March 31, 2000 Grant application deadline <br />preliminary Grant Approval Completion of plans and specifications and project bidding. <br />8 week duration <br />Grant Agreement Approval Award of contract, mobilization, and order equipment <br />4 week duration <br />Demolition Removals and Earthwork <br />2 week duration <br />Playground and Other Equipment Installation <br />4 week duration <br />• Trail Installation and Site Restoration <br />4 week duration <br />Project Completion <br />14 weeks after approval of grant agreement <br />Project Financing <br />The City of Orono will match 50% of the project construction costs from the Park Dedication <br />Fund account. No project costs will be assessed to the community residents <br />The project engineering and bidding costs will be paid for by the City and not be included in the <br />request for grant funds. The City will be completing the engineering work and project bidding <br />prior to approval of the final grant agreement to expedite construction of the project in order to <br />benefit the area residents sooner.