<br />March 18, 1985
<br />City of Orono
<br />Box 66
<br />Crystal Bay, MN 55323
<br />Attn: Mr. John Cerhardson
<br />Re: Our File No. 13918
<br />Crystal Bay Sanitary Sewer Improvements
<br />Dear John:
<br />GA -A R ( w1 P I
<br />A WA Gwd—. P I
<br />1Aoww E % s. P !
<br />Rw Mrd N loon•. P F
<br />*0G &.4—hi, P E
<br />Mime / Swale. P E
<br />lbe.)d C 0wro,d,, P E
<br />Jr— A fk . d.., P E
<br />AluA A Hbe , P f
<br />Ird A I,Nd. P E
<br />Mrhd.I ) A....... P E
<br />Rob", R Plrflr+lr, P E
<br />D..,d (I EOfAwe. PE
<br />CMrAry A &rA,on
<br />I rv, .N Pra.rbAr
<br />Hn4n .M (Abo.
<br />We have reviewed the bids received on the Crystal Bay Sanitary Sewer Improve-
<br />ment Project and would recommend award to A.R.I. Contracting, Inc, for the bid
<br />amount of $691,587.65. We have worked with the low bidder on projects in the
<br />past and feel that he can satisfactorily complete the project.
<br />The following is a summary of all bids received on the project.
<br />ARI Contracting, Inc. $691,587.65
<br />Progressive Contractors, Inc. $692,755.95
<br />Orfei and Sons $693,272.59
<br />Widmer, Inc. $769,380.00
<br />Barbarossa b Sons $797,130.00
<br />Lametti b Sons $840,000.00
<br />Northdale Construction $881,273.50
<br />A.P. Keller Construction $887,755,00
<br />Engineers Estimate $610,000.00
<br />'rhe low bids received were approximately 4 percent over the preliminary report
<br />cost estimate. The following is a compariGon of the low received and the pre-
<br />liminary report cost.
<br />Pre1imina�-Re 4R.L Bid
<br />Sewer Construction $455,550.00 $455,477.15
<br />Contingency (5%) 22,775.00 OZ.) 13,664.32
<br />Street Construction 198,400.00 236,110.50
<br />Contingency (5%) 9,920.00 (3%) 7,083.32
<br />Total Construction $686,645.00 $712,335.29
<br />Legal, Engineering 6 Admin. (25%) 171,655.00 178,083.83
<br />Total Project Cost $858,300.00 $890,419.12
<br />Cost/Unit (83 Units) $ 10,341.00 : 10,727.94
<br />Page 1.