HomeMy WebLinkAboutMN wetland Conservation act notice of decision w � �� �'� �
Minnesota Wetland Conservation Act
Notic� of Decisoon
Local Government Unit(LGin Address
Minnehaha Creek Watershed District 18202 Minnetonka Blvd
Deephaven,MN 55391
1.PROJECT INFORMATION
Applicant Name Project Name Date of Application
Spring Hill Golf Club Spring Hill Golf Club Application Number
(Tim Johnson) 11/1/11 Wll-31
(completed
12/5/11)
�Attach site locator map.
T e of Decision:
�Wetland Boundary or Type ❑No-Loss ❑Exemption ❑ Sequancing
❑Replacement Plan ❑Banking Plan
Technicat Evaluation Panel Findin and Recommendation if an :
❑Approve ❑Approve with conditions ❑Deny
Summary(or attach): �
2. LOCAL GOVERNMENT UNTr DECISION
Date of Decision: 2/2/12
�Approved ❑Approved with conditions(include below) ❑Denied
LGU Findings and Conclusions(attach additional sheets as necessary):
A wetland delineation for a project area at Spring Hill Golf Club was performed by Graham
Environmental Services,Inc.(GES)on October 24,2011. The project area is within the parcel located at
1050 Tamarack Drive in Orono(PID#26-118-23-42-0006). The boundary was reviewed in the field on
November 1,2011 by Minnehaha Creek Watershed District(MCWD)staff,with a representative from
GES present.
The project area consists of two geographically separate project areas shown in Figure 3 of the delineation
report. One wetland was found in each project area(Wetland A within the north project area and Wetland
B within the south project area). Wetlands A&B are technically part of the same wetland,which is
classified as DNR Protected Water 27-837W,but are delineated as separate wetlands because of the
separate project areas. Wetland A was identified as a Type 3 shallow marsh,and Wetland B was
identified as a Type 2/Type 3 fresh(wet)meadow/shallow marsh. The boundary of Wetland B was
adjusted slightly during the field review to include more wetland.
The wetland boundaries as fla ed in the field and described in the delineation re ort dated&received
BWSR Forms 7-1-10 Page 1 of 3
December 5,2011 are approved by the MCWD. This decision is valid for five years. A project on this
property may require a permit from the MCWD.
For Re lacement Plans usin credits from the State Wetland Bank:
Bank Account# Bank Service Area County Credits Approved for
Withdrawa](sq.ft. or nearest.O1
acre)
Replacement Plan Approval Conditions. In addition to any conditions specified by the LGU, the
approval of a Wetland Replacement Plan is conditional upon the following:
❑ Financial Assnrance: For project-specific replacement that is not in-advance, a financial
assurance specified by the LGU must be submitted to the LGU in accordance with MN Rule
8420.0522,Subp.9(List amount and type in LGU Findings).
❑ Deed Recording: For project-specific replacement, evidence must be provided to the LGU that
the B�VSR "Declaration of Restrictions and Covenants" and "Consent to Replacement Wetland"
forms have been filed with the county recorder's office in which the replacement wetland is located.
❑ Credit Withdrawal: For replacement consisting of wetland bank credits, confirmation that
BWSR has withdrawn the credits from the state wetland baz►k as specified in the approved
replacement plan.
Wetlands may not be impacted until all applicable conditions have been metl
LGU Authorized Si ature:
Signing and mailing of this completed form to the appropriate recipients in accordance with 8420.0255,
Subp. 5 provides notice that a decision was made by the LGU under the Wetland Conservation Act as
specified above. ff additional details on the decision e�ust,they have been provided to the landowner and
are available from the LGU u on re uest
Name Title
Catherine Bach District Techniclan
Sigaa Date Phone Number and E-mail
2/2/12 (952)641-4504
cbachQ�innehahacreek.org
THIS DECISION ONLY APPLIES TO THE 1VIINNESOTA WETLAND CONSERVATION ACT.
Additional approvals or permits from local, state, and federal agencies may be required. Check with all
appropriate authorities before commencing work in or near wetlands.
Applicants proceed at their own risk if work authorized by this decision is started before the time period
for appeal(30 days)has expired. If this decision is reversed or revised under appeal,the applicant may be
responsible for restoring or replacing all wetland impacts.
This decision is valid for three years from the date of decision unless a longer period is advised by the
TEP and specified in this notice of decision. �
3.APPEAL OF THIS DECISION
Pursuant to MN Rule 8420.0905, any appeal of this decision can only be commanced by mailing a
petition for appeal, including applicable fee,within thirty(30)calendar days of the date of the mailing of
this Notice to the following as indicated;
Check one:
BWSR Forms 7-1-10 Page 2 of 3
� Appeal of an LGU staff decision. Send ❑Appeal of LGU governing body decision. Send
petition and$ 0 fee(if applicable)to: petition and$500 filing fee to:
Minnehaha Creek Watershed District Executive Director
18202 Minnetonka Blvd Minnesota Board of Water and Soil Resources
Deephaven,MN 55391 520 Lafayette Road North
St.Paul,MN 55155
4.LIST OF ADDRESSEES
� SWCD TEP member: Stacey Lijewski—stacey.lijewski@co.hennepin.mn.us
� BWSR TEP member:Lynda Peterson—lynda.petersonQstate.mn.us
❑ LGU TEP member(if different than LGU Contact):
� DNR TEP member:Jack Gleason—john.gleasonQstate.mn.us
� DNR Regional Office(if dit�erent than DNR TEP member):Melissa Doperalsld—
Melissa.Doperalski@state.mn.us
❑ WD or WMO(if applicable):
� Applicant(notice only)and Landowner(if different): Tim Johnson—tim�cQspringhillgc.com
� Members of the public who requested notica(notice only):
Graham Environmental Services(Mike Graham)—mgraham@grahamenvironmental.com
City of Orono(Christine Mattson)—cmattson(a�ci.orono.mn.us
� Corps of Engineers Project Manager(notice only):Melissa Jenny—
Melissa.m.jennyQusace.army.mil
❑ B�VSR Wetland Bank Coordinator(wetland bank plan applications only)
5. MAILING INFORMATION
➢For a list of BWSR TEP representatives:www.bwsr.state.mn.us/aboutbwsr/workareas/WCA areas.pdf
➢For a list of DNR TEP representatives:www.bwsr.state.mn.us/wetlands/wca/DNR TEP contacts.pdf
➢De artment ofNatural Resources Re 'onal Offices:
NW Re�on: NE Region: Central Re 'on: Southern Re '�on,:
Reg.Env.Assess.Ecol. Reg.Env.Assess.Ecol. Reg.Env.Assess.Ecol. Reg.Env.Assess.Ecol.
Div.Ecol.Resources Div.Ecol.Resources Div.Ecol.Resources Div.Ecol.Resources
2115 Birchmont Beach Rd. 1201 E.Hwy.2 1200 Warner Road 261 Hwy. 15 South
NE Grand Rapids,MN 55744 St.Paul,MN 55106 New Ulm,MN 56073
Bemid'i MN 56601
For a map of DNR Administrative Regions, see:htt�://files.dnr.state.mn.us/aboutdnr/dnr reaions.pdf
➢For a list of Corps of Project Managers: www.mvp.usace.atm, .y miUre�rulatorv/dafault.asp?naaeid=687
or send to:
US Army Corps of Engineers
St.Paul District,ATTN: OP-R
180 Fifth St.East, Suite 700
St.Paul,MN 55101-1678
➢For Wetland Bank Plan applications,also send a copy of the application to:
Minnesota Board of Water and Soil Resources
Wetland Bank Coordinator
520 Lafayette Road North
St.Paul,MN 55155
6.ATTAC�IlVI��N1'S
In addition to the site locator map,list any other attachments:
BWSR Forms 7-1-10 Page 3 of 3
v � - � � , � ��^,-- . � r - U - '� l
r _. .----•- � -- -- �`'� ��i4�. . Q � .. �':.yt A �_ r,.. �I,I ' . � 1'
I. �` �j � _ _�' .� I . • _ -- � �;,, �ot��� _•\� � ' ' ' _' � "-ti,G
.�' � �t o_. r ,
, , , �;�-� I a\�� C�-� _�+ _ -y , ' , �� -..�
,.
Q ° ,, g - � . �
__ . �
:o° �. , � ' f ''�,'-� �.,, � -. •�
�
�.
_..- _.__ � ' . , �/`� n . f�p . ` . � `y "E1r.y
i /6 - /� �� . . ..."�.-... — .y!� �- II � •II' ____....�." - .. . - ����,iG03 _ . .. ¢ - '_'
� • '`�
° (J \\ �l�}`'� /( :l007 �EEII IC[l ���`'-�^�'� � •� � _ �/LUd �..�•r-
.. V �' .��7L1% ' I� � _ �f ',� r y..�y�j � � •�� ,5• .�w _.^
• �"� �67 . �0. �� /�� C `-i C� .�� ��'s � - �� -�. /���. � '
. � . - \` .i`�� ,�II�� � ~ /•a* ���nJ �• � � �� . O O \I`..� o
'`ii ( . v ^ ,,.� �^c '` � 1 �
.. • r,�-- ��l i �� )��� T � � 1;Y O . .�/�.�'rT'I � r �. ^t I �. � , • O ��_5 �,__"�i! ( � Q � v
��� � � '.� \�--��� � ( _/
_ � 'p, �� . .. . , r� I� �.��� �, �'�� �,iz
� � Approximate , � �;-, �. I���� .t .i�, � • 25 L_=� �'�_�•� � � �e
,
,
-� , __� Site Location � " '=-`- ___ _ _ ' �
• �r��nFsg e�y _ . F - - . Hni �,
, _
-- -- - n
.:.
.
.
, ; , •- i 3• �f,cn � �:
' �/625 I O 'I. �P
� �,�
i • •
�
/Oa2 :��- — ._'�`_ , �r O � ., . _•'� . - � h'2 +r^. U T / �MOO'.
� �s�' � - � ,e, ,I ,�• �� 1 9B6
—�j, �� • . ���, �: q, �, r ; ' ' �ioo � � , '�' - I'Oao �oo ��i -
` �v Iq � a�1,,. n
�� p kgey� ��.- •,: I �� ` • l�i.%��,,�,,r, ---'�. , l �� ' - r�� k.
• �� � �� � 9ea�: �, i" ,.��� �"�'s!
` _ �'� - I :Cf', • / �I�, =< r: i� ,�` i� M='���-1,
� � /' � �
o / � ,'� � .:�,,,.- � � �d '!'a +` •'" , v.d�"(���' � ,"
. . � l C •� 1 ! S� I� •� O _ — �'Y-\ \\.-�I/ F'� O •� ��(y�� �t�� \\ :'%/ '� 1 V I
.
i
,� t.•�'�' . ��fw r�, ., •� O� 9so 1� .��T ,/� ..'4r� _ ' ia.la
.�� ��� - :�!� �:�o ' � ., - - � ��,�/ ,i .. �o _ _ . '
.♦. -''�� " �:����" ,�.,� . _ � ._._ O '�.
.
, � � . — at�t k
� '� ' � �� �' �I �� � _ ��-!O .L al��� � ,I �G j.tJ� 'R�
,��- -•. - .�. ` �.
� .� �� ,�a _�2�� _, \ �p�` _ ' ._ _-.�� +r � �pO ���} '`"\.. _ r I�I
� b � � �- ,. J.,�a `g
I�/ :I . . _. .�.y� `�'.., - Q .� � �, %-' �'"` ! � ;' J i __ .f� •r GG y.;f .
(. — — —. � �` +,��,�'� ���C e ' � __- �i�, � Ll� ,. �i� • C ,
��r:. a ' .f �� - " ``!�� ,� o u� c� � '�� �;.
s,�� _ ti! o � z'r �y � ,
_, . s�" � ,� Lo A J�°` > � 9� � � - � ( :.
-� �������� � ��� r:.. r��V ,,, ;�i' �� �/ ,� � , ti' .�� � �1, , o' �010a.
�4 � ., �, � �. \ t i�.� � ! .�" l� • '' .l,� � c v ... �o. ��v
� � `_��• ' \ `�...,';-_:,�--`-� �'`--�_---" . � � yp�i E���. � ' ,`/- rt Rrr7
_-+��-- _..�r �:_AA � >�t i a :;���'- ,te�l�lt 1 . ��� �""-4 �1F; • w. �
A
N
Not to Scale
Figure 2. U.S.G.S.
� \ Excelsior Quadrangle
� Spring Hill Golf Club
EOrono, Minnesota
S �
GES Pro�ect No. 2011.036
Graham Environmental Services, Inc.
City of Orono
Spring Hill Golf Club
Wetland Fill Proposal:
A—Wetlands are protected by state law.The purpose of the law is to protect wetlands and to the extent
possible prevent any further loss of wetlands in the state. Any proposed work in wetlands requires a
wetland application.
B—A joint application can be completed and submitted to Minnehaha Creek Watershed District
(MCWD).
C—This application must include identification of the project purpose, a detailed description of the
project and alternatives considered (at least 2 alternatives must be considered in order to meet
sequencing requirements). The application cannot be approved unless the proposed activity complies
with the order of sequencing as follows:
1. Does the project avoid direct or indirect impacts to wetland
2. Does the project minimize impacts
3. Does the project rectify impacts
4. Does the project reduce or eliminate impacts over time
5. Replace unavoidable impacts.
D—The owner must demonstrate why impacts are unavoidable and how unavoidable impacts are being
minimized.These reasons have to be approved by the Technical Evaluation Panel (TEP)which includes
MCWD, Board of Soil and Water Resources(BWSR), Department of Natural Resources(DNR) and the
Army Corps of Engineers (ACOE).
E—If the reasons for impact are accepted,then replacement must be made. MWCD requires that this
replacement be made on site or within the same sub-watershed if at all possible. Replacement required
can be as low as 2:1 (replacement:impact) but as high as 5:1 replacement can be required.
F—Both the impacted wetland and the replacement area require establishment of buffer.This wetland
would probably require a 30 foot buffer.The buffer area has to be marked with signs every 100 feet.The
buffer area and wetland must be protected from future impacts by filing a Deed Restrictions and
Covenant with the County Recorder or a similar document with the MCWD.
This is a summary of the application process. Approval can take up to 60 days from receipt of a
complete application.
725 S�� Rve 1J
Christine Mattson
From: Catherine Bach [cbach@minnehahacreek.org]
Sent: Friday, June 22, 2012 5:24 PM
To: 'Stacey.Lijewski@co.hennepin.mn.us'; 'Peterson, Lynda (BWSR)'; 'Doperalski, Melissa
(DNR)'; 'Jenny, Melissa M MVP'; 'john.gleason@dnr.state.mn.us'; Christine Mattson; 'Tim
Johnson'; Mike Graham
Cc: Steve Christopher
Subject: WCA Sequencing Notice of Decision - Spring Hill Golf Club, Orono
Attachments: W12-04_Sequencing NOD.pdf
Good afternoon,
Please find attached a Wetland Conservation Act Notice of Decision for a sequencing application that was submitted in
preparation for a proposed project at Spring Hill Golf Club in Orono. Please feel free to contact me with any questions.
Thanks,
Catherine Bach
District Technician
Minnehaha Creek Watershed District
18202 Minnetonka Boulevard
Deephaven, MN 55391
Direct: (952) 641-4504
Main Office: (952)471-0590
Fax: 952-471-0682
www.minnehahacreek.org
_�
�i�aN����a c���x
wwTERSMED a15TRiCT
; Think Green- please do not print this email unless necessary
1
r •
t t ,
Minnesota Wetland Consenration Act
No�ce of Decision
Local Government Unit(I,Gi� Address
Minnehaha Creek Watershed District 18202 Minnetonka Blvd
Deephaven,MN 55391
1.PROJECT INFORMATION
Applicant Name . Project Name Date of Application
Spring Hill Golf Club Spring Hill Golf Clnb Application Number
Improvements 3/30/12 W12-04
�Attach site locator map.
e of Decision:
❑Wetland Boundary or Type ❑No-Loss ❑Exemption � Sequencing
��Yieplacement Plan ❑Banking Plan '
Technical Evaluation Panel Findin and Recommendation if an :
�Approve ❑Approve with conditions ❑Deny
Summary(or attach): See attached Technical Evaluation Panel Finding of Fact.
2.LOCAL GOVERNMENT UNTI'DECISION
Date of Decision: 6/21/12
�Approved ❑Approved with conditions(include below) ❑Denied
LGU Findings and Conclusions(attach additional sheets as necessary):
A sequencing application was submitted on March 30,2012 in preparation for proposed project at Spring
Fiill Golf Club in Orono(specifically the parcel�located at 1050 Tamarack Drive). On May 25,2012,the
applicant requested a 30-day deadline extension in order to allow time for the Technical Evaluation Panel
(TEP)to meet with the City of Orono and the applicanYs consultant to discuss the proposed project. A
TEP meeting was held on June 4,2012 to discuss the application,and it was determined that the
application as originally submitted would not be approved and additional information was requested. An
addendum to the original application was submitted on June 20,2012,and the TEP met on June 21,2012
to review the addendum. At the meeting,the TEP determined that the original application and addendum
adequately met sequencing flelcibility requirements and the application is approved. See attached TEP
Finding of Fact. The addendum received on June 20,2012 is also attached. This decision is valid for
three years.
For Re lacemant Plans usin credits from the State Wetland Bank:
Bank Account# Bank Service Area County Credits Approved for
Withdrawal(sq.ft.or nearest.O1
acre)
BWSR Forms 7-1-10 Page 1 of 3
r
Y� �
Replacement Plan Approval Conditions. In addition to any conditions specified by the LGU, the
approval of a Wetland Replacement Plan is conditional upon the following:
❑ Flnancial Asaarance: For project-specific replacement that is not in-advance,�a financial
assurance spe,cified by the LGU must be submitt� to the LGU in accordance with MN Rule
8420.0522,Subp.9(List amount and type in LGU Findings).
❑ Deed Recording: For project-specific replacement, evidence must be provided to the LGU that
tt►e BWSR "Declaration of Restrictions and Covenants" and "Consent to Replacement Wetland"
forms have been filed with the county recorder's office in which the replacement wetland is located. �
❑ Credit Withdrawal: For replacement consisting of wetland bank crodits, confirmation that
BWSR has withdrawn the credits from the state wetland bank as specified in the approved
roplacement plan.
Wetlands may not be impacted until aU applicable conditions have been met!
LGU Authorized Si ature:
Signing and mailing of this completed form to the appropriate recipieuts in accordanca with 8420.0255, �
Subp. 5 providos notice that a decision`was made by the LGU under the Wetland Conservation Act as
�specified above. If additional details on the d�ision exist,they have been provided to the landowner and
are available from the LGU u on uest. �
Name Title
Catherl�ne Bach Diatrict TecLnician
Signa Date Phone Number and E-mail
, 6/�1/12 (952)641-4504
cbach�minnehahacreek.org
THIS DECISION ONLY APPLIES TO THE MINNESOTA WETLAND CONSERVATION ACT.
Additional approvals or permits from local, state, and federal agencies may be required. Check with all
appropriate authorities before commencing work in or near wetlands.
Applicants proceed at their own risk if work authorized by this decision is started before the time period
for appeal(30 days)has eacpired.If this decision is reversed or revised under appeal,the applicant may be
responsible for restoring or replacing all wetland impacts.
This decision is valid for three years from the date of decision unless a longer period is advised by the
. TEP and specified in this notice of decision.
� 3.APPEAL OF THIS DECISION
Pursuant to MN Rule 8420.0905, any appeal of this docision can only be commenced by mailing a
petition for appeal, including applicable fee,within thirty(30)calendar days of the date of the mailing of
this Notice to the following as indicated:
Check one: �
� Appeal of an LGU staff decision. Send ❑Appeal of LGU governing body decision. Send
petition and$0 fee(if applicable)to: petition and$500 filing feo to:
Minnehaha Creek Watershed District Executive Director
18202 Minnetonka Blvd Minnesota Board of Wator and Soil Resources
Deephaven,MN 55391 520 Lafayette Road North
St. Paul,MN 55155
4. LIST OF ADDRESSEES
BWSR Forms 7-1-10 Page 2 of 3
I �
� �
� SWCD TEP member: Stacey L�jewski
� BWSR TEP member:Lynda Peterson
❑ LGU TEP member(if different than LGU Contact): .
� DNR TEP member:Jack Gleason
� DNR Regional Office(if different than DNR TEP member):Melissa Doperalsla
❑ WD or WMO(if applicable):
� Applicant(notice only)and Landowner(if different):Tim Johnson
� Members of the public who requested notice(notice only):
Consultant: Graham Environmental Services,Inc(Mike Graham)
City: ChrisHne Mattson
� Corps of Engineers Project Manager(notice only):Melissa Jenny
❑ BWSR Wetland Bank Coordinator(wedand bank plan applications only)
5.MAILING INFORMATION
➢For a list of BWSR TEP representatives:www:bwsr.state.mn.us/aboutbwsr/workareas/WCA areas.pdf
➢For a list of DNR TEP representatives:www.bwsr.state.mn.us/wetlands/wca/DNR TEP contacts.pdf
➢De artment of Natural Resources Re ional Offices:
NW Re¢ion: NE Region: Central Re i�on: Southern Re►'on:
Reg.Env.Assess.Ecol. Rog.Env.Assess.Ecol. Reg.Env..Assess.Ecol. Reg.Env.Assess.Ecol.
Div.Ecol.Resources Div.Ecol.Resources Div.Ecol.Resources Div.Ecol.Resources -
2115 Birchmont Beach Rd. 1201 E.Hwy.2 1200 Warner Road 261 Hwy. 15 South
NE Crrand Rapids,MN 55744 S�Paul,MN 55106 New Ulm,MN 56073
Bemid'i,MN 56601
For a map of DNR Administrative Regions,see:http://files.dnr.state.mn.us/aboutdnr/dnr roaions.pdf
➢For a list of Corps of Project Managers:www.mvp.usace.armv.miUre�ulatory/default.asn?p�geid=687
or send to:
US Army Corps of Enginears
' St.Paul District,ATTN:OP-R
180 Fifth St.East, Suite 700
St.Paul,MN 55101-1678
➢For Wetland Bank Plan applications,also send a copy of the application to:
Minnesota Board of Water and Soil Resources
Wetland Bank Coordinator
520 Lafayette Road North
St.Paul,MN 55155
6.ATTACHMENTS
In addition to the site locator map,list any other attachments:
�TEP Finding of Fact
� Addendura to original applicntion received June 20,2012
BWSR Forms 7-1-10 Page 3 of 3
1� �
SPUr�
Medina ---:.._. �,�. �
Green
Deer Hil�Rd Oal�Park
�,� z
Approximate "�'t�°r �'�- J
m
Site Location �
�' �' a
�
�
Z � o
� m
� �
� �
6 S
� I� �'_ 6th Avg N� Orona Ptymouth
m -- _ �� �-._-
�a ' ��—_ � � -��—-
w �i c�a ' —:: ,,_�
-� W �{..
�� �. _
Z �
� .n:� ����. � -
� �ior�rd Ra
� x sT m
c �t°� z� �
,, � �� ���,�, L.On3�
`� ,r� �� ��' ' e
Det118(g�, � ��y�_ ��`�,,. �'i(y�
�`` q')
�\ Z �
.:.-..,_.. '� �'
Loeg �_..,�. ,_—r�u��B�. Ohi� �
116 ���""�,, 12.` \1 m
�.�,,.,�,,. :_ �\ �,fe �
Co "'�h��3and P'1988-2006 Microeoft Co oretion and/or ite euY�lfers.All ri hts reserved\ Ra �
A
N
Not to Scale
Figure 1 . Site Location Map
� \
� � Spring Hill Golf Club
r,-+ Orono, Minnesota
S �
GES Pro�ect No. 2012.001
Graham Environmental Services, Inc.
� • �
�. l
� � � � � � �
� � � �
Date:6-22-12 LGU:Minneheha Crcek WD
County:Henne�i�/Carver LGU Contect:Catherine Bach
Project Namo/#: vV 12-Q4 Phone#:952-641-4504
Location of Project: I�v _ �SE 26 118N 23 W �
%, '/+ %. Sec. 'I`uvp. Ranga LotBlock
City: no County:Hennopin
TEP Members(and others)who reviewed project:(Check if vtewed proj�ct site)
�LGU:Catharine Bach �BWSR:Lvnda Peterson
❑SWCD:StaceX Lijewsla ❑DNR(if applicabk):
Other Wetland Experts present:Jesse Struve.Citv of Orono ,
TEP requested by:Catherine Bach
1. Type of TEP determination requested(check those that apply):
Exemption(WCA Exemption#_� NaLoss
Wetland Boundary and Type Replacement Plan
X Sequencing
2. Description of Wetland{s)with proposed impact:
a.Wetland Type(Circular 39),�(Cowardin)PEMC Wetland Plant Community Type'Shallow Marsh
b.Wetland Size 6.52 ac c.Size of Proposed Impact(acres and square feet)To be determined
3. � Have uencing re uirements been met? Attach Sequencing Finding of Fact as supporting information.
� �Yes �No(if no,list why):
4. Ts the project consistent with the intent of the comprehensive local water plan and/or the watershed district plan,the
metropolitan surface water maYa ement lan and metropolitan goundwater managament plan,and local comprehensive
plan and zoning ordinance? [�Yes �]No(if no,list why):
5. What is the net result of the project on the following wetland functions:
F�tnerions e de N�e � �rnove �
Floodwater Storage
Nutriant Assimilation �
Sediment Entrapment
� Groundwater Recharge
Low Flow Augmentation
Aesthetics/Recreation
Shoreland Anchoring
Wildlife Habitat
Fisheries Habitat
� Rare P1andAnimal Habitat
Commercial Uses
6. For replacement plan or naloss determinations,are wetland funcdons maintained at an eqtu�l or greater level?�
❑Yes ❑No(if no,list why)
7_ Doas Technicel Evaluation Panel recommend a roval of the activity proposed in item 1?
�Yes ❑Yas,with Conditions �No(if no,list why):
8. List TEP findings to support recommendation in quostion 7 above.(Please attach documeentt if necessary).The applicant
has minimized the proposed impacts by reducing the impacts originally proposed to both the north and south impact areas. The
applicant has also submitted functional assessments using the MnRAM for the proposed impact sites as well as the proposed
replacement sites. The replacement sites had higher quality values dt functions than the proposed impact sites.
9. ,�NATIJRES((J'TEP recom�nendallon is no!a consensus, ole tiv�l an as�rlsk nd lafn on lhe back of thfaPQBe)
�
. W�!' lJ���� �
Sw ) B xepr�aativo te)
�
L(3 tative ) DNR Repnseotative N�te)
Page 1 of 1 •
Spring Hill Sequeacing TEP FOF (August 200�
, L
1 , � Graham Environmental Services, Inc. S1095 Westland Drive
� � Spring Valley, WI 54767
Phone: 715-778-5730/888-279-2070
����' Fax: 715-778-5867/888-279-2069
Memorandum
TO: Catherine Bach
FROM: Mike Graham�-� �
DATE: June 20, 2012
SUBJECT: Spring Hill Golf Club Sequencing Application
Catherine,
Since our meeting of June 4, 2012 with yourself and other members of the Technical
Evaluation Panel (TEP), we have completed additional information for the TEP's
consideration of sequencing flexibility(Minn. Rules 8420.0520 Subp. 7a) for the wetland
impacts proposed as part of improvements to the 13�' hole at Spring Hill Golf Club.
Specifically, we have completed MnRAM analyses for the entire wetland complex on the
site (referenced as Wetland 15 in old permit documents), the proposed north impact
site, the proposed south impact site, and the proposed on-site mitigation wetland. The
consultant for the wetland bank proposed to be used for the remaining mitigation
requirement has completed a MnRAM analysis for the wetland bank.
Based upon the MCWD's policy of desiring wetland mitigation within the watershed
district, Spring Hill has proposed to provide what mitigation it can on the site which
would be adjacent to the proposed south wetland fill area. Space within the golf course
is limited and, as this would be a wetland "creation", only up to seventy-five percent of
the new wetland area on the site would be eligible for wetland credit and the required
finrenty-five foot average upland buffer(per WCA) would likely qualify for up to twenty-
five percent credit. For these reasons, Spring Hill proposes to purchase approximately
one-half of the required mitigation credit from a wetland bank (see below).
Revised Wetland Imqact
Since our June 4 meeting, Spring Hill has modified its plans which would reduce the
amount of proposed wetland impact in both the north and south fill areas. In the north
fill area, the proposed earthen bridge has been deleted from the plan and the existing
span bridge will be reconstructed or replaced to address the maintenance and safety
issues discussed in GES, Inc.'s March 30, 2012 Sequencing Application document.
Based on preliminary grading plans, the north wetland fill area would cover 15,568
square feet (0.36 acres) as opposed to the 20,600 square feet (0.47 acres) originally
proposed.
. . .
1l� 'n
Spring Hili Golf Club
Sequencing Application Addendum
June 20, 2012
Page 2 of 3
The south fill area has been reduced nearly in half from 10,200 square feet(0.23 acres)
to 5,400 square feet(0.12 acres). The total wetland fill proposed per the revised plans
is 0.48 acres compared to the 0.707 acres originally proposed. A pr+eliminary grading
sketch is shown in Figure 1. In Figure 1, the green shaded areas represerrt where
erosion control fabric would be placed on the sideslopes. The flll areas are those areas
within the heavy dashed black lines and the heavy red lines.
Sequencing Flexibilitv
For this project, the question of sequencing flexibility comes down to two basfc
questions: 1) Is the quality of the wetlands proposed for impact demonstrably degraded
such that m�igation would result in a certain galn in wetland function and value and 2)
Do the mitigation wetlands provide a certain gain in wetland function and value. We
believe that the proposed we�and impact areas are obviously degraded based on their
vegetative composifion and that the MnRAM analysis bears this out. We further believe
that the mi�ga�on wetlands provide clearly higher functions and values and therefore
that flexibility in the sequencing steps is warranted in this case. Please see the
discussion below under"MnRAM Anayses".
On-Site Mitis�ation
The attached Figure 2 shows the approximate area and corifiguration of the proposed
on-site wetland mitigation area. (Please ignore the original wetland flll area note and
hatching). The design of the on-site mitigation wetland would be wet meadow(Type 2)
to avoid having � infested w�h invasive cattails. Although designing for Type 2 will
provide ideal habitat for reed canary grass, a management plan would be developed
and followed to control reed canary grass and other invasives (see add�ional
information under"MnRAM Analyses" below). The exact footprint of wetland and
required upland buffer in this area would be developed at a later date but we believe
that approximately 20,000 square feet of viretland (15.000 square feet at 75%)and
approximately 7,500 square feet of upland buffer(1,875 square feet at 25) could be
developed on-site in this location. This would provide approximately 0.39 acres of the
required 0.96 acres(0.48 x 2) of mitigation cnedit. The mitigation bank wouid be used
for the balance of 0.57 acres.
Off-Site Mitis�ation
The "Heritage Woods" wetland bank(#1410)would be used to provide the balance of
0.57 acres of mitigation credit not provided on-site. This bank has Type 1, 2 and 4
wetland credit,s as well as upland buffer. it is located in the North Fork Crow River
Major Watershed. Spring Hill has had discussions with this bank owner and couid enter
into a purchase agreement to acquire the credits at any time.
Other Wetland Banks Considered
Per the TEP's recommendation at the June 4 meeting, Spring Hill has talked with the
City of Wa�2ata's wetland bank corrtact person. As of the date of this memorandum, it
is not known whether the City is intending to make their credits available for public sale
, ,
ti 1
Spring Hili Golf Club
Sequencing Application Addendum
June 20, 2012
Page 3 of 3
or not. Spring Hill was told that the bank has deposited 15 percent of their credits into
the state bank thus far.
Other banks within the same Major Watershed (20) as the impact site and/or within
Hennepin County were also considered. A total of 14 banks met one, the other or both
of these criteria. Of those 14, two do not have enough credit, three are not for sale to
the public or the ovmer could not be reached, two are not Corps-approved (it is not
known whether the Corps has jurisdiction on the Spring Hill project as of this date), one
is selling for$2.50 per square foot (considered to be outrageously priced), one has just
upland credits (assumed to be a problem for the Corps).
This lea�res four banks that are possibili�es f�or the Spring Hill Golf Club (Banks#1310,
1346, 1410, and 1414). The only one of these banks in the same Major Watersh� as
the project site is#1346 but it only has Type 5 wetland credits available. Although
credits deposited in the state wetland bank have been converted to "Standard Wetland
Credits" (SWC), the preference would be to replace the Type 2/3 wetland impacts with
Type 2 wetlands if possible. This narnows the banks to #1310 and 1410 (Heritage
Woods).
MnRAM Analyses
Please see the attached MnRAM summaries which indicate that the overall wetland
basin as well as the north and south impact areas generally score "Moderate"for almost
every category.
The MnRAM for the on-site mitigation area generally scores moderate to high, primarily
because it would have a managed upland buffer with an average width of 25 feet, would
be protected by a permanent conservation easement and would be managed to score
"High" as a Type 2 fresh meadow for vegetative diversity/integrity. When completing
the MnRAM for this basin, obviously some projection is involved since it is not yet
constructed. Assumptions that were made include: 1)the wetland would be
constructed/maintained as a Type 2 wetland, 2) active management would be done per
a Vegetation Management Plan to maintain the wetland as a "High Qualit�'fresh
meadow, 3) BWSR Mix 34-271 or similar would be used for the wetland, 4) BWSR Mix
35-641 or similar would be used for the upland buffer, 5)the condition of the mitigation
wetland was assumed to be assessed one growing season after the first full growing
season, 6) Lester topsoils in the area of the mitigation site wouid be stockpiled and used
as topdressing — hydric soils from wetland impact areas would not be used because of
reed canary grass and cattail problems.
Piease consider the aforementioned and attached ir�formation as an addendum to our
March 30, 2012 Sequencing Application.
cc: Tim Johnson, Spring Hill Golf Club
Kurt Quaintance, James R. Hill, Inc.
� aan6i� - .__
'f�� •��t t -_.. .. . .- 4
.. ._ ,. l � ' - f�r��. -.
__� . .
- �• Y."l:� :.•i�� _ "� __ � �� _ r ' _
� � � . �� - r . u.. , _ ` ` I . . �;' _ • " •• • .-
' .i .' �:�. '�;` ' A. . _ -! ^ . . .
! .' . `� 1 't• �- � 1 ` I. `" ' . . . �.
\
_.._ . . ' ..1. ^ i. - . . .
. �/ � _ �• � . . �. i- ± � - .. � ., �
� - % . .. . ._ I ' _
_v 'f.� . �. 1`� 'f.' i. .__ ` .. __.. `. ..' \ . _
II' �, � , ( �4''�,•� . .. S•- .
'•� \
.. 1' .. � . ^/• . _ ^ . _ ' _
M 1S( �, , . .��! ' ' ,
�� � r
n �J `
h�,y���y `, �;`
`�•�Q �,�'� �>� _ � . _
� '. � •�
� , , � r� � .
J � \ � ^ � � _ ,� ��E��
� , �' /� �--- f,��, :.,. '='��.�, r
, ��"� , �,\
. �
� i , �;« � .
�_' I � � '✓ ' '` ..
f._ \� 1 ,C gl,�� '�y ' �� � �.s�l
1 �.. �� � . k:`� �� _� ��I • y.+.!a�....«,�
� � �� � � s��� � � �"���+ - �_i-_ i�i� '}�..;� 1
;.t 1 `:� � � \ '�.,... — 'S3+._' �. � . ,,-"rt:��, ` —,„\
� . � �'� �� /��� ,'j� �"�"
-`�.
�,
-v . . ' I ' � ,CL
. � :I t:h\ ;,a`���;�' ,,,��rj 4 r�� �' \\�
_ ' ` \ \� ' m� �r� � �Y 4Y r•. �'�. ..
�� � � � �������� ��'�r�°���,Q����� �' '���-
,
, ', ''`� , �� .
; ,.�`,, � .,�1..
.� , � '�, ��^J '�,`, �V�/ �
� '_- • � i:J'.'.i ` /y4i�`,i,�,Y;_ �/ `
�� . • . r- � I oj• -
� � � � ��g�(� � ��� s' , ,
_.�. ' *�i I ` �I/•a ,'� 1 /.
` ' . .- �/�. � '�� � / .. �
�1�'L. 1�
L: � I //
., .t ;
, -•� � � � ` '��� . � �i
� � � � (
, i � I � �
` �' f� �► ._
- �} \ :� ,
� �'. � y " -;, �
. ".I.. y• ~^ . t' r �"� � .., �,
. `�_ �sy +,`,�. � � �! �'x %i �� J / I
._. .� � � � ir �,_. �� .
. - /, �j �, 1�� �..� � J - ' .
y t t ' i
� � � �{.
..^ ~ -- —. _ ,�'�°t✓,�i` .., �1.��`�d �.. `~� a,� `�
—.� "i�m_�_- —n u ��y - , �'
. �\ -�-- _� ��{T\ .�.�yn +� �t�'�6�1 Z 1 `� - (�
_ -- J �� y...�-� ` ��� .. . .
� j y�� �"' �j{�1� ��.
' , '�.Y� �,/1 �;�d�� ' I
i Y �'��i-,�e
7�y1'
i ��
�� � � I ,� _ J __ - i i �
` � 'A / ��'` i f j � �� —- , I
�
1
7 , A l�,� 1�'L � . � . � :i (A> �U ?t � � � ��- , 1 . � __'
�i / � .��n�. I t � � � - .
�� .. __ .� � �� � ��1 c.7 ���� �� 1 V�����,J.h � � r� � .'�. _
� t a�Jl) , � � � � n � S � /''�
i ' ,.. -- .'� •�. ?L� "— `• 1� '� � � � �
� 'J<;t1.�i ` � � � �!� � 1 �� � ��
r f .r -a- 1 � '+ - � ` \ � t ': , .
�� x C1-;-, �; � !� : ��, �` ���� � � �, � � j � �
�' `� � � � � ,� � O
r{� �� ,: . � 't \ � i1 � .\ -�\ � � , 'ii . _ .
, �
�: ' �
; , � '��
�
, ,
, , i _ l .
� � � .._..c �� � , �, , �.. � �`-.�� � .
/ .._ � �. .i . ,{' � j'� ��� � . .. _ .
. ' � �, � � -_. �
-
\ � ,
_. , ; DELINEATED ��—=_ .�, , . � ._. ' , ,�. � ,
z � WETLAND _ � � , — —
, � � ,
r� �� .�, , ''` � s:ar����arar w � _, � N
,.1 . ,,,
( , , �. . . �+. �. �. :.
. .- if �{1'j�(' (� t � � i r r . � � - �- .
� , a77 �' y�' -_ ���s+ s+ _ a � `1 -
. , .__�
x:� 1 r -' � i � rs _ �r ' '- -,_ __
� , � � . -
� , . _ . ._ -
\ � a� ���a . � � _�
�. � � r �, _ �'
� !. t � �e � � `� '� � - —
� � ��'� ,
-, . _ I ; r °;. ; � � '
� _ ,-
�, \� �,`` b i. ,�� �a� �� - � .. � • ►� � _ l � � ,
\
i
i _ . . ' . .._.
'. \ �. '—' - � � r r . .. �: � , � F .. .. �
: Y � , I • � � � .
� �
,.
+`�`• � ` . !, F � a ', � : ,-' �' �^ �
`\ � �'_,{ -�,. , � � � �`� t \ �� y � ti ��
t�'�` "'ci�'`t2 ,
�,,, ` � . _- � ��•s� '� SCALE IN FEET
- , �.
., � _ ., - .
, ., . , ,
``,' `,� � �� �, � ; � ,, � ��\, l _ w 0 100
, .
. . c
��1 � '` � ! � � �� ��1 y F�i�1 ti � � � �1 -
.s_
� , �
, t ' .
� ; , '_ t_ ' � , 1 inch = 100 feet
;< ?�.�,i ` _ • �'i ��O , � x �` � � ' ' _
.
. : � _ , . �? � , � . , i i ,�
\ ` � �: , -.- ..
;t -��� ' � � i ' � .
, � ��v� � ' ����� -•��
,n .LT `� � � a:i�,: ', ,� _ _ -- ..._
i , . � l t� ,4 .. . ' ! � 1 .�,��/ , ��- ` _
� �-�\". , � . , / . I (l��J� � - ...._ .
_�� � - � � � �,:} i �' �j'///
� _ � , l� V 7}�1 '_
" J: �Q� . k, I 1 I � 4 �� �' .
���,-� - �� ' � ' .
�u'' . �..v � �:�-` i/�i
t
�� '�:<�.� �� � 7��� ! �1 _. �r�j, ��� �� ��
.
� � �
.
, � �
�,
,:
;-
! ' �. � . `.. � ��, ' ' . . � .. '
- ,
, r
� � C�, - t -� . . A _ � �� . �� :� ' f
;
, � �
, �+'�
i ` �
, ,
� l i � ) ) ��
�
� ., . .,__..
t � +
�
`�l
i ��v t i� ` � . \ , - _ _ " i .
,.r' J , , �c3 _ � , ,... �y..�
_ _
, .
,
,
�< - . , - ' �� -
_. , ._. . _. .. -. _ _.=.
� .
. �n � - .. ' ' � :L._t ( �yc�
r� � -
� , �; �� i �_ ` .� _�` � �
i;_.. - { ,� � x� './
�
,. - �
1 �u. �E � �-� � '._
_. � � ��t Figure 2
; ,
,
;
� .
� ; - �. , : ,. _ � �
� ,
�
, , .
,. _ �
� „ � ix _ - � �
, �
MnRAM: Site Response Record
For Wetland:Onsite Wetland (whole bas
Location: 27-118-23-26-001
Onsite Wetland (whole basin)
Plant Community: Shallow Marsh ,f� Commercial crop--hydro impacr NA
Adjacent area slope
Cowardin ClassificaUon: Circular 39: 26_A Genrle 100�0
PEM1Cd Type 3 o Groundwate►�specific questions
26-8 Moderate 0 k
Piant Communfty: Fresh(Wet)Meadow Stee 0°�6 58 Wetland soils Discharge
Cowardin Classiflcatlon: Circular 39: 26-C p - - S9 Subwatershed land use Discharge
PEMBd Type 2 60 Wetland size/soil group Recharge
Q Lisled,rare,specia[species? No 27 pvwnstreamsens./WQprotect A 61 Wet[and hydroperiod ReCharge
62 InledOutlet conftguratlon Discharge
S Rare community or habita�? Na 28 Nutrient loading B 63 Upland lopo relief DisCherge
6 Pre-European-settlemertt condiiion? No
Hydrogeoniorphology/toQography: 29 Shorelinew�etland? No Additionalinformation
� DepressionallTributary Shoreline Wetland 6¢ Restoration porentia! No
30 Rooted veg.,%cover 0% 6S LO affected by res�orotion
$_j Maximum wnter depth 24 inches
8_2 %inundoted 70% 3j Wetland in-wa�er width OI feet � ,
32 Emerg. veg.erosiort resitlance C 66 �rsting size 8
/mmedia�e draina e local WS 20 acres �
9 g 33 Erosion potential ojsite � Restomble sfze �
10 Eslmaled size%xisting site: (see#66) Potentia!new wedartd �l
34 Upslope veg./bank protection �
I/-Upland Soil L22C2-Lester loam 3S Rare wild[ife? No 67 Avemge width of pot.bujfer 0 feet
!!-We�/and Sor/ L24A-Glencoe loam 36 �Qre/Rare/Sl/S2 community No 68 Ease ojpotentia!res�ora�ion
3� Vegetative cover � 69 Hydrologic alterations 0
38 Yeg.community interspersion C 70 Po�en�ial wetland rype 0
39 Wetland detritus ( g 71 Stormwatersensitiviry B
� 71 Additiona!treatment needs B
12 OutletjorJTood control � ¢Q /nterspersion on[andscape C
13 Outlet for hydro regime � 41 Wildlije barriers �� B WaterShed Mississippi(Metro)
14 Dominanl upland land use B I WS# 20 ServiCe Aree: 7
IS We�land soil condieion B I Antphibian-breeding potentia! For funcxional ratings, please run the
1( Vegelation(%cover) 90°/u 42 H1"�roperiod adequacy Adequate �mma tab re
-' Fish resence A ry ��
j� Emerg.vegJ7ood resis[ance � 43 p �J� This report printed on: 6/ZW2012
j$ Sediment delivery B I 44 Overwintering habitat �
19 Upland soils(soil group) B ¢S Wildlije species(l'ut)
Slormwater runo C
20 .l.j`� 46 Fish habi�a[quality C
2 j Subwatershed we[lond density B 47 Fish species Qist)
22 Channels/sheetJlow A I
48 Unique/rare opportuniry No ;
23 Adjacenl bufJ`'er width 15 feet� 49 Weiland visibi/ity C l
Adjacent area management SQ Pro.rimiry�o population No �
24 A Fu!/ 30% S j Public ownership B 1
24-B Mnnicured 70%j S2 Public access _C]
24-C Bare 0% i ,S3 Numan inJluence on wetlnnd B�
Adjacent area diversity/s/ructure S4 fluman inJJuence on viewshed �
25-A Na�ive 20%oJ SS Spa�ialbuJJ'er C
2S-B M�re� 80% .S6 Recrealional acliviry polen[ial C I
2S-C Sparse 0%� -
Wetland Functional Assessment Summary Maln�tnance n�at,u����
oJ Ftood/ Downshrau� oj wuland
Wedand Name H ro somo ho% Hydrologlc SYorniwater/ Wotsr Water Shortllnt
.W� 8 �P SY Reg/ert Attenuallon Qua/Ity QuaU(y p�edloa
Onsite Wetland(whole basin) Depressional/Tribufary(outlet but no perennfal inlet or drainege enterinp from upstream 0.63 0.50 0.53 0.57 0.00
subwatershed)
Moderate Moderate Moderate Moderate Not Applicable
Add�ional Infor�nat�on
Malntuiance oj Matrotsnance of AeslheNcs/ Widand Sensiti►vty Additiona!
Chorocverls�tic MaTptenance of Charocteristic Rec�adae/ Cround- Wd/and to Stonuwata Stormwater
H?ldl�Jb Habl�ar Characterlsdc Awrphiblan Educalloe/ Wats� Restoradon oyd Urban Trtat�wenr
Wa/and Nama Structtere Flsh Habltat Habitot (5�ltwro/ Cowr�nerclarl Uses Intaraclion Potende! p�v�%pment Needs
Onsite Wetland(whole 0.51 0.47 0.38 0.25 0.00 Combination 0.00 0.50 0.57
Disc�targe.
Recharge
Moderate Mo�rate Moderate Law Not A
pplicable Not Applicable Moderate Moderate
Wetland Community Summary _ _ _
� Vegetat�ve Divers�ty/Integr�ty i
� Community l � i Weighted 'i
' lndivutual Highest i Average Average �
; Cowardtn GYrcular lant Wetland Conimunity' WeAiasnuf � Wetland Wetland
�Wetland Name Location CYass�/Icadon 39 omnrunity Propordon Rating Rating � Rating � Ru�tueg i
Onsite WeUand(whole basin) 27-11&23-26-001 L PEM1Cd � Type 3 Shallow Marsh 90 � _0.5 � 0.50 0.30 � 0.46 ��
Moderate Low Moderate
! PEMBd � Type 2 'Fresh(Wet)Meadow 10 0.1 I 0.50 i 0.30 0.46
Moderate Low Moderate �
! 100 I � 0.50 0.30 } 0.46 � [;
�
Q Denotes incomplete calculation data.
Wednesday,June 20,2012 Page 1 of 1
MnRAM: Site Response Record
For Wetland: North Impact Area
Locatio n: 27-118-23-26-001
North Impact Area
Plant Community: Shallow Marsh Adjacent area slope
Cowardin Classiflca6on: Circular 39: 26-A Centle 100% Croundwater-speciJlc questions
PEMCd Type 3 26_B Moderate 0% S8 We�land soils Recharge
26-C Sleep 0% 59 Subwatershed land use DisCharge
¢ Lfsted,rare,specia[speeies? No 6Q We�lond size:soil group Recharge
S Rare community or habitat? No _ 61 Wellond hydroperiod ReCharge
6 Pre-European-set!lement condition? No 27 �wnstreom sens./WQ protect. A 62 InledOul(et configuration Discharge
� 28 Nuvtent loadtng g 63 Upland lopo relief Discharge
Hydrogeomorphology/topognaphy: --
� DepressionallTributary -- Additiona[information
29 Shorefine wetland? NO _ 64 Restoralion potentla[ No
g_j Maximum water dep�h 12���� Shorellne Wetland
8_Z %inundated 70% 6S LO affected by res[oration
j� Rooted veg.,%cover 0%
9 Immediate drainage-local WS 20 acres 31 Wetland in-water width 0 feet 66 Exfstfng size � 0.36
/0 Esimated sizeiexisling site: (see#66J 32 Fmerg.veg.erosion resistance C Res�orab[e size �•�
//_(/p(Q�$�i( L22C2-Lester loam
3 j Erosion potentio!ojsite � Patentia!new wetland ' 7.64
34 Upslope veg./bank protection
I1-Wetland Soil L24A-Glencoe loam � 67 Average width ojpo�.buffer 0 feet
3S Rare wild/ife? C 68 Ease ojpotentia!restomtlon
36 Scare/Rare/SJ/S2 community C 69 yy�(rologic alterations 0
j� Vegetalive cover C 70 Potenlial wedand rype 0
jg Veg.communityinterspenion NA 71 Stormwatersensitiviry 8
12 Outle�forjlood contro[ �
39 Wetland delritus C 72 Additiona[treatmenl needs B
13 Outlel for hydro regime �
40 1n�erspersion on landscape C
14 Dominan�upland land use � B Watershed Missfssippi(Metro)
41 Wildfi e barriers
IS K'e<<and soil condition B f � 20 g��p��; �
16 Vegetation("/cover) 100%'
1� Emerg.veg,�lood resisrance C��� A�nphibian-breeding potenttal For func�ional ratings, please run the
� 42 Hydroperiod adequacy Adequate Summary tab repart.
j$ Sediment deflvery � This report printed on: 6/20/2012
43 Fish presence a
19 Upland soi/s(soil group) �
44 Overwintering habita� �
20 Stormwa�er runoJj C�
2 j Subwalershed wetland density � ¢S Wi(dlije species(!is!)
22 Channels/shee�Jlow � 46 Fish habitat quality C
47 Fish species(list)
23 Adjacent buf)''er width 5 feet
¢$ Unique/mre opporlunity No�
Adjacent area maiiageinent - -
24-A
Ful! �po�a 49 Wetfand visibifity C �
24-B
Manicured gpo/, SO f roximity to populalion No I
24-C
Bare 0% SI Public ownership �
SZ Public access C l
Adjacent area diversity/shucture
S3 Human inJluence on wet[nnd _—B 1
2S A Narive 10% i
S4 Human inJluence on viewshed B
25-8 Mixed 90°h -_
S f Spatial bu,�'er C
15-C Spaise 0%
56 Recrea[ional ac[ivity poren�ia! C
s� Commercinl crop--hydro impac� NA
� I
1 �
� � O � ........ � 0 � a � �
y b � p �` � °a 3 a �'
m � d � ,A�, � q � q ,�T,
` y ^' a � Q � � � a
N O � � Q � n n �
�
t� �
o �
N � �
"A � S h.
N �p � ;� �A l\�
� � � ti,;s � g z O
� w� ° o �w a n v
� rv h t„' � noi �3 � � ° �" �'o� �
..� � �T a i a F'e �' o0
,A,� .� n � � � � �o �' o �
s- ,R,� r— � n `o �d a �
�1 0
� $ �
� N � � �p � � �
� � ; yp � � � �
`� � g q � $ � �
� �r�w � w�
� �� o w�
_ £� n 3 � �
n ag� �� `�
�µ n � a � � ��3 � �t A
� a�� � �
4 a � A: � " a !Q n a
�� � � � �� �
�
�`�; �� �„ � �
� ' m �o � ta �a
� "� °' �' n �z^ � �
� � � �q � s
� r,�
.—ti_ _ � � � � o� � �
kF+�� � � wi Z � \�\ C
�` � r � '�� �
�:.
� � � � 3
_ � o �
�: � o �
o g
$ �
�t"' `° � � o �p�` a
� W � o��
� � � � °3. a
n �
i , � � � Q� �� " "
b
�
� ' S � � ��� �; � ��
� � ' � � � �� �
_—�` a �� o
W ti
o � '� ' �
�
o " � 2 �e o ,��e
� `� � �C 0. � .o c � o� a �
6p .�' A � � g p a s � W �o=
�ti9�
`_ ~ — � Q �a � m� '�� a
�� o � � �� � da �
o � o � � � �� e p � `,a
- — � � , � o �
a � �i o a ,�, � ���a
� 0 3 z� � ti � � �� ��
a o � � � � � �
� o r o '� � � ` ,�
m o � o � � Op II � � �o
0
O � Q � y� a � S � w
� � oa �,� oi
_ _� _._— � Q �� $ � � a ^
�o � a � � �� A � �
oir o � � � ::. �° �L � �.
o� F o � _ � fi
R �e iy,
� — --
1 �
MnRAM: Site Response Record
For WeUand: South Impact Area
Location: 27-118-23-26-001
South Impact Area
Plant Community: Shallow Marsh 57 Commercial crop—hydro impact �NA
Adjacent area slope
Cowardin Classification: Ciroular 39: 16_A �ntle 100°k
PEM1 Cd Type 3 == Groundwate�speciflc questions
26-8 Moderate 0%
Plant Community: Fresh(Wet)Meadow 26_C P �o�o sg We�land soi/s Recharge
Stee
Cowardin Classificatlon: Grcular 39: S9 Subwarershed fand use Discharge
PEMBd Type 2 60 Wetland size/soilgroup Recharge
¢ Listed,rare,special species? No 27 pvwns[ream sens./WQ protect A 61 Wet[and hydroperiod Recharge
s Ra�r communily or habitot? No 28 Nu�rient loading B 62 /nlet/Ou!!e�configura�ion Discharge
63 Upland topo relieJ Discharge
6 Pre-European-settlemen[condition? No
Hydrogeomorphology/topography: 29 Shorelinewetland? No Additiona[inforination
7 DepressionallTributary Shoreline Wetland 64 Restoration potentia/ No
g_j Maxrmum waler depth 12 inches
30 Rooted veg.,%cover 0% 6S LO affec�ed by restomtion
8_2 %inundated gp% 31 Wetland in-water widlh 0 feet
9 lmmediale drainage—[oca!WS 20 acres 32 �erg.veg.erosion resis�ance C 66 ��'��ng size 0.12
33 �'osion potentiol ofsite Restomble size �•�
10 Fsimated size%xistingsi�e: (see#66) � Potential new wet[and L 7.88 i
34 Upslope veg./Gunk proteclion �
/1-Upland Soi! L22C2-Lester loam 35 Rare wildlije? � 67 Average width ojpoL buffer 0 feet
/1-Wet/ond Soil L24A-Glencce loam 36 Scare/Rare/SI/S2 communtty C 68 Ease ojpo�entia!restorntion
37 Vegetative cover � 69 Hydrologic alteralions 0
38 Veg.community in�erspersion C 7� Potentia!wetland rype 0
39 Wetlnnd detri[us � 71 Stormwa[ersensitiviry B
12 Outlet jor flood control B ej� /nterspersion on londreape � 72 Additiona!treatrxen[needs B
13 Outlet jor hydro regime B J 41 Wildlife barriers C Watershed Mississippi(Metro)
j¢ Dominanl upland land use B WS# 20 Service Ares: 7
1 S Wet/and soi!condi�ion � Amphlblan-breeding potenlial
� 42 Hydroperiod adequacy Adequate For functionai ratings, please run the
16 Vegeta[ion(%cover) 90/o Summary tab report.
/� Emerg.vegJlood resislance � 43 F�'h presence a This r rt
epo printed on: 6I20�2012
j$ Sedimentdelivery � 44 �'erwinteringhabi�al �
/9 Upland soils(soil group) � 4S Wildlife species(!is[J
20 Stormwater runoJj � 46 Frsh habi[at quality C
2[ Subwatershed wetland densiry � 47 Fish species(list)
12 Chonnels/sheetJlow �
¢$ Unique/rare opportunity No
Z3 Adjacenl bu./J'er width _ 10 feet 49 We�land visibility �
Adjacent area management SO Proximiry�o population No
24_,4 Fu!! 10% s j Public ownership �
24-8 Manicured 90% S2 Public access �
24-C Bnre 0% ,S3 Hunian inJluence on wetland �
Adjacent area diversity/structttre $q Human inJluence on viewshed �
2S A Nalive 1p% SS SpatialbuJJ'er �
2S-B Miaed gp% 56 Recreationa!ac[iviry potentia! �
2S-C Spmse 0%
Wetland Functional Assessment Summa Malntenance M��,�p��
� of Plood/ Downstrea� oj weMand
Hydrologic Storu�wated Wett� Wattr ShordJnt
Wd/and Nams Hydrogeoiaorpho%gy Rsgtsre Attenuallon Qualiry QuaUty p��aton
South Impad Area Depressional/Tributary(outlet but no perennial inlet or drainage entering from upstream 0.63 0.44 0.53 0.54 0.00
subwatershed)
Moderate Moderate Moderate Moderate Not Applicable
AddiNona!I�'ormation
Male�enance oj Mointananea of AestbeNes/ WeNand Sensltivl;v AddlNona!
Charae�erlsllc Malnfenanee of Charoctedstle Rscnaallon/ Croun� Wdland �o S7torarwata Stormwater
Wl/d/{fe Habl�al CharactarlaNc Amphlbl,n BOucotlon/ Water Rsstorodoa and Uiban Treanaerot
Wetland Name Structurs Flsh Hablfat Hablror Cultwral Comursrclsl Uses lnttrocdon Potentle! pQvslopinenr Needs
South Impad Area 0.45 0.46 0.38 0.20 0.00 Combination 0.00 0.50 0.54
Discharge,
Recharge
Moderate Moderate Moderate Low Not AppNcable Not AppUcable Moderate Moderate
Wetland Community Summary _ _ _ ___ __ __ _—
� VegetaHve Diversity/Integrity - '
Cominunity Weighted
Individua! Highest Average Average
Cowardin GYrcular lant Wetland Community Wetland Wetland Wetland
'Wetland Name Locadon CYpssificalion J� 39 Community Propordon Rating Rating Rating Rating �
South Impact Area 27-118-23-2fr001 � PEM1Cd ; Type 3 1hallow Marsh 70 0.5 0.50 0.30 0.38
_ _ - - --- ---
Moderate � Low i Moderate
PEMBd Type 2 Fresh(Wet)Meadaw 30 0.1 � 0.50 0.�-0.38
Moderate Low Moderate
i 100 I � 0.50 i 0.30 } 0.38 ❑
Q De�:otes incomplete calculation data.
Wednesday,June 20,2012 Page 1 of 1
i r
1 �
MnRAM: Site Response Record
For Wetland:On-Site Mitigation Area
Location: 27-118-23-26-001
On-Site Mitigation Area
Plant Community: Freah(Wet)Meadow AdJacent area slape
Cowardin Class(flcaUon: Circular 39: 26-A Gen��e �% Croundwater�specific questions
PEMBd Type 2 26_B Moderate 50% S$ Weeland soils Recharge
26-C Steep 0% S9 Subwatershed land use Discharge
Q Lrsted,rare,specfalspecies? No 60 Wet[and size/soi[group Recharge
s Rare com�nunity or habitat? No 61 Wetland hydroperiod Recharge
Downs�reomsens./W rotect A 62 InledOutlel confegura[ion ReCharge
6 Pre-European-selllement condition? No 27 Qp — 63 Upland topo relief ReCharge
28 Nuaient loading B
Hydrogeoniorphology/topogrnphy: --
� Depressional/Tributary — Additional injorrnation
29 Shoreline wetland? No
$_j Maxtmum water deplh 0 inches — 64 Resloration potentia! No
%inundated 0% Sho►elJne Wetla�td 6S LO affected by restoratton
8-2 30 Rooted veg.,%cover 0%
9 /mmediate drainage-local WS 20 aCres � -
31 Wedand in-waterwid[h O�feet 66 Extstingsize I 0.5
!0 Esimaled size%xisting site: (see#661 32 Emerg.veg.erosion resistance � Restorable size , 7.5
1!-Upland Soi! L22C2-Lester loam 33 Erarion potential ojsite � PotenUa!new wedand i 7.5
j¢ Upslope veg./bonk protection
11-Wetlond Soi! L22C2-Lester loam 67 Average wid[h ojpot.6q(J'er 0 feet
3s Rare wildlife? � Ease ojpolen�iaf restorallon
36 Scare/Rare/Sl/S2 community No 69 Hydrologic alleratlons 0
j� Vegefative cover NA �� Potentia!wet/and type 0
12 Ou[!et jorJlood con[rof B ,
38 Veg.community interspersion NA �j Stormwarer sensitivity B
13 Outlet for hydro regime g I 39 Wetland detritus C 72 Addittonal trea�ment needs B
J 40 lnterspersion on landscape C
14 Dominant upland land use �
Watershed Mississippi(Metro)
j f Welland soi/condilion g 1 `f 1 Wildlife barriers � W� 20 ServiCe Area: 7
16 �e8e�ation(%cover) 80%J
j� Emerg. vegJlood resistance C I Anrphibiait-breedingpotential For functional ratings, please run the
42 Hydroperiod adequacy Inadequate Summary tab report.
j$ Sediment delivery B I This report printed on: 6/20/2012
¢j Fish presence ❑A
19 Upland soils(soil group) B a
¢¢ Overwinlering habilat
Z� Slormwaler runoJ)'' C �
2 j Subwa�e�shed wet(and densiry � 4S Wildlije species(list)
22 Channels/sheelJlow � 46 Fish habi�a�quality _C
47 Fish species(list)
23 Adjacen�buJjer width 25 feet �
¢$ Unique/rare opporlunity No
Adjacent area niaaagen�ent 49 Wetland visibility �
24-A Fu�1 40%�
o � SQ Proximity to popula(ion No
24_B Manicured 50/o�
24-C
Bare �p% SI Publicowners{�ip �
S2 Public access �
Adjace�et area diversity/structure S3 Human iq/luence on wetland _�
2S A Na�ive 80%i
S4 Human inJluence on viewshed �
2S-B Mixed 10%i
fs Spalia!buJ�"er �
2S-C Sparse 10%I
S6 Recrenliona!nctivity po[entia! �
S7 Commercia!crop--hydro impact NA
Wetland Functional Assessment Summary "'°""�"°"" "'°'"``"°""
of Flood/ Downstrsam ojWedond
Nydrologlc Sltorwrtwatar/ Watsr Waar Shordlne
Wuland Nomr Nydrogaonrorphology Rsglirre Attsnaallon Qwa/hy Qaollry Protectlon
OnSite Mifigation Area DepressionaUTributary(oudet but no perennial inlet or drainage entering from upstream 0.83 0.50 0.54 0.73 0.00
subwatershed)
tibderate Moderate Moderate High NotApplicable
Additlonal Inforn�ation
MaJntrnanca oj Molatsnarocs oj AestheNcs/ Wedand Sensitiviry AddldonaJ
C/+araeterlstic MalKteroanes oj Characterlsttc Reenallon/ Cround- Wd/and to Storerwater Stor�awater
W!!dlife Nabltat Charactsrlsdc AnrphJblan Educalloa/ Woter RestorotJon and Urban Treatnrent
Wet/and Na�e SYrucn�re Flsb Habltat Habltot Cultwro/ ConrNrercid Uaes /ateroclloa PotenBo/ Devdop�nent Needs
On-Site Mitigation Area 0.70 0.48 0.00 0.31 0.00 Rec�arye 0.00 1.00 0.73
High Moderate Not Applicable Low Not Applicable Not Applicable High High
Wetland Community Summary __
Vegetative Diversity/Integrity
Coinmunity Weighted i
I I Individual Highest Average Average
Cowardin CYrcular lant �' Wetland Community Wetland I� WeBand Wetland ,
Wetland Name Location C7ass�/'tcadon 39 Cominunity Propordon Rating Rating � Raiing � Rating
OnSite Mitigation Area 27-11&23-26-001 PEMBd � Type 2 IFresh(Wet)Meadow 100 1 1.00 1.00 1.00
–_ — -- _
High High j High ';
- —
� 100 1.00 � 1.U0 1.00 ! ❑
� ------–- � �
[� Denotes incomplete calculation data.
Wednesday,June 20,2012 Page 1 of 1
Wetland Community Summary
Heritage Woods Wetland Bank
Vegetative Diversity/Integrity
Community Weighted
Wetland Individual Highest Average Average
Size Cowardin Circu/ar lant Wetland Community R'etland Wetland Wetland
Wetland ID Subwatershed (acres) Classifuation 39 Community Proportion Rating Rating Rating Rating
27-119-24-02-001-M Pioneer-Sarah Creek 4.5 PEMA Type 1 Seasonally Flooded Basin 10 1
Watershed
27-119-24-02-001-M Pioneer-Sarah Creek 4.5 PEMB Type 2 Sedge Meadow 40 1
Watershed
27-119-24-02-001-M Pioneer-Sarah Creek 4.5 PEMC Type 3 Shaliow Marsh 30 1
Watershed
27-119-2M02-001-M Pioneer-Sarah Creek 4.5 PUBH Type 4 Deep Marsh 20 1
Watershed
82-028-21-07-0O6-W Pioneer-Sarah Creek 1.460000 PEMA Type 1 Fresh(Wet)Meadow 10 1
Watershed
82-028-21-07-006-W Pioneer-Sarah Creek 1.460000 PEMB Type 2 Wet to Wet-Mesic Prairie 40 1
Watershed
82-028-21-07-0O6-W Pioneer-Sarah Creek 1.460000 PEMC Type 3 Shallow Marsh 30 1
Watershed
82-028-21-07-0O6-W Pioneer-Sarah Creek 1.460000 PUBH Type 4 Deep Marsh 20 1
Watershed
�<�"�
*Denotes incomplete calculation data.
�..��� ���
Tuesday,June l9,2012 Page 1 of I
Wetland Community Summary
Heritage Woods Wetland Bank
Vegetative Diversity/Integrity
Community R'eighted
R'etland Individual Highest Ave�age Average
Size Cowardin Circular Plant R'etland Community R'etland Wetland Wetland
Wetland ID Subwatershed (acres) Classification 39 Community Proportion Rating Rating Rating Rating
27-119-2402-001-M Pioneer-Sarah Creek 4.5 PEMA Type 1 Seasonalty Flooded Basin 10 1
Watershed
27-119-2402-001-M Pioneer-Sarah Creek 4.5 PEMB Type 2 Sedge Meadow 40 1
Watershed
27-119-24-02-001-M Pioneer-Sarah Creek 4.5 PEMC Type 3 Shallow Marsh 30 1
Watershed
27-119-2402-001-M Pioneer-Sarah Creek 4.5 PUBH Type 4 Deep Marsh 20 1
Watershed
82-028-21-07-0O6-W Pioneer-Sarah Creek 1.460000 PEMA Type 1 Fresh(Wet)Meadow 10 1
Watershed
82-02&21-07-006-W Pioneer-Sarah Creek 1.460000 PEMB Type 2 Wet to Wet-Mesic Prairie 40 1
Watershed
82-028-21-07-006-W Pioneer-Sarah Creek 1.460000 PEMC Type 3 Shallow Marsh 30 1
Watershed
82-028-21-07-006-W Pioneer-Sarah Creek 1.460000 PUBH Type 4 Deep Marsh 20 1
Watershed
*Denotes incomplete calculation data.
Tutsday,June 19,2012 Page 1 ojl
�
t � r
�
m a� ~
a �
v r � .�i �
tl
� � a a 4
o � Z Z
��
a � �'
V
�� � � O1
2 S
C
�3 4 �
b �� � a
QCZ� _ _
� �
0
� o
� �� _
�
�
� � ° �
�
w Qq �� � �
� ,� �� _ _
� 'w L �
� �
a n
� � m m
� � �
� �
.� � � �
o �
0 0
.� .�
� .� �
� � � �
� � o 0
� � �
w m �
� � �
.� .�
� �
a n
a n
m m
t t
� rn
� � £
\
� j j
p z v
� �g ��
N
s € o 00
�� �� ���
� � �
�, m� �m
� o� o�
N
ti
O
N
� � ti
� 4 e
q o q ,�
'C! N N
� � N '�
� N m F
Wetland Functional Assessment Summary
Heritage Woods Wetland Bank
Downs�ream Wet[axd
Hydmlogic Flood R'ater R'arer Shoreline
Wetland ID Hydrogeomorpholo� Reglme SYorage Qua/tty Quallty Protedion
27-11&2402-001-M DepressionaUFlow-through(apparent inlet and outlet),Depressional/Flow-through(apparent 0.88 0.83 0.82 0.93 0.00
inlet and outlet)
82-02&21-07-006-W DepressionaUFlow-through(apparent inlet and outlet),Depressional/Flow-through(apparent 0.88 0.88 0.75 0.93 0.00
inlet and outlet)
� ��
Tuesday,June 19,2012 Page 1 ojl
Wetland Functional Assessment Summary
Heritage Woods Wetland Bank
Aevthetics, Ground- Wetland R'etland Stormwoter
Amphibian Recreatlon, Water Restoraaton Stormwater Treatment
Wetland ID R?Id/!fe Habltat Fishery Habitat Habitat Education Co���[ 1Meractlon Potemial SensiJJvity Needs
27-119-2402-001-M High Moderate Low High NotAppiicable Recharge NotApplicable Exceptional High
82-028-21-07-008-W High Nloderate Moderate High NotApplicable Recharge NotApplicabie High High
Tuesday,June 19,201Z Page 1 of 1
t k ►
�
�
�
d
� � o 0 4
� ��y
���
� �
� �� S o
a��
e
o g
=��d o
�� o d
� �4
�
�
� o
� a� m
� � � � � � �
d
Vj � ��� � �
� �
4� �
�
� ��" � g o
0�
V�j � U°
� ,�
�
� 0
e
� � �� � � �
� � o 0
V � � �i i
� � e�W
� �
�
� �j o
:o rci m
� ,tggg,,,,,� o 0
� ��
�
�o`
�
� � �
„C o 0
�
�
�
� � �
� o 0
S
N
�
O
N
5 � O�
T ti
O � �"
q O Q �
ti �
= N N
� � N �
3 N aND �j