATE: May 11, 1992
You are directed to make the following changes in this Contract
Add to contract for items 1-4 listed
on attached sheet.Total Net Add; $2,701.00
Not valid until signad by iha Ownar, the Architect and the Construction Manager.
Signature of the Contractor indicate* agreement herewith, including anv adiusiment m the Contract Sum or the Contract Time.
390,000.00.
(9,758.713
380,241.29.
The Ofiginal (Conuact Sum) (Guaranteed Manimum Cost) was ............................................
Net change by previously .uthorized Change Orders ........11-, . •# 2*................................
The (Contract Sum) (Guaranteed Maximum Cost) prior to this Change Order was .............
The (Contract Sum) (Guaranteed Maximum Cost) will be (increased) (decreased) (unchanged)
by this Change Order................................................................................................ » 2,7gi.uu.
The new (Contract Sum) (Guaranteed Maximum Cost) including this Change Order will be ... S 3B2,
The Contract Time will be (ittcreased) (decreased) (unchanged) by w -s i oo
The Oara of Substantial Completion as of the date of this Change Order therefore is December 31, 1992
Recommended:
Kraus-Anderson Construction Company
CONSTRUaiON MANAGER ’
Mini^apolis. MN 55404
AOORESl^
App
Bo4lman Kro Pfister and Associates
DATE
Agreed To:
Allied Mechanical Systems
y
lorized:
City of Orono
CONTRACTOR
^^^i^tchinson^ MN^ ^5350
OWNER
Crystal Bay, MN 55323
ADDRESS
r-t DATE DATE
« •AIA CAUTION: You ehould algn an original AIA document which hae Ihia caution prinlod In red,
An original aaaurea that changaa will not be obscured at may occur whan documants are reproduced.
e 1SW C7t1/CM^t9Sa
4
A-lHcd Mechanical Systems
Chamye Order #8 - Attachment
1. Add to contract for revisions to plumbing fixtures
as noted in Proposal Request No. 12.
2.Deduct to contract amount for changing to poly^
drains ii^eu of cast iron drains in sally port
-------------------------
Ad<r to contract for miscellaneous plumbing
revisions as noted on Allied Change Order
“ It No. 9. Includes items 1-5.
4. Add to contract for piping revisions for airland
water piping in public worlu according to Proposal
Request No. 21.
Add: $ 123.00
Deduct: ($ 603.00)
Add: $1,085.1
Add: S2.096.(
Total Net Add: $2,701.00
CHANGE ORDER
CONSTRUCTION MANAGEMENT EDITION
AM DOCUMENT C701/CM
piiQirpT. Orono City H^il ^nd
(o.n»,addrejsl Public Works Buildings
Crystal Bay, MN 55323
TO (Contractor):
LaForce Hardware and
Manufacturing
1060 West Mason Street
Green Bay, WI 54303
QV
Distribution to:
OWNER O
ARCHITECT □
CONSTRUCTION MANAGER □
CONTRACTOR □
FIELD □
OTHER O
CHANCE ORDER NUMBER: Three ( 3 )
INITIATION DATE:
ARCHITECT'S PROJECT NO: 1124.04
CONSTRUCTION MANAGER'S
PROJECT NO: , , „ ^Hollow Metal, Wood
CONTRACT FOR Doors ^ Finish Hdwr.
CO.'ITRACT DATE: May 11, 1992
of item »3
on Change Order No. 2. Amount was previously
included with revisions to Proposal Request No. 6.
2. Add to contract for revisions to locltsets as
noted in Proposal Request No. 30.
3. Add to contract for furnishing new tracJc and
doors for bi”fold door opening B114A.
Add $ 385.00
Add: $ 935.00 6-^iC
Add: $ 750.00 .
Total Add: $2,070.00
35.465.00
6,590.00 .
42.055.00 .
Th« orifinal (Contract Sum) (Guaranteed Maximum Cost) was ........................................... S
Net change by previously authoriaed Change Orders .......«1.#. • 2...................................... »
The (Contract Sum) (Guaranteed Maximum Cost) prior to this Change Order was ............... S
The (Contract Sum) (Guaranteed Maximum Cost) will be (increased) (decreased) (unchanged)
by this Change Order ............................................................................. * • -----:
The new (Contract Sum) (Guaranteed Ditaximum Cost) including this Change Order will be ... J
The Contract Time will be (increased) (decreased) (unchanged) by . De'^ember 31, 1992
The Date of Substantial Completion as of the date of this Change Order therefore is
2,070.00
44,125.00
Recommended:
Kraus-Anderson Construction Company
CONSTRUCTION MANAGER , , . ^ ,
Minneapolis, MN 55404______________
AOORI
Approved:
Boaifnan Kroo:. Pfister and Associates
DATE
Agreed
XjaForce_JHardware_and_Maitu^^£jturijn2
CONTRACTOR
Green Bav, WI >^4303'''^ - - --------SiSi------Y. ... J99JOO..SS
toATE BV
Authorized:
City of Orono
OWNER
Crystal Bay, MN 55323
DATE
AIA CAUTION: should elBn an orlQlnsI AIA document which hse Ihle caution printed In
An original aeeuret Ihsi changee will not bo obscured ae may occur when documonte are reproducod.
niAMMT amUtM • CMANCt OtOIt • CONSTRUCTION MANAClMfhBT lOlTlQN e |UN| ^^TlQN •.wlwTi r Niw Yoxx avinui nw . wasmincton . dc . x»s C7f1/CM~T
KRAUS-AN PERSON CONSTRUCTION COMPANY
rnsFR v/Tf^KSn ( ru >\ -.r-.s \c.lr>
June 3,1993 fn.
I w
» .
• I
Mr. Tom Kuehn
City of Orono
P.O. Box 66
Crystal Bay, MN 55323
QL'M' T tia-
Orono City Hall and
Public Works Buildings
K/A Project #4059
Dear Mr. Kuehn:
Enclosed are four copies of change orders for the following contractor(s):
Midwest Asphalt
.Mannstedt and Son
Change Order No. One
Change Order No. Three
Pleajftv sign all copies and return three of each to Kraus-Anderson. Wc will
distribute to the appropriate parties.
Very truly yours,
KRAUS-ANDERSON CONSTRUCTION COMPANY
John Davies
Project Manager
JD/lp
Enc.
■‘j
Minncapolb OMawn
525 South 0lh Street, Minneapolis, MN 55404
Phone: 1612) 3J2-728I ?^AX: (612) 332*0739
Equal Opportunity Employer
CHANGE ORDER
CONSTRUCTION MANAGEMENT EDITION
AIA DOCUMBNT C701/CM
Distribution to:
OWNER □
ARCHITECT □
CONSTRUCT ION MANAGER □
CONTRACTOR □
FIELD □
OTHER □
PROJECT:
(name, address)
TO (Contractor):
Orono City Hall and
Public Wor)cs Buildings
Midwest Asphalt Company
P.O. Box 5477
HopJcins, MN 55343
CHANCE ORDER NUMBER: One (1)
INITIATION DATE: January 22, 1993
ARCHITECT'S PROJECT NO: 1124.04
CONSTRUCTION MANAGER'S
PROJECT NO: ^0^9
CONTRACT FOR: Bituminous Paving
CONTRACT DATE: May 11, 1992
You are directed to make the following changes in this Contract
Add to contract amount for items
1-3 listed on attached sheet.Total Add: $20,457.50
Net valid until slfncd by tht Owner, the Architect and the Construction Manager.
Signature of the Contra^or indicate* agreement herewith, including any adjustment in the Contract Sum or the Contract Time.
41,100.00.
-0- .
41,100.00.
The original (Contract Sum) (Guaranteed Maaimum Cost) was..............................................
Net change by previously authorized Change Orders ............................................................
The (Contract Sum) (Guaranteed Maximum Cost) prior to this Change Order was..............
Tho (Contract Sum) (Guaranteed Maximum Cost) will be (increased) (decreased) (unchanged)
by Ais Change Order......................................................................................................
The new (Contract Sum) (Guaranteed Maximum Cost) including this Change Order will be ...
The Contract Time will be (increased) (decreased) (unchanged) by ^ s o
Tho Date of Substantial Completion as of the date of this Change Order therefore is December 31, 1992
Recommended: Approved; ^ _
Kraus-Anderson Construction Company Boarpan Krjai^/Pf ister and Associates
20,457.50
61,557.50’
CONSTRUCTION MANAGER
Minneapolis, MN 55404
ADDRESS
•Y DATE
Agreed To:
Midwest Asphalt Company
CONTRACTOR
Hopkins, MN 55343
•V <7 DATE
rman Kr/9^ajp:
ARCHITlfT /Minoeapadis yMN 55401
^2^
Authorized:
City of Orono
OWNERCrystal Bay, MN 55323
ADDRESS
DATE
AIA CAUTION: You ghould elgn an original AIA documont which hoe thie caution prinlod In rod.
An original aeturte that changaa will not ba obacurad aa may occur whan documonta aro roproducad.
oei/CM • CHANci otoie • coNSTaucrioN manacimcmt ioition . iuni ism ioition • aia *
• THI AMieiCAN INSTirUTI OT AKCMITICTS. 17JS NfW YORK AVtNUI. N.W., WASHINGTON. O.C.
■eenaeeeiMaaai
C7f1/CM — 19M
OvleW pwnoiHion.
4
1.
3.
Midwest Asphalt Company
Chanye Order #1 « Attachment
Furnish additional labor and material necessary
to install 8” of class five base material in the gravel
areas of public works.Add: $13.4
Furnish additional labor and equipment
necessary to remove snow and grade lot as
directed on November 7th, 9th and 12th.Add; $ 997.50
Furnish additional labor and material necessary
to install 2" of class five 100% crushed limestone
in gravel areas of public works.Add: f 6.060.00
Total Add: $20,457.50
CHANGE ORDER
CONSTRUCTION MANAGEMENT EDITION
AIA DOCUMENT C701/CM
Distribution to:
OWNER □
ARCHITECT □
CONSTRUCTION MANAGER □
CONTRACTOR □
FIELD □
OTHER □
'll?
PROJECT:
(name, address)
TO (Contractor):
Orono City Hall and
Public WorJcs Buildings
CHANCE ORDER NUMBER: Three ( 3 )
INITIATION DATE: January 25, 1993
ARCHITECT'S PROJECT NO: 1124,04
«SrSicou2t siuth CpNS3)CTION MANAGER'S
Minneapolis, MN 55409 PROJECT NO:4059
CONTRACT FOR: Me^al Fabrication
CONTRACT DATE:
You are directed to malce the following changes in this Contract:
Add to contract for sales tax that needed
to be paid but was not included in original
contract amount.Add; $3,106.00
Not valW until siintd by tho Ownor, the Architect and the Construction Manager. . u
Signature of the Contractor indicates agreentent herewith, including any adjustment in the Contract Sum or the Contract Tinte.
40.460.00
9,333.00
49.793.00
3,106.00
52,899.00
December 31*, 19 9^2
The original (Contract Sum) (Guaranteed Manimum Cost) was • • • • • • y..............................
Net change by previously authoriaed Change Orders..........E l.«. J 2................................
The (Contract Sum) (Guaranteed Maximum Cost) prior to this Change Order was .............
The (Contract Sum) (Guaranteed Maximum Cost) will be (increased) (decreased) (unchanged)
by this Change Order............................................... — ........................ ..........
(Contract Sum) (Guaranteed Maximum Cost) including this Change Order will be ...
The Contract Time will be (increased) (decreased) (unchanged) by
The Date of Substantial Completion as of the date of this Change Order therefore Is
Approved:
Boarm^D_-J^oos Pfister and Associates
CONSTRUCTION MANAGER ^^ [Z ITTni 7/ JMinneapoUfli MM
Recommended:
Kraua»AnderaQ)n Construction Company
Minneapoxxa, an
DATE
Agreed To:
/ATE
and Son. Inc.
lorized:
Citv of Orono
roR
Minneapol
AOORISS"
ia. MN 55409
<
OWNER
Crystal Bay, MN 55323
OATi
ADDRESS
DAn
AIA CAUTION: You ehouM sign an original AIA document which has this caution printed In red.
An original aaaurea that changes will not be obscured as may occur when documents are reproduced.
... • CHANCI oacts • COHSTtUCTlON MANACSMINT IOITION • lUNI ISaS fOITION . Aixe
om a Seuican instituti or aschiticts . irss nsw votx avinui . n w . wash »»<(C ton . d c . jooos C7B1/CM —19M
tUnaaanaae ipyeiCvM
TO:
PROM:
DATS:
Mayor and City Council
Ron Moorse, City Administrator
June 23, 1993
SUBJSCTx City Facilities Landscaping Plan
%
%
The majo. ity of the landscaping for the city facilities has now
been installed. The large barm area at the main facilities
entrance I’as a 2'\i' wide strip of sod laid around the entire
perimeter. The landscape plan calls for the remainder of the berm
to be seeded with tall grass which would be left to grow naturally
and would not be mowed. The landscape architect wanted to create
a natural setting at the entrance rather than a manicured setting
for the facilities. Prior to doing the seeding, staff would like
some direction from the Council about whether the Council prefers
to keep that berm in a natural state rather than seeding it with
regular grass and keeping the entire beirm mowed.
■%
I
TO:
PROM:
LXTB:
>/
Orono HRA
Ron Moorse, City Administrator
June 25, 1993
SUBJSCTt City Facilities Update
CILMBmNB
3 1993
l Y OF ORONO
All items related to the construction of the buildings are
substantially complete. There are a number of punch list items
remaining and a number of concerns related to the building that
remain to be addressed. I have attached a copy of a letter sent to
the architect and construction manager identifying items needing
correction and other remaining concerns regarding the building.
The major items remaining to be completed are specific items
separate from the buildings themselves. They are as follows:
1. Completing the paving of the parking area and paving the floor
of the salt and sand storage building - $2,800.
The landscaping is nearly complete but has not been billed.
This amount is $35,884.
The salt and sand storage building is substantially
complete but has not yet been billed. This amount is
$36,400.
The fuel storage tank and fueling system has not yet been
installed. The cost is $51,000.
The demolition of the old City Hall buildings has not been
completed. The remaining cost is $16,000.
In addition to these items, there is approximately $50,000 of rough
carpentry and drywall work that has been completed but not billed.
The City is also holding $264,000 of retainage related to the
various contracts.
2.
3.
4.
5.
r:
F
O o//
/ •*.
. .V J —.
.\
\'CITY of ORONO
>*/
A» •■■
//
//
MuaidptlOflka
PMOIBc*Boti64
CfTitat B«};MI mi0M> 5532M0M
June 24, 1993
Jack Boarman
Boarman Architects, Inc.
222 North 2nd Street
Minneapolis, Minnesota 55401
Dear Mr. Boarman,
ust Of Ton«";ns “" 'nt^aSlicfes
by city staff.
1.
Look into providing additional capacity to draw fresh air
5S?o the building through the HVAC system.
2 .The heat vents in the ceiling do not provide sufficient
warm air to the floor level.
3.The speakers podi.™ noT^een as^Fp^iim
fxinctional. It is too iow alao it does not
4.
Road.
5.The overhead ///twoTtlft %ople.leaves too little space for two stacr peop
6.
rhe reception counter is too
Io:."Thr|h«"w/itTng surface needs to be added.
7.«at ion*l«a''«e loafed a^ve I'he ”o”k'surfIce'creat ing
a cluttered appearance.
telephone • FAX--ffMPl«
Jack Boarman
June 24, 1993
page 2
e.
9.
10 .
11.
12.
13.
14 .
15.
16.
17.
18.
19.
20 .
21.
22.
23 .
24 .
The locks on the Administrative and Council Chambers
lobbies are on the outer doors. This means a person has
to unlock the door to get in from the weather. Although
there is an overhang, it is not sufficient to protect
during a rain storm.
There is a need for at least one additional light
standard in the Police parking lot area.
A solution needs to be worked out regarding the locking
of the Police lobby area.
The interior signage needs to be completed.
The exterior signage including a monument sign needs to
be completed.
Allied Mechanical did not obtain a permit for its work.
The toilet is lose in the link Men's bathroom.
The sprinkler system has not had final inspections and
testing.
The dumpster needs a gate to provide a screen.
the sun has moved north additional needs for window
treatments have been identified.
The lights on the security key pad are inoperative on the
rear door and Property Room of the Police Department.
The holding cells. Police Department link, and Police
conference room will not keep am even temperature.
The garage floor is broken and sloping in the wrong
direction.
There are several pieces of incorrect ceiling tile in the
Men's bathroom in the Police Department.
The rear Police Department door is warped and closes
improperly.
The sidewalk to the rear door of the Police Department is
cracked.
There is no shower curtain in the Women's bathroom.
Jack Boarman
June 24, 1993
page 3
25. The Norcon intercom system (right side) to the front
lobby has heavy reverberation.
26. There is no baseboard in either the property room or the
garage storage area.
assistance of the architect and construction manager.
Sincerely,
Ronald J. Moorse
City Administrator
cc: John Davies, Kraus-Anderson Construction Co.