Building permit tracking <br />New home 470 Orchard Park <br />2/5/2016 Application <br />2/18/2016 sent to engineering <br />2/26/2016 engineering comments <br />2/29/2016 Comments to builder <br />3/1/2016 Updated survey <br />3/14/2016 Updated comments sent <br />3/28/2016 Grading Plan approved <br />4/1/2016 Building approved <br />5/31/2016 Driveway inspected and <br />approved <br />6/1/2016 Septic approved <br />6/2/2016 zoning approved <br />6/2/2016 Contractor called <br />6/6/2016 Permit issued <br />New home 1380 Orono Lane <br />5/12/2016 MCWD application <br />5/18/2016 Application <br />6/1/2016 comment letter <br />6/1/2016 MCWD permit <br />6/3/2016 revised survey/ hard cover <br />6/9/2016 Building approved <br />6/10/2016 Engineering approved <br />6/10/2016 Zoning approved <br />6/10/2016 Contractor called <br />6/13/2016 Permit issued <br />CC WS <br />Exhibit B <br />17 weeks <br />No MCWD, escrow <br />No access, access need to <br />be improved and <br />approved prior to BP <br />4 weeks <br />Incomplete survey, <br />landscape pla, hard cover <br />calcs, escrow agreement, <br />watershed <br />