� <br /> � <br /> MINUTES OF THE <br /> ORONO CITY COUNCIL MEETING <br /> Monday,January 9,2012 <br /> 7:00 o'clock p.m. <br /> (4. FOREST LAKE CHANNEL- CSAH 19 BRIDGE REPLACEMENT, Continued) <br /> Archer stated the Hennepin County Transportation Department is planning to replace the North Shore <br /> Drive bridge over the channel that links Forest Lake to West Arm. Construction is planned for the <br /> summer of 2012. <br /> The bridge was originally constructed in 1928 and has far exceeded both its design and service life. The <br /> current sufficiency rating of the structure is 24.4,which makes the structure structurally deficient and the <br /> worst bridge on Hennepin County's rating system. <br /> Archer displayed some pictures of the bridge and noted that the bridge currently has narrow shoulders and <br /> is located on a curve. In addition,the substructure is canted, there is substantial corrosion on the girders, <br /> and the deck is becoming deteriorated. <br /> Archer indicated the design considerations being looked at are a higher vertical clearance for boat traffic <br /> and a wider structure to accommodate pedestrian and bicycle traffic. Hennepin County Transportation <br /> Department will be attempting to limit the impacts of construction on adjacent property owners, the water <br /> body, and users. Cost is a factor in the design. There are also some steep embankments and existing <br /> utilities that will need to be taken into consideration. Water patrol issues will be addressed during the <br /> construction phase. <br /> The proposed design for the new bridge is a three span concrete slab to allow for maximum boat <br /> clearance and piers that will be placed outside the channel to reduce impacts on boat traffic. As a result <br /> of those improvements,the structure will be lengthened by 32 feet,the roadway approach will be <br /> improved, and some architectural features will be added to the bridge. <br /> There is an open house scheduled for Thursday,January 26. Letters have been sent to the residents of <br /> Forest Lake and other adjacent property owners. The project is currently in detailed engineering and will <br /> need to undergo a federal review process, which is roughly a four week process. Following that review <br /> process,the project will then be put out for bids,with construction anticipated to start sometime in June. <br /> The project should be completed in October. <br /> Archer indicated there will not be many impacts to users before or after construction. During <br /> construction they do anticipate a detour around the north side of Forest Lake along CSAH 151. There <br /> wi(1 be impacts to boat traffic during construction. Archer indicated they hope to have a flag person on <br /> the construction crew to stop boat traffic during certain periods of construction but that they hope to keep <br /> the channel open part of the time. They will maintain channel usage for emergency patrol. The duration <br /> of the detour would be June through October. <br /> Archer noted there is no cost to the City at this time but that the Hennepin County Transportation <br /> Department still has to determine what items will be funded through the federal review process. Archer <br /> stated they hope to have the final plans to Orono Staff sometime in February for comment and then the <br /> City Council would be approving the project following that comment period. <br /> Rahn asked how long the bridge would be closed at any one time to boat traffic. <br /> Archer indicated he is not sure at this time but that the adjacent property owners would be given advance <br /> notice of any closures. They will be avoiding closures on major holidays and weekends. <br /> — ---- T_.__.— Page 2 of 7 — --------__._._.___.____—__ <br />