<br />Prepared By: Reviewed By: A.Carlson Approved By:
<br />
<br />
<br /> CITY OF ORONO MEMORANDUM
<br />
<br />DATE: April 26th, 2021
<br />TO: City Council Members
<br />FROM: City Engineer
<br />RE: 2022 Street Maintenance Project
<br />
<br />1. Purpose. The purpose of this action item is to gain council guidance on planning for the 2022 Street
<br />Maintenance Project.
<br />
<br />2. Background. In order to maintain our city streets the engineering department recommends a portion
<br />of the city’s streets for various pavement preservation activities. Streets are inspected and assigned a
<br />pavement condition index (PCI) rating. The PCI allows street to street comparisons and provides the data
<br />required to conduct street maintenance programming and planning.
<br />
<br />3. 2022 Recommended Streets. For 2022, I recommend taking one of the longer streets and then using
<br />any remaining resources to work on the adjacent or nearby shorter residential streets.
<br />
<br />Road Pavement
<br />Cost
<br />Estimate
<br />Nearby roads that could be
<br />grouped with it
<br />Pavement
<br />Cost
<br />Estimate
<br />Total
<br />Pavement
<br />Cost Estimate
<br />Fox Street (Brown
<br />to Orono Orchard) $ 1,003,800 None- Cost prohibitive $1,003,800
<br />Townline Road
<br /> $ 365,600 $365,600
<br />Ferndale Road
<br />West $ 327,700 Dickenson Street, Orono Lane,
<br />Heritage $ 475,105 $802,805
<br />North Arm Drive
<br /> $ 707,000 North Arm Lane, Dahl, Linden La,
<br />Forest Lake $182,300 $889,300
<br />Willow Drive (Fox
<br />to Brown) $ 575,700 Arbor, Crystal, Prospect, Lakeview
<br />Ave, Briar, Railroad, Spates $ 256,300 $832,000
<br />Old Long Lake
<br />Road $ 385,200 Country Club, Lakeview Terrace $177,200 $562,400
<br />Kelley Avenue
<br /> $ 506,900 Lydiard, Lydiard Cir, Carman $108,600 $615,500
<br />Orchard Park Road
<br /> $ 356,900 Chippewa, Stubbs Bay N, High Lane $ 331,500 $688,400
<br />Partenwood Road
<br />and Lane $ 120,000 West Lake St, Linden Ave, Park Ave,
<br />Oak St., Crestview $ 124,100 $244,100
<br />
<br /> The list above is not exhaustive. There are several other roads in need on maintenance in the
<br />immediate future (PCI <70). These include Kelley Parkway, Fairview Cottage, Birch Ln, Highwood,
<br />Brown N (MSA), Maple Pl, Dakota Ave, Dickey Lake Dr, Fagerness Dr, and Webb St.
<br />
<br />4. Funding. The projects will be funded with a combination of the Pavement Management Fund, Sewer
|