HomeMy WebLinkAboutTemp CO �---- TEMPORARY CERTIFICATE OF OCCUPANCY
City of Orono
Building and Zoning Department
DATE APPROVED: 7/12/2002
SITE ADDRESS 2995 Watertown Rd PLD. 0411723210010
OWNER Tony Eiden BUILDER Tony Eiden
MAILING ADDRESS 4155 Berkshire Lane BUILDING PERMIT.
NO. P03640 DATE ISSUED 06/11/01
THE FOLLOWING ARE NOTED AS INCOMPLETE OR MISSING.THESE MUST BE CORRECTED OR
COMPLETED AND REINSPECTED WITHIN 30 DAYS OR THIS CERTIFICATE WILL BE VOID.
Failure to correct these deficiencies will cause occupancy violation citiations to be issued.
1. Complete Stucco
2. Complete final grading
I hereby agree to make the above corrections and to call.for reinspection within the time allowed.
Owner/Contractor .. •2e-J!e ,� /� Date
START BILLING FOR:
�J
� �tO
Building Official
Friday,July 12,2002 White:Owner/Builder Green:Billing Clerk Yellow:File
TEMPORARY CERTIFICATE OF OCCUPANCY
City of Orono
Building and Zoning Department
DATE APPROVED: 3/15/2002
SITE ADDRESS 2995 North Shore Dr P.I.D. 0411723210010
OWNER Tony Eiden Co BUILDER Tony Eiden Co
MAILINGADDRESS 4100 Berkshire Lan 55443 BUILDING PERMIT:
NO. P03840 DATE ISSUED 06/11/01
THE FOLLOWING ARE NOTED AS INCOMPLETE OR MISSING.THESE MUST BE CORRECTED OR
COMPLETED AND REINSPECTED WITHIN 90 DAYS OR THIS CERTIFICATE WILL BE VOID.
Failure to correct these deficiencies will cause occupancy violation citiations to be issued.
1. Provide address at street 191C `5-02 C;j�
CAJ
2. Provide septic final O�c �-
3. Provide guardrail on north patio
4. Provide final grade
5. Ok for Temporary Certificate of Occupancy for 3 months
I hereby agree to make the above corrections and to call.for reinspection within the time allowed:
Owner/Contractor L,, -e�` / Date 3
START BILLING FOR:
Gr,A, 32(461,1Pr, C 0 -mnyl
Buildi g Official
Friday,March 15,2002 White:Owner/Builder Green:Billing Clerk Yellow:File