quest, shall uncover, expose or otherwise make available for <br />observation, inspection or testing as ENGINEER may re- <br />quire, that portion of the Work in question, furnishing all <br />necessary labor, material and equipment. If it is found that <br />such Work is defective. CONTRACTOR shall bear all the ex- <br />penses of such uncovering, exposure, observation, inspection <br />and testing and of satisfactory reconstruction, including com- <br />pensation for additional professional services, and an appro- <br />priate deductive Change Order shall be issued. If', however, <br />such Work is not found to be defective. CONTRACTOR shall <br />be allowed an increase in the Contract Price or an extension of <br />the Contract Time, or both. directly attributable to such un- <br />covering, exposure, observation, inspection, testing and <br />reconstruction if he makes a claim therefor a% provided in <br />Articles 11 and 12. <br />OwnerMay Stop the Work: <br />13.10. If the Work is defective, or CONTRACTOR fails <br />to supply sufficient skilled workmen or suitable materials or <br />equipment, OWNER may order CONTRACTOR to stop the <br />Work, or anv portion thereof, until the cacse for such order <br />has been efiminated; however, this right of OWNER to stop <br />the Work shall nor give rise to any duty on the part of <br />OWNER to exercise this right for the benefit of CONTRAC- <br />TOR or any other party. <br />Correction or Removal of Defective 14'ork: <br />13.11. If required by ENGINEER. CONTRACTOR shall <br />promptly. without cost to OWNER and as specified by EN(iI- <br />NEER, either correct any detecuse Work, whether or not fab- <br />ricated, installed or completed, or, if the Work has been re- <br />jected by ENGINEER, remove it from the site and replace it <br />with nondefective Work. <br />One Year C )rrection Period. <br />1? 12- f within one year after the date of Substantial <br />(:ompletior or such longer period of time as may be pre- <br />scribed by law or by the terms of ans applicable special <br />guarantee required by the Contract Documents or by any spe- <br />cific provision of the Contract Documents, anv Work is <br />found to be defective. CONTRACTOR shall promptly. <br />without cost to (,ANER and in accordance with OWNER'% <br />written instructions. either correct such defective Work, or, if <br />it has peen rejected by OWNER, removc it from the site and <br />replace it with nondefectise Work If CONTRACTOR does <br />nor nrompijv comply with the !erms of such instructions, or in <br />an emergency where delay would :ause serious risk of loss or <br />damage. OWNER may have the detccti%c Work corrected or <br />the rejected Work removed and ---placed, and all direct and <br />indirect costs of such removal and replacement, including <br />compensation for additional professional services, shall he <br />paid by CONTRACTOR <br />.4cCgMffMV of Defective 14 ork: <br />13.13. It, instead of requiring correction or removal and <br />replacement pit defective Work. OWNER land. prior to <br />ENGINEER'% recommendation of final payment, also ENGI- <br />NEER) prefers to accept it. OWNER may do so. In .uch case. <br />if acceptance occurs prior to EN(;INFER's recommendation <br />of final payment, a Change Order shall be issued incorporat- <br />ing the necessary revisions in the Contract Documents, i.iclud- <br />ing appropriate reduction in the Contract Price; or, if the ac- <br />ceptance occurs after such recommendation, an appropriate <br />amount shall tie paid by CONTRACTOR to OWNER. <br />0W.ti'ER Nav Correct Defective Work: <br />13.14 If CONTRACTOR fails within a reasonable time <br />after written notice of ENGINEER to proceed to correct and <br />to correct defective Work or to remove and replace rejected <br />Work as required by ENGINEER in accordance with para- <br />graph 13.11. or if CONTRACTOR fails to perform the Work <br />in accordance with the Contract Documents (including any re- <br />quirements of the progress schedule). OWNER may, after <br />,even dass' written notice to CONTRACTOR, correct and <br />remedy any such deticienc%. In exercising his rights under this <br />paragraph OWNER shall proceed expeditiously To the extent <br />necessary to complete corrective and remedial action. <br />OWNER may exclude CONTRACTOR from all or part of <br />the site. take possession of all or part of the Work, and sus- <br />pend CONTRACTOR's services related thereto, take posses- <br />sion of CONTRACTOR',, tools, appliances, construction <br />equipment and machinery at the site and incorporate in the <br />Work all materials and equipment stored at the site or for <br />which OWNER has paid CONTRACTOR but which are <br />stored elsewhere. CONTRACTOR shall allow OWNER, <br />OWNER's representatives. agents and employees such access <br />to the site as may be necessary to enable OWNER to exercise <br />h,s rights under this paragraph. All direct and indirect costs of <br />C .VNER in exercising such rights shall be charged against <br />CONTRACTOR in an amount verified by ENGINEER, and a <br />Change Order shall be issued incorporating the necessary resl- <br />%ions in the Contract Documents and .' rit,iucrion in the Con- <br />tract Price. Such direct and indirect cows shall include, in par- <br />ticular but without limitation, compensation for additional <br />professional .cry ices required and all costs of repair and <br />replacement of work of others destroyed or damaged by cor- <br />tection. removal or replacement of CONTRACTOR', defec <br />n%c A ork CONTRACTOR shall not be allowed an extension <br />of the Contract Time because of any delay in performance of <br />Hie Work a,tributable to the exercise by OWNER of <br />OWNER',, rights hereunder <br />ARTICLE la —PAYMENTS TO CONTRACTOR AND <br />COMPLETION <br />Schedules. <br />14.1 -Ni least ten ,lass prior to submitting the first Appli- <br />cation for a progress payment. CONTRACTOR .hall texcept <br />as otherwise specified in the General Requirements) submit to <br />ENGINEFR a progress schedulc. a final schedule of Shop <br />Drawing uhmission and whet e .ipplicable a schedule of val- <br />ues of the A ork These schedules shall he satisfactor in form <br />and suhstance to ENGINEER The schedule of values shall in- <br />clude quantities and unit prices aggregating the Contract <br />Price. and shall subdivide the Work into component puts in <br />%uftictem detail to serve as the basis for progress pavments <br />during construction. Upon acceptance of the whedwe of val- <br />ues by ENGINEER, it shall be incorporated into a form or <br />Application for Payment acceptable to ENGINEER <br />