Laserfiche WebLink
' Page 14 <br /> Melheny Construction Company, the Progressive Construction <br /> Company and the Beekman Construction Company. The contractor <br /> agreed to send a letter to the city stating that within 30 days <br /> it would have a complete response to the requested change order <br /> with all of the prices outlined therein. � <br /> There then followed a discussion concerning liquidated damages <br /> to be assessed on the project because of the contractor ' s failure <br /> to meet the deadline date of November 15, 1979. Johnson, the <br /> attorney for the contractor, stated that the contractor at this <br /> time wanted to show its good will, get the project completed, <br /> and then discuss the question of liquidated damages. Malkerson <br /> stated that it may make sense for the contractor at this time to <br /> allow the reasons why the contractor tbinks it should not have to <br /> pay liquidated damages . Johnson stated that although under the <br /> contract liquidated damages may be due, he would hope that the <br /> city would not assess liquidated damages because of the weather <br /> in 1979 , and the timing of the contract. Malkerson asked him to <br /> explain both matters. It was then discussed generally that the <br /> bid opening for the contract was on April 27 , 1979 , and that pur- <br /> suant to the terms of the specifications, that if the city wanted <br /> to bind the contractor, the city would have to let the contract <br /> to the contractor by May 27 , 1979 . Malkerson noted that there <br /> had been discussions with various property owners concerning <br /> whether or not to construct the project in 1979, and therefore <br /> there was a possibility that after the bid opening, the city <br /> may not proceed with the project. The City Engineer had spoken <br /> with the contractor and the contractor agreed to extend the nor- <br /> mal thirty day time period to January 12 , 1979, so that the city <br /> could decide to let the contract up and through June 12 , 1979. <br /> The contractor noted that the contract was awarded to the con- <br /> tractor on June 12, 1979 , and the contractor had been asked by <br /> the City Engineer previously to submit a letter to the city con- <br /> firming the oral understanding concerning the extension of the <br /> 30 days through June 12 , 1979 . The city never received such a <br /> letter. After the award of contract on �une 12, 1979 , the city <br /> sent the contract documents to the contractor on June 14, 1979, <br /> and thereafter the contractor executed the documents and provided <br /> the performance bond as required by the contract documents. Aow- <br /> ever, it was agreed by everyone that at no time did the contractor <br /> ask for a change in the contract completion date or in anyway <br /> indicated that he would not then be able to complete the project <br /> as provided for in the contract. In fact, it was noted that the <br /> contractor signed that contract and, therefore, without doubt <br /> bound himself to the November 15, 1979 deadline date. The <br /> engineer and the public works administrator noted that at the <br /> preconstruction conference at which the contractor was present <br /> on June 14 , 1979 , the contractor again said he would have no <br /> problems meeting the completion date of November 15, 1979, and <br /> in fact he expected to complete the project in early October, <br /> 1979 . <br /> ' -2- <br />