Laserfiche WebLink
STORM SEWER POLLUTION PREVENTION PLAN (SWPPP) <br />CRYSTAL BAY ESTATES <br />1. CONSTRUCTION ACTIVITY INFORMATION <br />This SWPPP was prepared by personnel certified in the design of construction SWPPP5. Copies of certifications <br />are available upon request <br />Protect Name: Crystal Bay Estates <br />Project Location; <br />Address :18Old Crystal Bay Road North RECEIVED <br />City; Orono State: Mimheaals Zip Coda : 55358 <br />3. <br />Methods to be used to promate infiltration and aediment removal on the ado priar to discharge <br />• The water quality volume that must be treated by the projects permanent stamlwater managernant system <br />described in Part I11.C. shall be 112 Inch of runoff from the new lmpervima surfaces created by the project. <br />See Part NI.C.2 for more information an infiltration design and appropriate site conditions. if it fa determined <br />that site conditions are not appropriate for Infiltration (e.g. lack cf 3 ft, of Separation to seasonally saturated <br />ground water, proximity to bedrock, contaminated soils) the reasons should be documented to the SWrMWHar <br />Pollution Prevention Plan (SWPPP) for the project. Infiltration is not requited in Hydrologic Soil Group D soils. <br />Clay soils throughout the site resulted in volume reduction being achieved viafilbation shaft in three (3) of the <br />onsite ponds. <br />Timellnes fa be implemented on site for complatma the installation of the erosion prevention BMPs <br />• Prior to Grading - Slit and tree fence to locate grading limits and provide down gradient sedimentcordml. <br />Rack Entrance Berm to be installed. <br />County Parcel ID Number (PID); 3311823340001pUG <br />0 5 O i 6 <br />Grading - Erosion blanket wilt be utilized on ail 3:1 slopes. Biarolls will be used in near yard swales. MnDot <br />CITY PROJECT N0. <br />NRH i a9rdBr15 PE_R_WATE_RSHED OOMMENTS INFORMATION) OF THIS PRODUCT IS STRICTLY PROHIBITED WITHOUT <br />seed mix #250 will be spread at a rate of 100 f iaJacre and fertilize with 20-0-10 at 100 Ibs.lacre. Only <br />Project Typo: Residentlaf CommercialAndustrial Road Construction <br />phosphorus free fertilizer shall be used. <br />Resldgntlal/Road,Construction <br />Other ti�' <br />Utility & Street Work - Inlet protection an all alarm sewer eatehbasins. Weekly street sweeping to puavead <br />Cumulative Impervious Sur ace <br />C O� 4R�{'0 <br />off --site vehicle tracking. However weekly sweeping may not be adequate. Sweeping is required 24 hours <br />Number of acres to be disturbed: <br />5.5 (tenths of an acre) <br />atter discovery attack out. <br />Phe -co drudlon acres of impervious surface: <br />Post oonstruadon aches of impervious surface: <br />2.0 (tenths of an acre) <br />2.1 (tenths of an acre) <br />' permanent BMPs - Sediment bays are to be Installed at fisted end sections draining into dry pond and <br />Total new impervious surface acres: <br />0.1 (tenths ofan acre) <br />infiltration areas. Rip -rap to provide provide energy dissipollon and prevent emsku. <br />Receiving Wil <br />Nameof Water Body Type Special Watw? Impaired Water? <br />Wetland 1 Wetland No No <br />Wetland 2 Wetland No No <br />MinnetankaSlubbs Bay Lake No Yes <br />Dates of Construction <br />Construction Start Dote: September 15, 2016 <br />Estimated Completion Data: November 16, 2016 <br />2. General Construction Project Information <br />Personnel &Training <br />Provide a certified erosion control supervisor in good standing with who is knowledgeable & experienced in the application of <br />erasion prevention & sediment control BMPs. Supervisar ehaR work with the project engineer to oversee implementation of the <br />SWPPP & the installation, Inspection & maintenance of the arceian control BMPs. <br />Provide at lease one certified installer for each contractor or subcontractor that installs erasion control BMPs. <br />Chain or Responsibility <br />Owner! Developer & Contnactarare coparniteas for the National PO lu and Discharge Eleminadan System (NPDES) <br />Consrucion Permit. Contractor fa responsible to comply with all aspects of the NPDES Construction Permit at all dmas unlit the <br />Notice of Termination (NOT) has been filed with the MPCA or transferred to the home builder or another contractor. Contractor <br />will develop a chain of command with all operators on the site to ensure that the SWPPP will be implemented & stay in effect <br />until construction is complete, pts silo has final stabilization S NOT has been submitted to Me MPCA <br />Describe the construction activity <br />This +/- 15.4 acre development will consist of the land development of S single family detached homes, and 1,005 linearteet of <br />streets. Other sail disturbing aclivites will include: hams building, driveway construction, and lot landscaping. This project will be <br />mass graded and constructed in one phase, grading and utilities Willie completed in the fall oF201S. <br />Soil disturbing activides wdl Include: Demolition of the existing structures, Installation of a rock entrance berm, clearing and <br />grubbing, Installation of utllifiesiminor utifides(induding private utilities-gas,mWe,electric, etc..), the installation of silt fence and <br />tree fence prior to grading, the installation of silt fence around The proposed panting areas after the grading Is complete, grading, <br />re -spreading topsoil, and grading restoration which will consist of seeding and mulching all disturbed areas outside of the sheet <br />row. Erosion blanket will also be installed on all 3:1 slopes or greater. Additional erasion blanket maybe used throughout the <br />site. See the Erosion & Sediment Contrd Plan forspeoific locations. <br />3. Temporary Erosion Prevention Practices <br />Describe typos of erosion prevention BMPs expected to be Implemented <br />Parimater Control shall be established around the site & around the base dstockpiles if the stockpilewill remain longarthan 30 <br />days. Perimeter control Is typically established with stltfence which also dennlates ureas not 47 be disturbed. Sill Fence <br />locations are shown an the Grading & Erosion Control plans. Where possible 50Rbuffers shall be maintained around surface <br />waters & werdand. Dual pertmeeer controls shad be Installed if work is to take place within Wit of surface waters 8 watlands. <br />Eroslon blanket will be installed art all &I slapaa. <br />Outing construction <br />a. Stabilization of aff axposed areas must the initiated immediately to limit sail erosion but in no case letter than seven (7) days <br />after the construction activity in that portion of the aite has temponvily or permanency ceased. <br />Once grading is complete, temporary erosion BMPs shall be Installed Immediately (le. bioHafls, erosion blanket, ditch checks, <br />etc). No later than seven (7) days, the permanent stabilization should be In place. <br />b. Temporary sediment basin requjnamenta described in Pan 111.8. 1,5 must be used for cormnmh drainage locations that <br />serve an area with five (5) or more acres disturbed at one time. <br />This project is being constructed in 1 phase. The permanent dry aedimerd basins shall be constructed first and all ort -alta <br />drainage shall he routed to the ponds. The site does not have any concentrated awaleo tat will directly diadhargeati-site <br />List anticipated BMP Quantities <br />• Slit Fence (Before Constrvclial3,615 L.F. <br />• Slit Fence (After Construction) - 300 LF. <br />• Sift Fence for Septic Protection Areas (Before Construction). 2,500 L.F. <br />• Slit Fence for Tree Protection (Hem's Conebuctlan) -1,000 <br />• MNDOT Category 4 Turf Refntiooement Mat -155 S.Y. <br />• Erosion Blanket -750 S.Y. <br />Methods of dissipating velocity along stormwaierconveyance channels? outlets <br />• Rlp•rep will be used at all f eradand structures <br />• Check Dams - installation of check dams or other grade control prautce to ensure shout flow and prevent rifts (far slopes <br />greater than 75 feet with a grade of 3:1 or steeper) <br />Methods to be used for stabilization of ditch and swale wed oertmeters <br />Bfo-rolls shall be used for stabilization of ditches and swalas as shown on the Erasion Car l Plan. <br />Methods to be used for anergy dissipation at pipe outlets <br />Rip -rap will be used at flared -end structures for energy dissipation. See plan for quantities. <br />Additional Erosion Control Prevention Measures to be hnplementod on Site <br />• Erosion Blanket - This blanket wilt be Installed as indicated on the erosion and sediment control plan. 1t will <br />provide slope protection until the turf Is established. For retaining wall construction the grading coMracar will <br />install Erosion blanket an the temporary 1:1 slopes unlit the wall construction can be canplated. <br />• - Bto-rolls - Bto-rolls will be installed In swale areas to help slow rurmf and minimize erosion. <br />• SeedingRastoration-TemporarylPermanent5tabilization (Seeding and Mulching)- Temporary seeding and <br />mulch must be placed on all disturbed sail within 14 days, unless actively being worked ort. All disturbed areas <br />will be restored with 4' to 6' of topsoil. The reatoradon shall begin within 72 hours of the grading completion. <br />The seed mix shall be MNDot Mix No. 250 applied at a rete of 100 Ibshicre and fertilized with 20-0-10 at a rete <br />of 100 be. per acre. The mulch shall be Type 1 and applfed at a rate of 2 tons per acre, disc anchored (with <br />disc blades set nearly straight) immediately after placement. <br />+ Sodding - Two types of sodding will be done with this project. The first Will be for erasion control pxolactian for <br />the streets, after the installation of the curb and the minor utilities the contractor will Install two tows of Bad <br />behind the curb fora temporary erosion protection. The second type of sod will be for the yards once the <br />house construction Is complete. <br />4. Temporary Sediment Control Practices <br />Methods of sediment control BMPs to be implemented on site <br />• Sediment controls for temporary or permanent drainage ditches and sediment basins that are designed as <br />part of a treatment system <br />• Installation of check dams or other grade control practice to ensure sheetfiow and prevent rills (for slope <br />lengths greater than 75 feet with a grade of 3:1 or ateepar). <br />Sediment control practices an all down gradient perimeters prior to land disturbing activities. <br />• Storm drain inlet protection for all Inlets. <br />• Silt fendng or other sediment control surrounding temporarysctl stockpiles. <br />• Minimize vehicle tracking of sediments (e.g,, stone pads, concrete arsteel wash hacks, orequivalent <br />systems). <br />Street sweeping of tracked sediment <br />Methods to be used for dawn gradient perimeter control <br />• <br />Slit Fences- are designed as a temporary sediment barrier consisting of a fillerfabric attached to support <br />pasts. This site has three applications for sift fence. These applications are as follow:1. the Installation of sift <br />fence along the grading limits to protect the wetlands from sediment during the grading and utility construction <br />process, 2. the instaAalion of sill fence around the created ponds and rain gardens atter construction to <br />control the sediment runoff until the turf is established and the development Is completed, & the installation of <br />silt fence surrounding temporary stockpiles. <br />if down gradient BMPs are overloaded (based on frequent failure crexcessive maintenance), additional up <br />gradient BMPs shall be installed to eliminate the overloading. The inspector or contractor shall notify the design <br />engineer to establish appropiate up gradient BMP's or climate any paint load sources. <br />Methods to be used to contain Stockpiles <br />Slit fence- will be used to provide perimeter control around stockpiles. <br />Methods to be sued forstann drain inlet pmtodion <br />• Storm Drain Inlet Protection - Storm drain inlet protection Is a sediment barrier placed around a storm sewer <br />inlet. This structure traps sediment before It enters the storm sewer system. The utilitywntractorwi{I be <br />-squired to install inlet protection per the City's details. <br />• 3utlat Structures and Outlet Protection - There ars wetlands located within & adjacent to this project, as a <br />ssuit outlet structures are proposed to transfer water from the storm water treatment pond to the wetland <br />after treatment. These structures will serve lo provide skimming and rate control. Rip -rap will be placed at <br />the base of all aprons to provide erosion protection by protecting the downstream soils from turbulence and <br />Sigh discharge velocities. <br />Methods to minimize vehicle tracking at construction exita'and shraotswespina activities <br />Temporary Rack Construction Entrance - A rock entrance berth W constructed ofcoarse dean rock installed <br />at the proposed entrance point for all construction vehicles. A detail of the rock entrance berm is shown an <br />the final grading plan. This stone pad provides a tire cleaning mechanism for all vehicles leaving uta site. <br />There Is one entrance for this project. Phase seethe Erosion &Sediment Control Plan for location of rock <br />entrance bene. <br />Street Sweeping - Weekly street sweeping shall be taking place. Howaverweekly sweeping may not be <br />adequate. Sweeping Is required 24 hours afterdiacovery of back out. <br />Methods to be used to minimize soil compaction and preserve top sou (unless Infeasible) on sits <br />• Topsail will be strapped and stockpiled. Grading operations will be performed and held down 0.5' lo ailo wfar <br />topsoil respreed. <br />Measures to be used if Dewatering is required on site <br />• Dowell shall be routed to the sadimamation ponds for treatment before leaving site. See F_malon Control <br />Plan for direction on Dewatering methods. <br />7. Pollution Prevention Mana em cit Measunes <br />Single family lots within Ors overall site will be disturbed on a lot by lot basis as Ids are add & hones are <br />constructed. Home construction shall disturb previously stabilized areas- Typically entire lots will be disturbed <br />as finish grading Is completed. Areas not to be disturbed are typically designated by the use at silt fence. <br />Topsoil shall be preserved by stockpiling with sediment conbul installed around the Perimeter of the stockpile. - <br />Individual lobs under coratmction shad also install vehicle tracking measures ouch as rock entrance berm or <br />atter tracking control BMP to maintain dean streets. Home builders shall be responsible far erosion & sediment <br />control Installation, maintenance, SWPPP Inspection and record keeping for lots under their coretructon. <br />Hame Construction BMP Phasing <br />Protect lot area through use of one or a combination of the following; silt fence, mulch, bio -rolls, rock <br />entrance berm, sad buffers or other approved method. In areas within 501t of surface waters redundant <br />controls shall be installed if a 50ft buffer can not be maintained. <br />install drainage protection on down gradient inlets. <br />Establish staging 1 material storage area & Install temporary sanitary Facilities& supply dumpeters <br />Prevent & manage spills of stored substances <br />Install Rock entrance berm, maintain clears sheets <br />Home Construction <br />Manage & protect stockpiles <br />maintain rock entrance berm & perimeter controls <br />trench, install & conned utilities <br />Continue vertical construction <br />Keep streets clean at all times & maintain inlet protection <br />Fine grad pads, Upon completion of fine grade pads & home construction soils disturbing activities, <br />each lot shall be stabilized with sod, seed, mulch, hydromulch, hydroseed, straw matting or combination <br />there of. Monitor stabilized areas until final stabilization is achieved <br />Maintain clean streets <br />Perimeter & temporary erosion & sediment controls are to remain in place until all up gradient areas <br />have been permanently stabilized. <br />Post Construction <br />Remove silt fence after once final vegetation stabilization is established <br />Remove inlet protection <br />Remove all construction materials & debris from site <br />clean all drainage structures <br />Remove all temporary erosion & sediment control BMPs & stabilize areas left disturbed. <br />File NOT for individual Id <br />5. Permanent Stomtwater Management System <br />Will the project result in one acre or moat; o new Impervious area? -YES <br />tfyea <br />The water quality volume that must be treated by the projects pernanentstomwatermanagement system <br />described In Part III.C. shall be one (1) inch of runoff from the new impandous surfaces created by this <br />project. Where site conditions allow, at least % Inch of the water quality volume must be infiltrated. See Part <br />III.C.2 for more information on infiltration desfgn and appropriate site conditions. ftt is determined that site <br />conditions are not appropriate for infiltration (e.g. lack of 3 fL of separation to seasonalfyeat uraisd ground <br />water, proximity to bedrock, contaminated sails) the reasons should be documented in the Siormwater <br />Pollution Prevention Plan (SWPPP) for the project. Infiltration is rut required in Hydrologic Sal Group D <br />soils. <br />A copy of the Stomhwaer Management Report is available through the owneror engineer upon request. <br />Sail boring and water level map is included In the Shonmxater Management Report <br />6. inspection and Maintenance Activities <br />Identifyindividual res onsfble for installin supervising, irin , ins i and maintains erosion <br />prevention and sediment control BMPs on site <br />The owner, North Oaks Company LLC, will be responsible for the operation and maintenance of lite erosion and <br />sediment control BMPs. He will select individuals who will be responsible for the inspections, maintenance, and <br />repair activities, and for filling out tha inspection and maintenance reports. <br />Rapp Farts HOA will operate and maintain the stormwater ponds. <br />The owner shall keep the SWPPP and all supporting documents for three years after tha Notice of TarmtnaWn <br />(NOT). These documents include, but aren't limited to, the SWPPP Narrative, am/ amendments, Inspection and <br />maintenance records, any stormwater related permits, any permanent operation and maintenance agreements, <br />and calculations for temporary and permanent alla mwater management systems. <br />Procedures to routinely inspect the construction site, including <br />1. Description of retard -keeping requirements and content <br />A maintenancelinapedion report will be mad after each Inspection. A copy of the report will be sent to <br />the City. <br />2. Frequency of Inspecdarrs <br />Once every seven (7) days during active construction and; <br />Within 24 hours after a rainfall event greater than 0.5 inches in 24 hours, and within seven(?) days alter <br />that <br />3. Areas to be inspected <br />The silt fence will be installed prior to any site grading. <br />Only about one half of the site will be exposed at any given time. The grading contractor will be finishing <br />lots as the arts and fills are achieved in accordance with the approved grading plan. <br />• Ali erosion control measures will be inspected every week and following any storm event greater than 0S" <br />in a 24 hour period. <br />• All erosion control measures will be maintained in goad working order. maintenance and repairs. will be <br />initiated within a 24 hour period of the report. Monitoring of all repairs will be done. <br />• Built up sediment will be removed from all silt fence when h has reached one-half of the fence height. <br />• <br />Slit fence will be inspected for depth of sediment, tears, and to see tithe fabric Is somra(y attached to the <br />fence posts, and to sea if the fence posts are firmly in the ground. <br />The pond and in6ltretlon/flOrstion area will be monitored for depth of sediment, and the build up of sediment <br />will be removed at the end of the project, it necessary. <br />• The embankment around the ponds and infiltratiantliltration areas will be inspected far any breeches or <br />erosion scare, over compaction and any repairs needed, will be promptly made. <br />• The seeding and mulching will be Inspected for any bare spots, washouts, and for healthy growth. <br />If site conditions result in a needed erosion or sediment control BMP that is not planned for, the inspector or <br />contractor shall contact the design engineer at Sothre-Sergquist Inc. (882.476.6000) to determine an appropriate <br />plan and BMP to stabilize the affected area. <br />BY I DATE ' REVISIONS USE (INCLUDING COPYING, DISTRIBUTION, ANOXJR CONVEYANCEOF <br />I HEREBY CERTIFY THAT THIS PLAN OR SPECIFICATION WAS <br />- <br />CITY PROJECT N0. <br />NRH i a9rdBr15 PE_R_WATE_RSHED OOMMENTS INFORMATION) OF THIS PRODUCT IS STRICTLY PROHIBITED WITHOUT <br />PREPARED BY ME OR UNDER MY DIRECT SUPERVISION AND THAT 1 <br />0; ; " , <br />#153749 <br />_REVISIONS _- <br />NRH t 09,21116 fi REV_:SION_S_PER CrtY &LASHED COMh&ffs '. SATHRE43ERGQUI8T, INC: s EXPRESS WRITTEN AUTHORIZATION. USE WITHOUT <br />AM A DULY REGISTERED PRC(FES IONAL ENGINEER UNDER THE <br />[ry {�' y �+ INC <br />H T, <br />DO a&ams s PLIU4-C <br />Ott r07117J98 i pt,�fR,`HhN-Z S _ <br />I SAID AUTNOR17ATION CONSTITUTES AN ILLEGITIMATE USE AND SHALL THEREBY <br />INDEMNIFY SATHRE-BERGQUIST,INC. OFALL RESPONSIBILITY. <br />LAWS 917 THE STATE OF MINNESOTA. <br />r I J1 <br />/ j-_' <br />yT - E� 7 t 7J .7 F 4 <br />�" 1605IX1THBROADWAY WAY7RYA,MN.SS%1 (9&)476-MORONO, <br />- <br />SHF ! 07/18/16 " - .- --ounaTCHANCEs - - <br />- <br />SATHRE-BERGQUIST, INC. RESERVES THE RIGHT TO HOLD ANY ILLEGITIMATE <br />USER OR PARTY LEGALLY RESPONSIBLE FOR DAMAGES OR LOSSES RESULTING <br />d .= .' <br />/,__..: �— <br />-- <br />m <br />Y' <br />MINNESOTA <br />�. _ - - - - - - - .. - _ .- - .- - <br />FROM ILLEGiTMATE USE. <br />_ a' <br />= ERARLIE A. WIEMERSLAGE, P.E. c� <br />T _ '- _. <br />Date: 07114!2016 Lic, No. 49189 <br />PSP <br />Prectices for stonage of pesticides, herbicides, insecticides, fertilizers, treatment chemlarl, and tandeca�e <br />matanals <br />Petroleum Products: All onsite vehicles and equipment will be monitored for teaks and receive <br />regular preventative maintenance to reduce the chance of leakage. Petroleum produce will be <br />stored in a dghdy sealed container, which is clearly labeled. Any asphaltsubstances used onsite <br />Will be applied according to the manufacdrrare recommendations. <br />Fertilizers: Fertilizers will be applied only in the minimum amounts as recommended by he <br />manufacturer. Once applied, the fertilizer will be worked into the soil to limit the exposure to <br />stormwater. <br />Paints: All containers will be tightly aeaied and stored when not required for use. Excess palm will <br />not be discharged into the storm sewer system, but will be properly disposed of in accordance with <br />local regulations. <br />Practices for storape and disposal of hazardous materials ortmdc waste <br />All hazardous materials like oil, gasoline and point must be propedysiored. To prevent spills and <br />leaks, secondary containment is necessary for hazardous materials. <br />A leak proof containment facllity shall be used for fuel storage tanks to prevent any leakage Cham <br />lnfiltrating the ground. <br />An effort will be made to store only enough products to do the required job. <br />• All materials stored on site will be stored in a neat and ordedymanner. <br />All products will be kept in theiroriginai container, with the original labels stili attached, unless they <br />are not resealable. <br />• Substances will not be mixed with one another unless recommended bythe manufacturer. <br />Whenever possible all of a product will be used up before disposing of a container. <br />Manufacturers' recommendations for proper disposal will befollowed. <br />The site superintendent will routinely inspect the site to ensure properdisposal of all on site materials <br />Collactim_starel and disposal.of solid waste fn compliance with Minn. R. ch. 7D36 <br />Solid Waste - All trash and construction debris from the site will be collected and deposited in a <br />dumpster. A dumpster will be required for each new home constructed. The dumpstars shall be <br />emptied as necessary. No construction materials shall be buried an site. All amid waste must be <br />disposed of in accordance with the MPCA disposal requirements (Part IV.F.1) <br />Momigarrient of portable kthlets to prevent tipping and disposal of sanitary wastes In accordance with <br />Minn. R. ch. 7040: <br />• Portable on-site sanitary and septa waste shall adequately be provided and maintained throughout <br />the duration of the project <br />• All sonitory sewer waste will be collected from the portable units as required by local reguiations. <br />Spill prevention and responee, for feeling and equipment or Vehicle maintenance: <br />Spill Control Practices - <br />AII spills will be cleaned up immediately after discovery, in accordance with the manufacturers <br />recommended methods. <br />The spill area will be kept Well ventilated. <br />Spoils of to>dc or hazardous materials must be reported to the Minnesota Duty Officer <br />1-800.422-a79B. <br />A log of the spill type, location, data, and time will be created bythe job suporinterhderd. The split <br />prevention plan will be adjusted to include measures to prevent this type of spill from reaacruring. <br />Containment and disposal of vehicle and equipment wash water and crohtb' _ engine degneasing on <br />the site: <br />• A defined and limited area of the site shall be used far textsmet washing of construction vehicles. <br />Washing runoff shall be contained and disposed of In accordance with MPCA. No enema <br />degreasing allowed onsite. <br />Storage and disposal of concrete and other washout wastes so that wastes do not contact the around: <br />A leak proof containment facility shelf be used for all liquid and solid wastes generated by concrete <br />washout operations. Liquid and solid wastes shall not erns in contact with the ground and must be <br />disposed of in accordance with the MPGA <br />7. Final Stabilization <br />Method of Final Stablilizatlon <br />Upon final grading of anygiven portion of the site, final stabilization must be implemented within 14 <br />days of completion. <br />a. Stabilization of all exposed areas must be indfated immediately to Ifmstsoil erasion but in no case <br />later than seven (7) days ager the construction will in that portion of the site has temporarily or <br />permanently ceased. <br />Ono& grading is complete, temporary erosion BMPs shall be Installed immediately (le. bio -rolls, <br />erosion blanket, ditch checks, etc). No later than seven (7) days, the permanent stabilization athould <br />be in place. <br />b. Temporary sediment basin requirements described In Part 111.6.1.5 must be used for common <br />drainage locations that serve an area with five (5) ormore acres disturbed atonsill <br />This project Is being constructed in one phase. The permanent dry sediment: basins shalt be conducted <br />first and all on-site drainage shat be routed to the ponds. The site does not have any cancantreted <br />awales that will directly discharge offsite <br />Procedures for completino final stabilization: <br />• Final stabilization Includes but is not limited to: seed & mulch as described above, Erosion blanket, <br />bio rolls, sad, and after grading silt fence. All perimeter and down gradient slit fence shall be <br />inspected and repaired as necessary. # 3858 <br />TITLE SHEET <br />CRYSTAL L BAY ESTATES SW <br />CHAMBERLAIN CAPITAL, LLC. SW <br />