HomeMy WebLinkAboutP19-000183 - plumbingPERMIT PROJECT
FILE #: 19-001116
560 SANDHILL DR LONG LAKE MN 55356
PLUMBING NEW CONSTRUCTION
INSPECTION INFORMATION
Department
Community Development
Inspection Type
Plumbing - Rough In
Assign To
Permit #:
P19-000183 Plumbing new construction
Created On
08/29/2019 by Nola Dickhausen
Notes
DATES
Date
09/04/2019
From
3: 30 PM
To
4: 00 PM
Completion Date
09/04/2019
Status
Correct Work & Proceed
#STATUS COMMENTS
INSPECTION COMMENTS
0 UG DWV PVC sch 40. 5 lb air test is holding. Backwater valves provided. Radon vented out of 10 ft length of
draintile. Provide permit card on site. OK to continue. Jim H.
PERMIT PROJECT
FILE #: 19-001116
560 SANDHILL DR LONG LAKE MN 55356
PLUMBING NEW CONSTRUCTION
INSPECTION INFORMATION
Department
Community Development
Inspection Type
Plumbing - Rough In
Assign To
Permit #:
P19-000183 Plumbing new construction
Created On
09/12/2019 by Anna Carlson
Notes
DATES
Date
09/16/2019
From
2: 00 PM
To
2: 30 PM
Completion Date
09/16/2019
Status
Correct Work & Proceed
#STATUS COMMENTS
INSPECTION COMMENTS
0 AG DWV PVC Sch 40 with 5# air test holding. Radon vented thru roof.
1. Provide structural straps on top plates of all bearing walls with plumbing DWV penetrations.
2. Finish insulating water lines.
3. Provide permit card on site. Correct and ok to continue. Jim H.
PERMIT PROJECT
FILE #: 19-001116
560 SANDHILL DR LONG LAKE MN 55356
PLUMBING NEW CONSTRUCTION
INSPECTION INFORMATION
Department
Community Development
Inspection Type
Plumbing - Final
Assign To
Permit #:
P19-000183 Plumbing new construction
Created On
11/07/2019 by Anne Hentges
Notes
DATES
Date
11/08/2019
From
1: 00 PM
To
1: 30 PM
Completion Date
11/08/2019
Status
Correct Work & Proceed
Erosion Control Checked, Found Compliant
Is Vegetation Established
#STATUS COMMENTS
INSPECTION COMMENTS
100 Manometer holding
101 Fixtures set &and sealed
102 Remove roof caps
Jason R.
PERMIT PROJECT
FILE #: 19-001116
560 SANDHILL DR LONG LAKE MN 55356
PLUMBING NEW CONSTRUCTION
INSPECTION INFORMATION
Department
Community Development
Inspection Type
Plumbing - Final
Assign To
Permit #:
P19-000183 Plumbing new construction
Created On
01/23/2020 by Anne Hentges
Notes
DATES
Date
01/27/2020
From
10: 45 AM
To
11: 15 AM
Completion Date
01/27/2020
Status
Permit Finaled
Erosion Control Checked, Found Compliant
Is Vegetation Established
#STATUS COMMENTS
INSPECTION COMMENTS
0 Plumbing manometer and nal inspections completed on 11/18/19. Roof caps ha e been removed. All work
complete, permit naled. Jim H.
1 Manometer holding
2 Fixtures set &and sealed
3 Remove roof caps
Jason R.
PERMIT PROJECT
FILE #: 19-001116
560 SANDHILL DR LONG LAKE MN 55356
PLUMBING NEW CONSTRUCTION
INSPECTION INFORMATION
Department
Community Development
Inspection Type
Set & Seal
Assign To
Anne Hentges
Permit #:
P19-000183 Plumbing new construction
Created On
06/22/2020 by Anne Hentges
Notes
DATES
Date
06/23/2020
From
9: 00 AM
To
9: 30 AM
Completion Date
06/23/2020
Status
Erosion Control Checked, Found Compliant
#STATUS COMMENTS
INSPECTION COMMENTS
0 ERT#: 1546711368
Serial#: 54058839
Reading: 000547625
3/4 meter
All OK - Scott