7 <br />SECTION 9 <br />PROGRESS AND COMPLETION OF WORK <br />9.1 NOTICE TO PROCEED <br />The date of commencement of the Work is the date set forth in the Notice to <br />Proceed. If there is no Notice to Proceed, commencement shall be the date of <br />the Contract or such other date as may be established therein. Thereupon, the <br />Contractor shall begin and shall prosecute the Work regularly and without in- <br />terruption, unless otherwise directed in writing by the Owner, with such man- <br />power and equipment as is necessary to complete the Work within the time A <br />stated in the Contract Documents. <br />9.2 CONTRACT TIME <br />�r <br />The Contractor shall completc, in an acceptable manner, all of the Work con- <br />tracted for in the time stated in the Contract Documents, subject only to ex- <br />tension for unforeseeable delays above -.nd beyond the control of the Contrac- <br />tor and his Subcontractors and wit, , their fault or negligence. Notice of <br />the Contractor claim for slich extension shall be given within 15 days of the <br />occurrence of the event giving rise to the claim; otherwise the claim shall be <br />waived, r. <br />9.3 SCHEDULE OF COMPLETION <br />The Contractor shall submit, ac such time as may reasonably be requested by <br />the Engineer, schedules which shall show the order in which the Contractor <br />proposes to carry on the Work, with dates at which the Contractor will start <br />the several parts of the Work and estimated dates of completion of the several <br />parts. <br />9.4 USE OF COMPLETED PORTIONS <br />�4 <br />The. Owner shall have the right to take possession of and use any completed fir + <br />partial.y completed portions of the Work, notwithstanding that the time for <br />completing the entire Work or such portions may not have expired. The OwnG.r <br />will sf:ek to minimize the delay to the Contractor occasioned by the Owner'3 <br />occupancy before Acceptance. <br />9.5 COMPUTATION OF TIME <br />04 <br />f <br />When any period of time is referred to in the Contract Documents by days, it awo <br />shall be computed to exclu he first and include the last dzy of such peri- <br />od, If the last day of c zch period falls on a Saturday o� Sunday cr on a + <br />day made a legal holiday i. the law of the ,appli:able jurisdi.-tion, su..h day <br />shill be omitted from the computation. ar <br />al <br />R � <br />r <br />- 30 - <br />1595a <br />4/91 <br />rr <br />