HomeMy WebLinkAboutSr. Hsg. L.O.C Phase I - permit conditions ORONO WOODS SENIOR HOUSING
PHASE 1 (SITE GRADING) PERMIT CONDITIONS
READ NOW!!
Attachment to 2040 W. Wayzata Blvd. (Orono Senior Housing) Phase 1 grading permit.
Terms and Conditions of Permit
1. This permit is subject to the terms and conditions of the PUD 2B Agreement,a copy of which
is attached hereto.
2. Permit approval is based on the approved Site Plan(Sheet C2-1, latest revision 12-17-01)
and the approved Grading/Drainage/Erosion Control Plan (Sheet C3-1, latest revision 12-
17-01) and is subject to ongoing review and site inspections by the City. Any changes to
plans require City approval.
3. Orange silt fence shall be installed and maintained in place and in functional condition at
all times, subject to Minnehaha Creek Watershed District requirements.
4. Tree removal shall occur only within the limits established by silt fencing as shown on
the approved plans.
5. In the event that site activities result in spillage of fill materials on adjacent roadways,
contractor shall be responsible for maintaining area roadways in a clean condition on a
daily basis or as may be required by the City.
6. In the event that excess fill is to be hauled off-site, be advised that any location in Orono
to be receiving such fill must first have obtained the appropriate permits from the City
(more than 500 cubic yards to any single receiving site requires a 60-day conditional use
permit review process).
7. This permit covers only the Phase 1 Improvements as listed in the attached Phase 1 Site
Grading Cost Estimate. A separate permit will be required for the Phase 2 Improvements
which include all work shown on the attached Phase 2 Utilities and Street Improvements Cost
Estimate.
8. THIS PHASE 1 IMPROVEMENTS PERMIT WILL BE REVOKED IF THE PHASE 1
LETTER OF CREDIT IS NOT RECEIVED AT THIS OFFICE BY 4:30 P.M. ON
WEDNESDAY, DECEMBER 26, 2001. IF THIS PERMIT IS REVOKED, THE CITY
WILL ORDER ALL WORK AT THE SITE TO BE STOPPED BEGINNING AT 8:00 A.M.
ON THURSDAY DECEMBER 27,UNTIL THE LETTER OF CREDIT IS RECEIVED AT
WHICH TIME THE PERMIT WILL BE REINSTATED.
9. Commencement of the Phase 2 (Utilities and Street) Improvements may not commence
until a Phase 2 Improvement Permit is issued, which we anticipate will be in the spring of
2002. Such permit will not be issued until the Phase 2 Letter of Credit is received.
10. This permit does not cover the following activities which require separate permits:
- Foundation and building construction
- Utility connections to building
- Building systems (plumbing, mechanical, electrical, etc.)
Sheet 1 of 4
11. Construction trailer is approved to be located near the northeast corner of the site. Any
temporary lighting shall be directed away from adjacent properties.
12. Do not commence site grading or improvements until all other agency permits have been
obtained (Mn/DOT, MCWD, etc.).
13. Applicant is advised that City will coordinate with the developer prior to commencing
burial of existing power lines, installation of street lighting along Brown Road and
Highway 12, and other off-site improvements for which the City is responsible.
14. Hours of construction activity(use of power equipment) limited by Orono Ordinance 155
to between the hours of 7:00 a.m. and 8:00 p.m. weekdays and 8:00 a.m. to 8:00 p.m. on
weekends and holidays.
Sheet 2 of 4
s ,
CITY OF ORONO
ORONO WOODS APARTMENTS
COMMERCIAL SITE DEVELOPMENT
PLAT FILE NO. 2641
SITE IMPROVEMENT COST ESTIMATE: PHASE 1-SITE GRADING
....................:::::::::::::::::... U N I T•
EST. ES T.
ITEM UNIT QUANTITY PRICE COST
Mobilization LS 1 $5,000.00 $5,000
Site grading LS 1 20,000.00 20,000
Common excavation
CY
2300 5.00
11,500
Landscaping LS 0.25
40,000.00 10,000
Retaining wall SF 320 15.00 4,800
Silt fence LF 1500 3.00 4,500
Estimated Construction Cost
$55,800
0
50/o Security Deposit 27,900
Total Security Deposit Required $83,700
Sheet 3 of 4
CITY OF ORONO -
ORONO WOODS APARTMENTS
COMMERCIAL SITE DEVELOPMENT
PLAT FILE NO. 2641
SITE IMPROVEMENT COST ESTIMATE: PHASE2 UTILITIES AND STREET
EST. UNIT 1 EST.
ITEM UNIT QUANTITY PRICE COST
Stabilization fabric SY 4000 1.00 4,000
Aggregate base, Cl. 4, 100% crushed TN 1900 11.00 20,900
Aggregate base, Cl. 5, 100% crushed TN 1900 11.00 20,900
Type 31 bit. base course TN 600 32.00 19,200
Type 41 bit. wear course TN 300 35.00 10,500
Bituminous material for tack GL 400 1.00 400
Concrete curb and gutter LF 1910 8.00 15,280
Landscaping LS 0.75 40,000.00 30,000
Concrete walk SF 3000 3.00 9,000
6" DIP LF 160 20.00 3,200
8" DIP LF 980 25.00 24,500
DIP fittings LB 3000 1.00 3,000
6" gate valve & box EA 5 800.00 4,000
8" gate valve & box EA 3 1,000.00 3,000
Hydrant EA 3 1,500.00 4,500
Connect to existing water main EA 2 1,000.00 2,000
12" HDPE storm sewer LF 565 15.00 8,475
12" RCP storm sewer LF 171 25.00 4,275
15" RCP storm sewer LF 405 30.00 12,150
21" RCP storm sewer LF 85 35.00 2,975
21" RCP FES EA 1 1,000.00 1,000
Class III riprap CY 8 50.00 400
Connect to existing storm MH EA 1 1,000.00 1,000
Storm catch basin w/casting EA 7 1,200.00 8,400
Storm catch basin MH w/casting EA 7 1,500.00 10,500
6" PVC sanitary sewer LF 180 15.00 2,700
8" PVC sanitary sewer LF 550 23.00 12,650
Improve pipe foundation LF 550 1.00 550
8"x6" wye EA 1 50.00 50
Sanitary MH w/casting EA 3 1,800.00 5,400
Construct MH over existing line EA 1 3,000.00 3,000
Connect to existing sanitary sewer EA 2 1,000.00 2,000
Remove existing sanitary sewer LF 380 5.00 1,900
Estimated Construction Cost $251,805
+50% Security Deposit 125,903
Total Security Deposit Required $377,708
Sheet 4 of 4
,1 4
ORONO WOODS SENIOR HOUSING
PHASE 1 (SITE GRADING) PERMIT CONDITIONS
READ NOW!!
Attachment to 2040 W. Wayzata Blvd. (Orono Senior Housing) Phase 1 grading permit.
Terms and Conditions of Permit
1. This permit is subject to the terms and conditions of the PUD 2B Agreement,a copy of which
is attached hereto.
2. Permit approval is based on the approved Site Plan(Sheet C2-1, latest revision 12-17-01)
and the approved Grading/Drainage/Erosion Control Plan (Sheet C3-1, latest revision 12-
17-01) and is subject to ongoing review and site inspections by the City. Any changes to
plans require City approval.
3. Orange silt fence shall be installed and maintained in place and in functional condition at
all times, subject to Minnehaha Creek Watershed District requirements.
4. Tree removal shall occur only within the limits established by silt fencing as shown on
the approved plans.
5. In the event that site activities result in spillage of fill materials on adjacent roadways,
contractor shall be responsible for maintaining area roadways in a clean condition on a
daily basis or as may be required by the City.
6. In the event that excess fill is to be hauled off-site, be advised that any location in Orono
to be receiving such fill must first have obtained the appropriate permits from the City
(more than 500 cubic yards to any single receiving site requires a 60-day conditional use
permit review process).
7. This permit covers only the Phase 1 Improvements as listed in the attached Phase 1 Site
Grading Cost Estimate. A separate permit will be required for the Phase 2 Improvements
which include all work shown on the attached Phase 2 Utilities and Street Improvements Cost
Estimate.
8. THIS PHASE 1 IMPROVEMENTS PERMIT WILL BE REVOKED IF THE PHASE 1
LETTER OF CREDIT IS NOT RECEIVED AT THIS OFFICE BY 4:30 P.M. ON
WEDNESDAY, DECEMBER 26, 2001. IF THIS PERMIT IS REVOKED, THE CITY
WILL ORDER ALL WORK AT THE SITE TO BE STOPPED BEGINNING AT 8:00 A.M.
ON THURSDAY DECEMBER 27,UNTIL THE LETTER OF CREDIT IS RECEIVED AT
WHICH TIME THE PERMIT WILL BE REINSTATED.
9. Commencement of the Phase 2 (Utilities and Street) Improvements may not commence
until a Phase 2 Improvement Permit is issued, which we anticipate will be in the spring of
2002. Such permit will not be issued until the Phase 2 Letter of Credit is received.
10. This permit does not cover the following activities which require separate permits:
- Foundation and building construction
- Utility connections to building
- Building systems (plumbing, mechanical, electrical, etc.)
Sheet 1 of 4
,
11. Construction trailer is approved to be located near the northeast corner of the site. Any
temporary lighting shall be directed away from adjacent properties.
12. Do not commence site grading or improvements until all other agency permits have been
obtained (Mn/DOT, MCWD, etc.).
13. Applicant is advised that City will coordinate with the developer prior to commencing
burial of existing power lines, installation of street lighting along Brown Road and
Highway 12, and other off-site improvements for which the City is responsible.
14. Hours of construction activity (use of power equipment) limited by Orono Ordinance 155
to between the hours of 7:00 a.m. and 8:00 p.m. weekdays and 8:00 a.m. to 8:00 p.m. on
weekends and holidays.
Sheet 2 of 4
CITY OF ORONO
ORONO WOODS APARTMENTS
COMMERCIAL SITE DEVELOPMENT
PLAT FILE NO. 2641
SITE IMPROVEMENT COST ESTIMATE: PHASE 1-SITE GRADING
.... ..............
EST. UNIT EST.
ITEM UNIT QUANTITY PRICE COST
Mobilization LS 1 $5,000.00 $5,000
Site grading LS 1 20,000.00 20,000
Common excavation CY 2300 5.00 11,500
Landscaping LS 0.25 40,000.00 10,000
Retaining wall SF 320 15.00 4,800
Silt fence LF 1500 3.00 4,500
Estimated Construction Cost $55,800
+50% Security Deposit 27,900
Total Security Deposit Required $83,700
Sheet 3 of 4
CITY OF ORONO -
ORONO WOODS APARTMENTS
COMMERCIAL SITE DEVELOPMENT
PLAT FILE NO. 2641
SITE IMPROVEMENT COST ESTIMATE: PHASE2 UTILITIES AND STREET
EST. UNIT 1 EST.
ITEM UNIT QUANTITY PRICE COST
Stabilization fabric SY 4000 1.00 4,000
Aggregate base, Cl. 4, 100% crushed TN 1900 11.00 20,900
Aggregate base, CI. 5, 100% crushed TN 1900 11.00 20,900
Type 31 bit. base course TN 600 32.00 19,200
Type 41 bit. wear course TN 300 35.00 10,500
Bituminous material for tack GL 400 1.00 400
Concrete curb and gutter LF 1910 8.00 15,280
Landscaping LS 0.75 40,000.00 30,000
Concrete walk SF 3000 3.00 9,000
6" DIP LF 160 20.00 3,200
8" DIP LF 980 25.00 24,500
DIP fittings LB 3000 1.00 3,000
6" gate valve & box EA 5 800.00 4,000
8" gate valve & box EA 3 1,000.00 3,000
Hydrant EA 3 1,500.00 4,500
Connect to existing water main EA 2 1,000.00 2,000
12" HDPE storm sewer LF 565 15.00 8,475
12" RCP storm sewer LF 171 25.00 4,275
15" RCP storm sewer LF 405 30.00 12,150
21" RCP storm sewer LF 85 35.00 2,975
21" RCP FES EA 1 1,000.00 1,000
Class III riprap CY 8 50.00 400
Connect to existing storm MH EA 1 1,000.00 1,000
Storm catch basin w/casting EA 7 1,200.00 8,400
Storm catch basin MH w/casting EA
7 1,500.00 10,500
6" PVC sanitary sewer LF 180 15.00 2,700
8" PVC sanitary sewer LF 550 23.00 12,650
Improve pipe foundation LF 550 1.00 550
8"x6" wye EA 1 50.00 50
Sanitary MH w/casting EA 3 1,800.00 5,400
Construct MH over existing line EA 1 3,000.00 3,000
Connect to existing sanitary sewer EA 2 1,000.00 2,000
Remove existing sanitary sewer LF 380 5.00 1,900
Estimated Construction Cost $251,805
+50% Security Deposit 125,903
Total Security Deposit Required $377,708
Sheet 4 of 4
ORONO WOODS SENIOR HOUSING
PHASE 1 (SITE GRADING) PERMIT CONDITIONS
READ NOW!!
Attachment to 2040 W. Wayzata Blvd. (Orono Senior Housing) Phase 1 grading permit.
Terms and Conditions of Permit
1. This permit is subject to the terms and conditions of the PUD 2B Agreement,a copy of which
is attached hereto.
2. Permit approval is based on the approved Site Plan(Sheet C2-1, latest revision 12-17-01)
and the approved Grading/Drainage/Erosion Control Plan (Sheet C3-1, latest revision 12-
17-01) and is subject to ongoing review and site inspections by the City. Any changes to
plans require City approval.
3. Orange silt fence shall be installed and maintained in place and in functional condition at
all times, subject to Minnehaha Creek Watershed District requirements.
4. Tree removal shall occur only within the limits established by silt fencing as shown on
the approved plans.
5. In the event that site activities result in spillage of fill materials on adjacent roadways,
contractor shall be responsible for maintaining area roadways in a clean condition on a
daily basis or as may be required by the City.
6. In the event that excess fill is to be hauled off-site, be advised that any location in Orono
to be receiving such fill must first have obtained the appropriate permits from the City
(more than 500 cubic yards to any single receiving site requires a 60-day conditional use
permit review process).
7. This permit covers only the Phase 1 Improvements as listed in the attached Phase 1 Site
Grading Cost Estimate. A separate permit will be required for the Phase 2 Improvements
which include all work shown on the attached Phase 2 Utilities and Street Improvements Cost
Estimate.
8. THIS PHASE 1 IMPROVEMENTS PERMIT WILL BE REVOKED IF THE PHASE 1
LETTER OF CREDIT IS NOT RECEIVED AT THIS OFFICE BY 4:30 P.M. ON
WEDNESDAY, DECEMBER 26, 2001. IF THIS PERMIT IS REVOKED, THE CITY
WILL ORDER ALL WORK AT THE SITE TO BE STOPPED BEGINNING AT 8:00 A.M.
ON THURSDAY DECEMBER 27,UNTIL THE LETTER OF CREDIT IS RECEIVED AT
WHICH TIME THE PERMIT WILL BE REINSTATED.
9. Commencement of the Phase 2 (Utilities and Street) Improvements may not commence
until a Phase 2 Improvement Permit is issued, which we anticipate will be in the spring of
2002. Such permit will not be issued until the Phase 2 Letter of Credit is received.
10. This permit does not cover the following activities which require separate permits:
- Foundation and building construction
-Utility connections to building
- Building systems (plumbing, mechanical, electrical, etc.)
Sheet 1 of 4
11. Construction trailer is approved to be located near the northeast corner of the site. Any
temporary lighting shall be directed away from adjacent properties.
12. Do not commence site grading or improvements until all other agency permits have been
obtained (Mn/DOT, MCWD, etc.).
13. Applicant is advised that City will coordinate with the developer prior to commencing
burial of existing power lines, installation of street lighting along Brown Road and
Highway 12, and other off-site improvements for which the City is responsible.
14. Hours of construction activity(use of power equipment) limited by Orono Ordinance 155
to between the hours of 7:00 a.m. and 8:00 p.m. weekdays and 8:00 a.m. to 8:00 p.m. on
weekends and holidays.
Sheet 2 of 4
CITY OF ORONO
ORONO WOODS APARTMENTS
COMMERCIAL SITE DEVELOPMENT
PLAT FILE NO. 2641
SITE IMPROVEMENT COST ESTIMATE: PHASE 1-SITE GRADING
EST. UNIT EST.
ITEM UNIT QUANTITY PRICE COST
Mobilization LS 1 $5,000.00 $5,000
Site grading LS 1 20,000.00 20,000
Common excavation CY 2300 5.00 11,500
Landscaping LS 0.25 40,000.00 10,000
Retaining wall SF 320 15.00 4,800
Silt fence LF 1500 3.00 4,500
Estimated Construction Cost $55,800
+50% Security Deposit 27,900
Total Security Deposit Required $83,700
Sheet 3 of 4
CITY OF ORONO
ORONO WOODS APARTMENTS
COMMERCIAL SITE DEVELOPMENT
PLAT FILE NO. 2641
kr
SITE IMPROVEMENT COST ESTIMATE: PHASE2-UTILITIES AND STREET
EST. UNIT EST.
ITEM UNIT QUANTITY PRICE COST
Stabilization fabric SY 4000 1.00 4,000
Aggregate base, Cl. 4, 100% crushed TN 1900 11.00 20,900
Aggregate base, CI. 5, 100% crushed TN 1900 11.00 20,900
Type 31 bit. base course TN 600 32.00 19,200
Type 41 bit. wear course TN 300 35.00 10,500
Bituminous material for tack GL 400 1.00 400
Concrete curb and gutter LF 1910 8.00 15,280
Landscaping LS 0.75 40,000.00 30,000
Concrete walk SF 3000 3.00 9,000
6" DIP LF 160 20.00 3,200
8" DIP LF 980 25.00 24,500
DIP fittings LB 3000 1.00 3,000
6" gate valve & box EA 5 800.00 4,000
8" gate valve & box EA 3 1,000.00 3,000
Hydrant EA 3 1,500.00 4,500
Connect to existing water main EA 2 1,000.00 2,000
12" HDPE storm sewer LF 565 15.00 8,475
12" RCP storm sewer LF 171 25.00 4,275
15" RCP storm sewer LF 405 30.00 12,150
21" RCP storm sewer LF 85 35.00 2,975
21" RCP FES EA 1 1,000.00 1,000
Class III riprap CY 8 50.00 400
Connect to existing storm MH EA 1 1,000.00 1,000
Storm catch basin w/casting EA 7 1,200.00 8,400
Storm catch basin MH w/casting EA 7 1,500.00 10,500
6" PVC sanitary sewer LF 180 15.00 2,700
8" PVC sanitary sewer LF 550 23.00 12,650
Improve pipe foundation LF 550 1.00 550
8"x6" wye EA 1 50.00 50
Sanitary MH w/casting EA 3 1,800.00 5,400
Construct MH over existing line EA 1 3,000.00 3,000
Connect to existing sanitary sewer EA 2 1,000.00 2,000
Remove existing sanitary sewer LF 380 5.00 1,900
Estimated Construction Cost $251,805
+50% Security Deposit 125,903
Total Security Deposit Required $377,708
Sheet 4 of 4
.,., A ('-
i !I
FF
u )/-0v) g O ow 0Yeo��. \�
C
{' 17-- - 1 '3-- 0l 6. ' O0 G0)1-
_
,;, . ,
i\A a\pe COw\10oony 0/1o\ne IAmOQh
Ma-t\- Ate( rrc,:. C:}-y o ro r\t) c;1S� - aLf 9- Li 60 O
;, c ., 6 cocAs 45., 3,h3 - Kui-
r�i. ,
/1/4/it/A i ��r 6 E S 95-z - 465 - 29'/ C
,p4r1 3a.)K tr7 (oa- %5'-'78,X0
---- ,/` F# eta? loses d We
11. Gee a 0\(, 0 gs2 - 2� 9 ( “Z)
11 c,,1 - -�,,ber r- Ocono 95 .2 - 2_(-0--L/600r
il ie,L 0 AiS6.4) quo C y-j---
Ai dtemo/u0 `7 "-2 - 0 it -516_00
i
� L 1/ C.:s 0444i7\) a FGO `< ti
f: �
Le-
1- 7/0 �z, v ,, lig`: 7-/'- r. _ 2, G- 9Z/
a
r
1
il
i t
...
t
PRECONSTRUCTION MEETING
CITY OF ORONO
Orono Senior Housing
BRA File No.: 139-01-000
Plat#2641
December 13, 2001, 9:00 am
Orono City Hall
1. INTRODUCTIONS, SIGN IN SHEET
2. PROJECT INFORMATION
Project Manager:
BRA Inspector: Tom Kellogg, (651) 604-4863, Harlan Olson, (612) 961-5466
Orono Contact:
Plan Sheets:Dated 11-30-01 and any supplemental City comments
Standard Construction Details: City Standard Details, January 2000
3. SCHEDULE: _ j
a. Start date: l �
b. Estimated Completion Date/J� / .
4. INTERIM COMPLETION DATE(S):
a. Grading f CRl d 1D LAS •""'" Gfr/AT-- 10/451
b. Utilities "Y ,t-0P e ^ sf �� ,CO ) t,,c1/
c. Building 0* Z
5. PERMITS/EASEMENTS/FNANCIAL GUARANTEES:
a. Health Department, MPCA, MnDOT
b. MPCA General Storm Water
c. Developer Financial Guarantee
d. Fox Ridge Road Financial Guarantee
•
6. PROJECT COORDINATION:
a. Fox Ridge Road
b. City utilities(water, sewer)
7. PRIVATE UTILITIES:
a. Xcel Energy
b. Reliant Energy
c. Qwest Communications
d. Mediacom
e. Others
8. CONTRACTORS CONTACT PEOPLE&PHONE NUMBERS: need to submit 114,1 / L4)/(/
9. HOURS OF OPERATION: eV �
a. Monday-Friday: 7:00 AM to 8:00 PM
b. Saturdays, Sundays and Holidays: 8:00 AM to 8:00 PM
emoolaikollesikiligiaranialaW
10. SUPPLIERS: need to submit
Orono Ambar Senior Housing Preconstruction Meeting
December 13, 2001 9:00 a.m.
Introductions and Attendance List
Utility Companies
Final Construction Plans
Status of Plan Review
Letter of Credit, LOC Reductions.
Permits MCWD City MNDOT
Personnel
City Engineer, Tom Kellogg
City Building, Inspector Marc Davis
City Building Official Lyle Oman
City Site Inspector Matt Bolterman
Contractor Personnel
24 Hour Contact
Construction Limits
City Testing Required, Tom Kellogg
Project Schedule
Noise Control
I 9C-2- — ?3.5---,g65?)
X41 ?tz•qr-III
DB2
dig