r <br />III. Sanitary Sewer <br />The proposed sanitary sewer for the Bay Ridge area is shown on Figure 2. From the review of the <br />project site, the routes shown on the figures are recommended from a construction standpoint. <br />The Bay Ridge area would be served by an 8" gravity sewer installed between the existing homes <br />and County Road 1.0 /Shoreline Drive). A lift station would be constructed approximately 250 feet <br />south of Bay Ridge near the intersection of the Hartwood private drive and County Road 15. This <br />location would allow for future service to the Hartwood neighborhood. A 4" forcemain would be <br />installed from the lift station north to County Road 51 (North Shore Drive), west to Bay Ridge Road, <br />then north across North Shore Drive and connect to an existing gravity sewer on Railroad Avenue. <br />An alternate forcemain design is shown on Figure 2. In this option the 4" forcemain would connect <br />directly to an existing MCES forcemain on North Shore Drive. Overall project costs would be <br />reduced slightly however, MCES approval would be required. Cost estimates for the alternate design <br />are presented in the Appendices. <br />An option to locate the sewer system on Bay Ridge Road would not significantly change the cost of <br />the project. This option is not feasible due to property owner opposition. <br />Sewer service for each home would consist of a 4-inch PVC line. Services will be extended toward <br />each home a distance of approximately 20 feet from the wye. The property owners would be <br />responsible for the connection to the service. <br />The project will generally be constructed on private property. The alignment shown on Figure 2 will <br />require permanent and construction easements. <br />Detailed cost estimates for the sanitary sewer improvements are presented in the Appendices. <br />Sanitary Sewer Improvements <br />I