HomeMy WebLinkAbout11-16-1987 Planning MinutesMINDTBS OF THE PLAmilHG COMMISSION TING HELD NOVEMBER 16, 1987
Km AHCE 7:05 P.M.
The Orono Planning Commission met on the above date
with the following members present: Acting Chairman
Bellows, Johnson, Hanson and Brown. Taylor arrived at
7:18 P.M. Chairman Kelley and Cohen were absent. The
following represented the City staff: Building & Zoning
Administrator Mabusth, Assistant Planning & Zoning
Administrator Gaffron, and City Recorder Peterson.
CounciImembers Goetten and Callahan were also present.
#1218 THE ESTATE OP ROTH SMITH
387 ORONO ORCHARD ROAD
PRELIMINARY SUBDIVISION
PUBLIC HEARING 7:0S>7:13
The Affidavit of Publication and Certificate of Mailing
were noted.
Attorney Betsy Baker was present representing the Estate
of Ruth Smith.
Mabusth explained the request to subdivide a 16.1 acre
tract into 2 lots as follows:
Lot 1 *= 2.706 acres total (2.62 acres dry)
Lot 2 = 13.426 acres total (11.1 acres dry)
All existing structures appear to meet required setbacks
for the RR-lB zoning district. Staff recommends tabling
the application pending resolve of the location of
existing septic system on Lot 1; amending the
preliminary plan to designate wetlands to east on Lot 2
and redefine dry buildable area on Lot 2; realign shared
lot line for Lots 1 and 2 and designate a platted access
corridor for Lot 2 to Orono Orchard Road.
It was noted in staff's memo the issue of the transfer
of land by Spencer Smith to Cedric Dettloff in the late
60's. Planning Commission will be expected to make a
recommendation to Council regarding the issue of the
illegal sale and violation of the subdivision
regulations of the City.
Regarding the penalty. Attorney Baker stated that the
property is owned by the estate and the income from the
estate goes to three charities (The National Wildlife,
The World Wildlife Fund, and The Christian Children's
Fund), and therefore, enforcing a penalty on the estate
would not actually be penalizing anyone. The estate
agrees that the application should be tabled at this
point. She noted that the estate does not own the
property over which the new access would be located,
however, they are trying to work out this situation.
She noted that the issue regarding the dedication of
right-of-way will remain regardless of this subdivision.
i
MiaOTBS OF THE PUUnilHG COMMISSIOfl TING HELD NOVEMBER 16, 1987
11218 THE ESTATE OF ROTH SMITH CONTIM1
Hanson noted that he has a personal interest in this
property but no financial interest, therefore felt there
was no problem with voting on this application.
Brown noted that several of the accessory structures on
the property are in a state of disrepair and asked how
the City could deal with that.
Mabusth stated that the condition of the accessory
structure are not related to the subdivision, hoewever,
the City can inspect the structures and consider them
under separate hazardous buildings proceedings.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Bellows, seconded by Johnson, to table
this application pending additional information per
staff recommendation. Motion, Ayes 4, Nays 0.
#1104 GREGG PERL
309 WESTLAKE STREET
VARIANCES
CONTINUATION OF PUBLIC BEARING 7:14-7:22
Gregg Perl was present for this matter.
Gaffron explained the request for rear and side setback
variances and height variance to construct an addition
to existing residence. Applicant requests a setback
variance for the garage to be located 2' from the house
structure, which staff recommends should be denied and
structures should be attached for safety reasons.
Regarding the height variance, he explained that a
variance would not be required if the peak did not have
open space, however because the peak is open space with
window, a variance is required. Regarding the septic
system, applicant plans an interim repair of the system
until it is known whether City sewer will come in in the
next few years. If sewer does not come through, a mound
system is anticipated with no alternate site tested to
date. Staff finds no problem with the proposed interim
repair.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Hanson, seconded by Johnson, to
recommend approval of the variances per staff
recommendation including attaching the garage to house
structure. Motion, Ayes 5, Nays 0.
■nniTBS or the plaioiiiig commissioh rriHG HELD EGV1 16, 1987
•1107 N. LEHIS/E. TRETTBL
475 LIEDEH AVBHUE
VARIAHCE
COHTIHUATIOH OP PUBLIC HEARIEG 7:24-7:56
William Lewis and Kathleen Trettel were present for this
matter.
Gaffron explained the request for a lot area variance
for construction of a residence. The lot is .61 acres
in an area zoned 1 acre. The .61 acre lot size is
consistent with the neighborhood lots. He reviewed lI.c
required setbacks that must be met on the lot in order
to build a house. The lot has been assessed for City
sewer. He noted that the neighbors are concerned with
the drainage and existing culvert.
Mr. Lewis stated that prior to buying the lot a lot area
variance was granted and noted they have been paying the
sewer assessment for a buildable lot.
Gaffron read the minutes from the August 11, 1980
Council meeting which approved the lot area variance.
Bellows stated she was not convinced that the lot was
buildable. She was concerned with the access and
structure location.
Mr. Lewis stated he planned to build in the next couple
of years noting he could not build this year because he
is currently working in Nashville, Tennessee.
Marty Blocker, 450 Linden, felt Planning Commission
should not make an objective decision until reviewing
the access, location of structure, and elevations.
Mr. Lewis stated that would require a lot of investment
and detail prior to obtaining a variance.
Hanson shared Bellows' concern regarding addressing the
access, but felt the building envelope does allow a
buildable house.
Regarding the access, Mr. Lewis stated they have
considered access off of Oak Street given the steepness
of a driveway off of Linden Ave.
Charles Hommeyer, 4126 Oak Street, stated he was
concerned with the drainage with the Increased hardcover
and felt it unrealistic to build a house on the lot
without changing the drainage.
MIHUTBS OF THB PLAMIIIH6 C»MlSSlGH STIHG HBU> HOVBlfBBR 16, !§•?
II > I•1107 LEHIS/TRBTTBL COMTIW
Gaffron explained the City Engineer's recommendation to
upgrade the culvert to solve the additional drainage
from the building site. The question is who should pay
for the cost to upgrade the culvert? Staff feels that
the two property owners that would directly benefit from
the culvert upgrade are Homineyer at 4125 Oak Street and
Roland/Roden at 4119 Oak Street, noting that applicant
receives an indirect benefit by the existence of the
culvert.
Ken Roland, 4119 Oak Street, stated he was concerned
that the lot area variance would be granted and the
property would be sold with new owner requesting
additional variances to build the house.
Bellows explained that the variance is in effect for one
year and runs with the property, not the owner.
Additional variance requests would have to be reviewed
and approved by the City.
Ann Hommeyer, 4125 Oak Street, stated it was her
understanding that if the variance is granted and the
culvert is upgraded they would have to share in the cost
of the upgrade, however, they have had no problem with
the culvert as it exists with maintenance.
Hanson felt the drainage may involve legal issues that
should be addressed by the City Attorney.
Taylor noted that staff recommendation states that
"Improvements to the property may not change the
drainage pattern in the neighborhood. Applicants shall
share in the costs and shall share in the responsibility
for improvements to the drainageway and culvert
underneath the driveway serving the two properties to
the west." He felt, based on comments made, that the
parties affected by this application are in now in a
position to deal with staff recomnendation.
Brown felt that the issue of who pays for the culvert
upgrade cost is beyond the Planning Commission's scope.
Taylor suggested tying the condition of no change in
drainage and/or resolve of drainage prior to issuance of
building permit.
Mabusth stated that tying this condition to the issuance
of a building permit is acceptable.
There were no other comments from the public and the
public hearing was closed.
iUMtinK OP THE PLMniHG COMMISSIOH MBBTIHG ■Q¥BMBBR li» 1987
• I .<41•1107 LBHIS/ntXTTBL COHTIV
It was Boved by Bellows, seconded by Taylor, to
recoirmend approval of the renewal variance per staff
recommendation subject to the following condition:
1. At the time of building permit review, sufficient
information shall be submitted to the City for staff
to make the determination that the drainage pattern
will not be "adversely affected" by improvements to
the property i.e. Condition #6 must be satisfied.
Motion, Ayes 5, Nays 0.
#1207 GSn AHD CATHSRIHB SCAHLOH
2815 CASCO POIHT ROAD
VARIARCBS
CORTIHUATIOR OP POBLIC HBARIHG
Mabusth stated that applicant has requested that their
application be tabled until further notice.
> II rs
#1209 TINA ffHITB
2150 PROSPECT AVI
VARIARCB
CORTIROATIOH OP PUBLIC HBARIHG 8:04-8:06
Tina White was present for this matter.
Gaffron noted that applicant has provided a design plan
showing elevations of the proposed solarium, and has
submitted a diagram of the room layout of the existing
house per Planning Commission direction. Applicant
requests a side setback variance to replace an
existing porch with a solarium.
Tina White noted that all other locations for the
solarium would require a variance, except the north side
which is not a desireable location for a sunroom; and
the main purpose for the solarium is to replace the
deteriorating porch.
Johnson agreed that the proposed location is the only
feasible location for the solarium, therefore, he is in
favor of the request.
Brown questioned the hardship feeling the porch could be
replaced in the same footprint that exists.
Tina White stated that the dimensions of the factory
built solarium to match the pitch of the house are
larger than the existing porch.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Taylor, seconded by Hanson, to recommend
approval of the sideyard setback variance as proposed
per staff recommendation. Motion, Ayes 5, Nays 0.
1
mMUTES OP THE PLIODilHG COMNISSIOH TI«G HELD HOVl 1C» 1987
#1215 SMITH BET HERIHE
1955 SHORELIME DRIVE
COHDITIOHEL USE PERMIT
SBCOHD RBVIEN
Gerald Toberman was present for this matter.
Mabusth showed the Planning Commission a photo of a
seawall similar to the proposal. She noted that a site
plan has been submitted and the photo submitted in place
of elevations.
Taylor felt that it would be an improvement to the
neighborhood.
Bellows felt the proposed seawall was a better
alternative to rip lap. She recommend staff approve the
treated wood that is used for caps.
It was moved by Hanson, seconded by Bellows, to
recoRonend approval per staff recommendation subject to
building permit being obtained and treated wood or
alternative cap being approved by the Building
Inspector. Motion, Ayes 5, Nays 0.
#1217 JAMBS TAYLOR/J.M.PBAROM
1160 TOMEAMA ROAD
VARIANCE
PUBLIC HEARING 8:13-8:21
The Affidavit of Publication and Certificate of Mailing
were noted.
Applicant James Taylor and owners, Michael & Julie
Fearon, were present for this matter.
Gaffron explained the request for a hardcover variance
to allow replacement of an existing block patio with a
larger ground level deck. The proposal includes a 7
foot screening wall along the south side of deck. Staff
finds no view encroachment. 75-250' proposed hardcover
is 36.6% (34.2 existing). Staff finds little extraneous
hardcover that could be removed as a trade-off.
James Taylor submitted photos of the two adjacent
properties that have decks located in front of the
proposed deck.
Commission member Taylor noted the letter from the
Fearon's regarding the proposal and hardship.
Hanson felt the impact of increased 75-250' hardcover
would be minimal.
NiaOTBS or THE PUynilHG CO SSlOH : I TIMG HELD BOVBIIBER 16, 1987
II > I§1217 TETLOR/PBEROH COHTIBI
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Brown, seconded by Hanson, to recommend
approval as proposed. Motion, Ayes 5, Nays 0.
#1219 OROHO COHMCmiTT CHURCH
770 OLD CRYSTAL BAT ROAD _
AFTER-THE-FACT COHDITIOEAL USE FBRMIT
PUBLIC HEARIB6 8:22-8:26
The Affidavit of Publication and Certificate of Mailing
were noted.
Ingeborg Cici, Owner/Director of the Busy Beaver Day
Care, and Gary Connell, representing the Orono Community
Church were precent for this matter.
Mabusth explained the request for the after-the-fact
conditional use permit application of Orono Community
Church that would allow designated areas of the church
facility to be used by Busy Beaver Day Care for day care
use, which Planning Commission and Council have
conceptually approved. She noted that all conditions
requested by the Building Inspector have been complied
with.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Hanson, seconded by Johnson, to
recommend approval per staff recommendation. Motion,
Ayes 5, Nays 0.
#1220 ROBERT KOEHHEH
537 HANLON AVENUE
VARIANCE
PUBLIC HEARING 8:27-8:29
The Affidavit of Publication and Certificate of Mailing
were noted.
Robert Koehnen was present for this matter.
Gaffron explained the request for a front setback
variance to construct a 16'x 24' room addition to the
south side of the residence. The addition continues the
front and rear lines of the existing house, which is
slightly skewed on the lot resulting in a slightly
decreased front setback from what now exists. The
addition will be 38' from the edge of the traveled
roadway. Due to the location of the existing house, any
addition would require a setback variance.
MIHUTBS OP TBB PLMOilHG CXNflUSSI TIHG HSLO HOITBilBBR 1987
11220 KOI corriHOBD
Bellows asked applicant why the addition could not be
constructed on the west side which would be in the
actual building envelope?
Mr. Koehnen stated he would like a southern exposure for
the addition; and a hill and walkout basement prohibit
the addition on the west side.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Taylor, seconded by Brown, to recommend
approval per staff recommendation. Motion, Ayes 5, Nays
0.
•1221 GARY BKLOP 6 CATHY LBB
1965 PAGBRMBSS POIHT ROAD
VARIABCBS
PUBLIC HBARIBG 8:30-9:04
The Affidavit of Publication and Certificate of Mailing
were noted.
Gary Eklof and Cathy Lee were present for this matter.
Gaffron explained the request for setback and hardcover
variances to remodel/expand house, and attach garage.
The proposed construction as follows:
1. Remove existing non-conforming garage, attach new
garage and mudroom to existing house.
2. Add new foyer and deck/stairs on street side.
3. Put new foundation under existing house which
requires raising it.
4. Add second story over portion of existing house
in 0-75' zone, 8' from side lot line.
Variances requested as follows:
1. 0-75' hardcover: existing = 39.0% (no change
proposed )
2. 75-250' hardcover: existing = 27.6%
proposed = 34.1%
3. Structure addition in 0-75' zone.
4. Structure addition within 8' of side lot line
(10' required).
5. Continue existing 1' house encroachment into
average lakeshore setback; add 4' 2nd story deck
with total average setback encroachment of 5'.
6. Street setback for principal structure of 20'
(30' required) (Garage doors 25'-35' from right-fo-
way, no turnaround provided).
8
MIK .tSS OP THE PIAHMIHG COMMISSIOH MBBTIHG BBLD HOVBNBBR 16, 1987
#1221 BELOP/I.BB COHTimiBD
Referring to Exhibit H - survey of hardcover variances
in immediate neighborhood, Gaffron noted that
applicant's property has excessive hardcover in the 0-
75' zone and excessive total lot hardcover compared to
the neighborhood lots.
Based on the extent of work being done. Bellows
thought that it may be better to start from scratch and
rebuild.
Cathy Lee stated that replacing the uniqueness of the
existing structure would cost twice what is proposed.
She explained that the summer rainsLorms did
considerable damage to their pitch & gravel roof which
leaked severely and damaged beamwork. According to
three contractors, major repairs are necessary.
Bellows noted that the issue of repairing storm damage
is independent of the requests in this application.
Bellows stated she had some very strong reservations
regarding this very ambitious plan. She was concerned
with Eagerness Point turning in to an area like Casco
Point. She asked applicants what their hardship was
involving the proposed improvements outside the existing
envelope.
Cathy Lee stated that the existing garage needs repair
and therefore would like to replace it in a location to
decrease the encroachment and provide a driveway area.
Gary Eklof noted that the only addition hardcover
proposed involves a much needed driveway.
John Waldron, 1951 Concordia Street, stated he did not
feel the proposal affected the density and felt it would
be a significant improvement to the neighborhood and
house.
Taylor felt the relocation of the encroaching garage was
an adequate trade-off for the additional hardcover. He
is in favor of the proposal subject to the removal of an
8'xl2' boat house in the 0-75' zone.
Brown felt the density issue is off-set by the home
improvement and that the driveway was needed for safety
reasons, therefore, in favor of the proposal.
Hanson concurred with Taylor & Brown but felt some
hardcover could be removed.
Cathy Lee felt that the hardcover could possibly be
reduced by removing the boat house, and slight
modifications to the proposed driveway steps to foyer.
MIBUTBS OF THE PIAinilHG COMMISSION MEETIHG HELD EOVEHBER 16, 1987
#1221 EKLOF/LEE COBTIEUED
Jan Waye, 1885 Concordia, felt the proposal will upgrade
the neighborhood.
There were no other comments from the public and the
public hearing was closed.
Planning Commission discussed different options to
reduce the hardcover.
Cathy Lee felt there were a few discrepencies with
staff's measurements and hardcover calculations.
Johnson agreed that the proposal would be an improvement
to neighborhood, however, felt Fagerness Point was
already congested and found the proposed hardcover
excessive, therefore could not support the proposal.
It was moved by Bellows, seconded by Hanson, to
recommend approval subject to:
1. Staff and applicant determining actual existing
hardcover.
2. Removal of 350 s.f. of existing hardcover within
the 0-75' setback.
Motion, Ayes 3, Nays 2. Johnson voted nay finding the
total hardcover excessive. Brown voted nay objecting to
the recommendation to remove existing hardcover.
#1222 JAM HAYB
1885 COMCORDIA STREET
AFTER-THE-FACT CONDITIONAL USB PERMIT
PUBLIC HEARING 9:21-9:22
The Affidavit of Publication and Certificate of Mailing
were noted.
Jan Waye was present for this matter.
The application involves an after-the-fact conditional
use permit for lakeshore restoration work already done.
Staff recommended tabling this application to provide
time for the applicant and applicant's contractor to
meet with staff and the City Engineer to determine
effectiveness of the technique used in stabilizing the
steep lakeshore bank of the property and to determine
what portions of the work should be removed.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Bellows, seconded by Hanson, to table
Application #1222 per staff recommendation. Motion,
Ayes 5, Nays 0.
MITOTBS OF THE PLAiniHG COMUSSIOH TIHG HELD EGVENBBR 16, 1987
§1223 JOBE B. HALDROE
1951 COECORDIA STREET
COEDITIOEAL OSE PERMIT
POBLIC HEARIEG 9:25-10:06
The Affidavit of Publication and Certificate of Mailing
were noted.
Gaffron explained the request for a conditional use
permit to repair the lakeshore bank that was damaged
during the "super storm". Applicant wishes to repair
the damage by lowering the grade to create a walkout
from the existing house, construct a retaining wall at
that cut up to the house, and regrade the slope and seed
it along the lakeshore. Proposal also includes a deck
extending from the west side of the house where no deck
previously existed. Applicant proposes to reduce some
house hardcover by installation of gutters and a sealed
pipe straight to the lake. This direct transportation
of roof runoff water to the lake through a pipe is
directly contrary to the City's philosophy that all roof
anc other hard surface runoff should travel over and
through the ground surface for filtration purposes prior
to reaching the lake.
John Waldron was present for this matter and explained
that the storm was the impetus of this proposal. He
explained the conditions of the SBA loan to be used for
repairing the lakeshore and house improvements. He
stated tne damage to the steep lakeshore bank is a
serious physical hardship that must be remedied and
believes that his proposal to reduce the slope is the
best solution. He submitted a letter from Hennepin
Conservation District which he feels addresses the slope
problem and supports his proposal as the best solution.
In general, he felt that, the proposal can only have a
positive effect on the health, safety and welfare of the
community, by protecting the lake from future pollution
as a result of erosion and other runoff; and by adding a
walkout and deck to the property, the proposal will only
have a positive effect on the values of the property in
the surrounding area. Regarding the transportation of
roof runoff through pipe, he contended that runoff from
the roof is clean, therefore, would not be detrimental
to lake quality. He noted that he would use perforated
pipe if necessary.
Hanson noted the three other alternatives to applicant's
proposal and suggested tabling this application in order
to review the alternatives.
MIMUTBS or TBB PLAHimK COHMISSIOH TIH6 HELD BOVEMBEK 1§, 1987
•i -r•1223 NJODROH COBTIHI
John Waldron noted the drawbacks of retaining wall and
stabilization fabric alternatives:
Retaining wa11s involve extensive cost* are less
aesthetically pleasing than a naturally vegetated
slope, and do not guarantee the stabilization of
steep slopes from a "super storm" event.
Stabilization fabric would also require some grading
to soften the steep slope.
He addressed the many issues outlined in his letter
dated October 22* 1987 included in staff's packet.
Bellows noted that the City has an ordinance and
guidelines regarding grading within the 0-75' lakeshore
yard. She noted the three alternatives within the
conformance of City guidelines to solve the erosion
damage. She did not feel there was any connection with
repairing the storm damage and the neccessity for a
waIkout.
Johnson voiced concern with controlling the erosion
until the s^orm damage is repaired.
John Waldron stated that he has placed hay bales at the
top of the slope but the bales have since been pushed
down the slope which he intends to replace.
Staff suggested installation of a silt fence at the
bottom of the slope at the lakeshore.
Cathy Lee* 1965 Fagerness Point Road* stated they had a
similar problem with a different property they owned*
and the only method that was found effective was cutting
back the slope. As a neighbor, they found the proposal
less objectional than "cribbing".
Taylor noted that none of the alternatives offered by
the City Engineer or Hennepin Conservation District
included a walkout.
Brown noted that the City has not allowed alot of
grading in the lakeshore yard and found very little
difference in the City Engineer's recommendation vs. the
recommendation of Hennepin Conservation District. He
would therefore agree with staff recommendation of
denial.
Hanson felt he would need to study the information
further before making a recommendation* and recommended
tabling the application.
There were no other comments from the public and the
public hearing was closed.
HIMITBS or ns FLAnirG comhissioh ;tihg ■OVBMBBII 16. 1987
#1223 HALOKOB COBTIl •J -»
It was moved by Bellows* seconded by Brown* to recomicend
denial of the proposed grading cuts to create a walkout
and recommend that applicant submit a revised proposal
for grading in order to repair and maintain his
lakeshore bank; and recommend approval of the lakeshore
deck proposal near the house as proposed conditioned
upon concurrent removal of the 9'x 14' deck at the edge
of the slope* resulting in a net increase of 37 s.f. of
0-75' hardcover - per staff recommendation. Motion*
Ayes 4* Nays 0* Abstention 1. Hanson abstained.
§1224 MimiBTOBKA BOAT liOASS
1449 SHOBKLIMB DRIVE
APTBR-THB-PACT COBDITIOBAL OSB PBI
PUBLIC BBARIBG 10:08-10:12
The Affidavit of Publication and Certificate of ^'ailing
were noted.
UTAARIABCB
Byron Heimark was present for this matter
Mabusth explained the after-the-fact conditional use
permit/variance request for upgrading and expansion of
the boat lift at Minnetonka Boat Wor»:s. The Orono
facility will service 3 of the larger boats currently
stored at the Wayzata facility. Council conceptually
approved the request at their November 9th ."neeting.
Bellows asked why the Orono facility must store the
larger boats at this point?
Byron Heimark explained that the Orono facility needed
to replace their boat lift with a safer style which sre
wider than the old style; and with the remodeling of the
Wayzata ficility, they can no longer store the larger
boats and meet the parking requirements.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Bellows* seconded by Johnson* to
recommend approval per staff recommendation. Motion*
Ayes 5* Nays 0.
NiaOTBS OP THE PIAmiSG COHMISSIOV TING HELD VOVEMBBR 16, 1987
#1225 JMf^ B. GILBraf
955 TOnUUni BOAD
VABIAKBS
POBUC BBARIMG 10:13-10:17
The Affidavit of Publication and Certificate of Mailing
were noted.
Jeuoes Gilbert was present for this matter,
Gaffron explained the request for average lakeshore
setback variance ahd hardcover variance to remove an
existing deck which extends from the main floor of the
residence and replace it with a somewhat larger deck and
patio system. The long terra plan also includes a
gazebo. None of the proposed structures are within the
0-75' setback zone. Staff recommends approval of the
average lakeshore setback variance finding there wi11 be
no view encroachment upon either neighboring property;
and recommends approval of the 75-250' hardcover
variance of 27.9% finding there is no extraneous
hardcover on the property that can be removed and
noting there is virtually no hardcover within the 90*
setback from the lakeshore. Staff recommends that if a
gazebo structure is constructed, it should be at least
10' from the side property line. In addition, referring
to a chain link fence shown on the plan, staff advises
applicant that the height of this fence may not exceed
42" above grade and may not continue into the 75'
lakeshore setback zone.
James Gilbert stated that the existing deck needs to be
replaced and noted that the proposed structures cannot
be seen from the lake or adjacent property owners due to
topography.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Bellows, seconded by Brown, to recommend
approval per staff recommendation. Motion, Ayes 5, Nays
0.
MimiTBS OP THE PIAMHIHG COHMISSIOH TIHG HELD HOVBIIBBR 16, 1987
#1226 MinOH HOLD
4650 aOKTB SHORE DRIVE
VARIAHCB
PUBLIC HBBRIBG 10:18-10:27
The Affidavit of Publication and Certificate of Hailing
were noted.
Applicant Winton Wold and owner Mr. Laughlin were
present for this matter.
Gaffron explained the request lot area variance to
construct a residence on Tract B of RLS 1036. The
proposed lot is .77 acre in a 1 acre zone. Staff
recommends approval based on the lot size being
consistent with existing developed lots in the
neighborhood and consistent with lot size variances
previously approved in the LR-IB zone. Staff further
recommei creation of a private access easement 20' in
width, to be located 10' either side of the lien between
Tract D and Tracts A & B. This easement would contain a
driveway to serve Tracts B & C.
Mr. Henry, 4725 North Shore Drive, complained that Tract
A has been used as a dumping area for many years and
would like it cleaned up. He is in favor of the lot
area variance.
Taylor questioned the easement proposed by staff which
varies from the proposal of applicant and owners of
Tracts A,B,C & D. He felt the easement should be
entirely within Tract D.
Winton Wold stated he had no objections to either way.
There were no other comments from the public and the
public hearing was closed.
It was moved by Hanson, seconded by Johnson, to
recommend approval subject to easement being contained
entirely in Tract D. Motion, Ayes, 5, Nays 0.
MIHIITBS or THE PIAMHXIIG CCMaSSIOil :\:a:TIHG HELD HOVEMBBR 16, 1987
11227 PATRICE NIDDLBTOK
720 TOMKAMA ROAD
VARIAMCB
PUBLIC HBARIRG 10:28>10:29
The Affidavit of Publication and Certificate of Mailing
were noted.
Patrick Middleton was not present for this matter.
Bellows explained the request for a hardcover variance
to construct a garage on the property (no garage
currently exists. Existing 75-250' hardcover is 55.5%
and applicant proposed to remove large portions of the
existing blacktop in the area near the road resulting in
a net 75-250' hardcover reduction to 50.4%. Staff
recommends approval.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Bellows, seconded by Taylor, to
recommend approval per staff recommendation, Motion,
Ayes 5, Nays 0.
#1228 HALTER R. HITTNER
1420 BALDOR PARK ROAD
VARIABCBS
PUBLIC HEARIliG 10:30-10:38
The Affidavit of Publication and Certificate of Mailing
were noted.
Walter Wittmer was present for this matter.
Gaffron explained the requst for side setback variance
and average lakeshore setback variance to construct a
second story addition in a side yard and slightly within
the 75' lakeshore setback zone. He explained the
objective of the proposal is to increase the space
within to existing second floor bedrooms. He explained
the issue of a deck that has been constructed in
violation of ci variance approved in 1978. Staff
recommends approve'1 of the proposed addition finding
that there will be no significant new encroachment upon
the neighbors, subject to removal of the 0'x 30' deck,
to be replaced with a smaller deck and stair system not
to exceed 6'x 7' in dimension.
Walter Wittmer stated there was a five year lapse in
time between the 1978 variance approval and building
permit and actual construction which led to a lack of
memory of what could be constructed. He noted that
previous to building the deck, he checked with the
neighbors regarding the size of deck and they had no
MIBDTBS OP THE PUaniMG O IISSIOM TIHG HELD HOVBMBBR 16, 1987
§1228 Nin ij»COBTIEI
problem. Regarding staff recommendation, he asked to be
allowed a deck and stair system 6'x 8* in dimension.
There were no comments from the public regarding this
matter and the public hearing was closed.
It was moved by Bellows, seconded by Hanson, to
recommend approval of the variance per staff
recommendation conditioned upon removal of the 8'x 30'
deck to be replaced with a smaller deck and stair system
not to exceed 6'x 8' in dimension. Moiton, Ayes 5, Nays
0.
#1187 BOETH ASM ESTATES ASSOCIATION
215, 340, 350, 360 6 370 NORTH ARM LANE
COMDITIOHAL USE PERMIT
SECOND REVIEH
Rod Backerud was present representing the North Arm
Estates Association.
Mabusth explained the request involving the creation of
berms to receive 25,000 cubic yards of spoils from the
suction dredging of the North Arm Channel. The revised
grading plans designate 2 berm areas now located out of
the 931.5 elevation. Each berm meets the 75' setback
from the lake (channel area) but the northern portions
of the berm now encroach within 26' of the the wetlands.
Berms are constructed with 4" PVC pipe at 2' height
intervals. Mabusth noted that the MCWD has not yet
given approval of the project.
Rod Backerud explained the process involved and length
of time involved.
Bellows stated she was very leary of
project being started at this time of
impact of a freeze-thaw cycle.
this type of
year and the
Staff did not have a definite answer to whether a
freeze-thaw cycle would adversely affect this project.
It was moved by Brown, seconded by Hanson, to recommend
approval per staff recommendation subject to applicant
working with staff regarding the freeze-thaw concerns;
and noting that the plan indicates a slight encroachment
in the 26' wetland setback. Motion, Ayes 5, Nays 0.
APPROVAL OF MINUTES
It was moved by Hanson, seconded by Brown, to approve
the Minutes of the October 19, 1987 Planning Commission
meeting. Motion, Ayes 5, Nays 0.
I-r-v
MIHUTBS OP THE PIAmiMG CONNISSIOH .1 h:TIHG HELD BOVSMBER IS, 1987
PIABBIEG COMUSSIOH REPBESEBT8T1VE
Johnson was appointed to attend the December 14, 1987
Council meeting.