My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
01-08-2018 Council Packet
Orono
>
City Council
>
2018
>
01-08-2018 Council Packet
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
5/24/2019 10:14:12 AM
Creation date
5/24/2019 10:11:09 AM
Metadata
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
108
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
AGENDA ITEM <br />Item No. 8 Date: January 8, 2018 <br />Item Description: Wayzata Blvd (CSAH 112) Phase Two Construction <br />Cooperative Agreement <br />Presenter: Adam T. Edwards Agenda Consent Agenda <br />Public Works Director/City Section: <br />Engineer <br />1. Purpose. The purpose of this item is to gain City Council approve the Cooperative agreement <br />with Hennepin County and Long Lake for the construction and maintenance of the CSAH 112 phase <br />two project. <br />2. Background. Hennepin County intends to improve CSAH 112 from Highway 12 to 6th Avenue <br />in joint effort with Long Lake and Orono. The majority of the project is funded with State Turn <br />Back Funding. The overall project is broken into three phases. Currently we are in the design <br />portion of phase two which includes the stretch of CSAH 112 from Wolf Pointe Trail to Wayzata <br />Blvd West. Phase one is under construction and consists of the portion from Willow Drive to Wolf <br />Pointe Trail. Phase three design is due to commence later this summer and consists of the section <br />from Willow Drive to CSAH 6. The Phase 2 design has been underway since 2016. To guide the <br />design choices a Planning Advisory Committee (PAC) was established with members appointed by <br />each of the two cities, Orono and Long Lake, as well as the County. The PAC provide planning <br />guidance to the design team. In addition a technical advisory committee was formed with <br />engineering representation from each city and the county to work out detailed planning. The <br />planning design followed the base guidance set out in the CSAH 112 preliminary design document <br />which was developed by a similar group of representatives from the two cities and county in 2013. <br />The Phase 2 design is complete. The overall estimated cost of this phase is $ 8,741,849.90. Bids <br />will be solicited this winter with award expected in the early spring. Work on Phase 2 is planned to <br />begin in April of 2018. Long Lake approved the agreement at their December 2017 Meeting. <br />3. Agreement Scope. The agreement lays out the responsibilities and cost participation during the <br />construction process and the maintenance responsibilities upon completion of the project. The <br />agreement once signed binds the parties to the project and associated costs as well as establishing the <br />future maintenance responsibilities. <br />4. Cost. The cost for Orono for Phase Two is $89,182.82 and will be funded from the Community <br />Investment Fund. <br />5. Funding. The project will be funded from the Community Investment Fund. The Capital <br />Improvement Plan (CIP) budgeted $114,300 for Phase Two. <br />6. Review. The attached agreement has been reviewed by the City Administrator, Engineer and <br />Attorney. <br />COUNCIL ACTION REQUESTED: <br />Move to approve the Cooperative Agreement. <br />Exhibit <br />A. CSAH 112 Phase Two Cooperative Agreement <br />Prepared By: <br />Reviewed By: <br />Approved By: 11 <br />
The URL can be used to link to this page
Your browser does not support the video tag.